(Amendment)Amendment 1 - Nuclear power plants - Instrumentation and control important to safety - Hardware design requirements for computer-based systems
Amendment 1 - Nuclear power plants - Instrumentation and control important to safety - Hardware design requirements for computer-based systems
This second, updated edition deals with electrical, thermal and loading characteristics of rotating anode X-ray tubes and X-ray tube assemblies intended for use in medical diagnosis, concerning their behaviour during and after energization.
Amendement 1 - Centrales nucléaires de puissance - Instrumentation et contrôle-commande importants pour la sûreté - Exigences applicables à la conception du matériel des systèmes informatisés
Traite des caractéristiques électriques, thermiques et de charge des tubes radiogènes à anode tournante et des gaines équipées prévus pour l'utilisation dans le diagnostic médical concernant leur comportement pendant et après la mise sous tension.
General Information
Relations
Standards Content (Sample)
IEC 60987 ®
Edition 2.0 2013-02
INTERNATIONAL
STANDARD
NORME
INTERNATIONALE
AMENDMENT 1
AMENDEMENT 1
Nuclear power plants – Instrumentation and control important to safety –
Hardware design requirements for computer-based systems
Centrales nucléaires de puissance – Instrumentation et contrôle-commande
importants pour la sûreté – Exigences applicables à la conception du matériel
des systèmes informatisés
IEC 60987:2007/A1:2013
All rights reserved. Unless otherwise specified, no part of this publication may be reproduced or utilized in any form
or by any means, electronic or mechanical, including photocopying and microfilm, without permission in writing from
either IEC or IEC's member National Committee in the country of the requester.
If you have any questions about IEC copyright or have an enquiry about obtaining additional rights to this publication,
please contact the address below or your local IEC member National Committee for further information.
Droits de reproduction réservés. Sauf indication contraire, aucune partie de cette publication ne peut être reproduite ni
utilisée sous quelque forme que ce soit et par aucun procédé, électronique ou mécanique, y compris la photocopie et les
microfilms, sans l'accord écrit de la CEI ou du Comité national de la CEI du pays du demandeur.
Si vous avez des questions sur le copyright de la CEI ou si vous désirez obtenir des droits supplémentaires sur cette
publication, utilisez les coordonnées ci-après ou contactez le Comité national de la CEI de votre pays de résidence.
IEC Central Office Tel.: +41 22 919 02 11
3, rue de Varembé Fax: +41 22 919 03 00
CH-1211 Geneva 20 info@iec.ch
Switzerland www.iec.ch
About the IEC
The International Electrotechnical Commission (IEC) is the leading global organization that prepares and publishes
International Standards for all electrical, electronic and related technologies.
About IEC publications
The technical content of IEC publications is kept under constant review by the IEC. Please make sure that you have the
latest edition, a corrigenda or an amendment might have been published.
Useful links:
IEC publications search - www.iec.ch/searchpub Electropedia - www.electropedia.org
The advanced search enables you to find IEC publications The world's leading online dictionary of electronic and
by a variety of criteria (reference number, text, technical electrical terms containing more than 30 000 terms and
committee,…). definitions in English and French, with equivalent terms in
It also gives information on projects, replaced and additional languages. Also known as the International
withdrawn publications. Electrotechnical Vocabulary (IEV) on-line.
IEC Just Published - webstore.iec.ch/justpublished Customer Service Centre - webstore.iec.ch/csc
Stay up to date on all new IEC publications. Just Published If you wish to give us your feedback on this publication
details all new publications released. Available on-line and or need further assistance, please contact the
also once a month by email. Customer Service Centre: csc@iec.ch.
A propos de la CEI
La Commission Electrotechnique Internationale (CEI) est la première organisation mondiale qui élabore et publie des
Normes internationales pour tout ce qui a trait à l'électricité, à l'électronique et aux technologies apparentées.
A propos des publications CEI
Le contenu technique des publications de la CEI est constamment revu. Veuillez vous assurer que vous possédez
l’édition la plus récente, un corrigendum ou amendement peut avoir été publié.
Liens utiles:
Recherche de publications CEI - www.iec.ch/searchpub Electropedia - www.electropedia.org
La recherche avancée vous permet de trouver des Le premier dictionnaire en ligne au monde de termes
publications CEI en utilisant différents critères (numéro de électroniques et électriques. Il contient plus de 30 000
référence, texte, comité d’études,…). termes et définitions en anglais et en français, ainsi que
Elle donne aussi des informations sur les projets et les les termes équivalents dans les langues additionnelles.
publications remplacées ou retirées. Egalement appelé Vocabulaire Electrotechnique
International (VEI) en ligne.
Just Published CEI - webstore.iec.ch/justpublished
Service Clients - webstore.iec.ch/csc
Restez informé sur les nouvelles publications de la CEI.
Just Published détaille les nouvelles publications parues. Si vous désirez nous donner des commentaires sur
Disponible en ligne et aussi une fois par mois par email. cette publication ou si vous avez des questions
contactez-nous: csc@iec.ch.
IEC 60987 ®
Edition 2.0 2013-02
INTERNATIONAL
STANDARD
NORME
INTERNATIONALE
AMENDMENT 1
AMENDEMENT 1
Nuclear power plants – Instrumentation and control important to safety –
Hardware design requirements for computer-based systems
Centrales nucléaires de puissance – Instrumentation et contrôle-commande
importants pour la sûreté – Exigences applicables à la conception du matériel
des systèmes informatisés
INTERNATIONAL
ELECTROTECHNICAL
COMMISSION
COMMISSION
ELECTROTECHNIQUE
PRICE CODE
INTERNATIONALE
CODE PRIX J
ICS 27.120.20 ISBN 978-2-83220-626-3
– 2 – 60987 Amend. 1 © IEC:2013
FOREWORD
This amendment has been prepared by subcommittee 45A: Instrumentation and control of
nuclear facilities, of IEC technical committee 45: Nuclear instrumentation.
The text of this amendment is based on the following documents:
FDIS Report on voting
45A/897/FDIS 45A/906/RVD
Full information on the voting for the approval of this amendment can be found in the report
on voting indicated in the above table.
The committee has decided that the contents of this amendment and the base publication will
remain unchanged until the stability date indicated on the IEC web site under
"http://webstore.iec.ch" in the data related to the specific publication. At this date, the
publication will be
• reconfirmed,
• withdrawn,
• replaced by a revised edition, or
• amended.
_____________
2 Normative references
Add the following standards:
IEC 62671, Nuclear power plants − Instrumentation and control important to safety – Selection
and use of industrial digital devices of limited functionality
ISO 2768-1, General tolerances − Part 1: Tolerances for linear and angular dimensions
without individual tolerance indications
ISO 2768-2, General tolerances − Part 2: Geometrical tolerances for features without
individual tolerance indications
ISO 3951-1, Sampling procedures for inspection by variables − Part 1: Specification for single
sampling plans indexed by acceptance quality limit (AQL) for lot-by-lot inspection for a single
quality characteristic and a single AQL
ISO 3951-2, Sampling procedures for inspection by variables − Part 2: General specification
for single sampling plans indexed by acceptance quality limit (AQL) for lot-by-lot inspection of
independent quality characteristics
9 Manufacturing
Replace the existing text with the following new text:
9.1 Quality assurance
9.1.1 Manufacturing may be one phase of the overall safety life cycle (see 4.1 and 4.2).
60987 Amend. 1 © IEC:2013 – 3 –
Where manufacturing is a phase of the overall safety lifecycle then manufacturing activities
shall be included in the hardware quality assurance plan of the overall safety life cycle or, if
not, shall be addressed by a separate manufacturing quality assurance plan (see 4.3).
Manufacturing-related activities during the design process (such as manufacturing
assessments during product qualification) shall be included in the hardware quality assurance
plan of the overall safety life cycle.
Hardware produced during the manufacturing phase, and addressed in this clause, includes
individual modules, sub-assemblies or equipment as a whole.
9.1.2 The primary consideration when defining manufacturing processes to which the quality
assurance plan applies shall be to ensure that the manufacturing does not compromise the
delivery of the safety functions by the product.
9.1.3 Procedures and work instructions shall be established for the manufacturing activities.
These activities include manufacturing processes and their control, inspection and testing,
independent quality surveillance and inspection, identification, handling, packaging, storage
and delivery.
9.1.4 The extent and details of procedures and work instructions necessary for
manufacturing activities shall be defined according to the relative importance of the safety
functions being performed by the hardware components (the intended system Class).
The objectives of the manufacturing activity are:
– to ensure the manufactured items are identical and meet the product description and
specification generated during the design and development phases,
– to ensure the production items meet the requirements demonstrated by the initial model
during the qualification programme.
9.1.5 When the hardware contains components provided by external suppliers, the suppliers
shall be evaluated and selected based on their ability to manufacture and supply these items
in accordance with the design requirements, including the requirements in Clause 9 and
appropriate quality assurance program requirements.
In the case where a programmable electronic equipment component is part of the external
scope of supply, an assessment of the supplier's ability and willingness to support a
successful qualification of the equipment should be performed as part of supplier qualification.
NOTE Specific product selection and qualification criteria may be found, as appropriate, in standards such as
IEC 60880, IEC 61513 or in related sub-tier standards such as IEC 62671 and IEC 62566.
9.1.6 When the designer of the I&C system chooses to outsource any process that affects
product conformity to requirements, control over such processes shall be ensured. The type
and extent of control to be applied to these outsourced processes shall be defined within the
quality management plan.
9.1.7 Criteria for the selection, evaluation and re-evaluation of either external suppliers or
sub-contractors shall be established (e.g. general information such as business areas, scope
of supply, technical capability and manufacturing capacity, quality organization, system and
technical audits, financial health, market behaviour, etc.).
9.1.8 Criteria for selection, evaluation and re-evaluation of external products shall be
established and these criteria shall be based on the requirements of relevant standards (e.g.
IEC 60880, IEC 62671 and/or IEC 62566).
– 4 – 60987 Amend. 1 © IEC:2013
9.1.9 The use of manufacturing processes independently certified to recognised international
standards by accredited bodies is recommended (e.g. the International Register for
Certificated Assessors scheme for ISO 9001).
9.2 Training of personnel
9.2.1 The necessary competence for personnel performing any kind of work involved in the
manufacturing and control activities shall be established, documented and maintained.
9.2.2 If personnel experience, education, and training records do not by themselves fulfil the
requirements of 9.2.1, training or relevant other actions shall be provided to achieve the
necessary competence. The effectiveness of the training and actions taken shall be evaluated
and recorded.
9.2.3 The personnel shall be trained to be aware of the relevance and importance of their
activities and how they contribute to the achievement of the quality and safety objectives. In
addition, appropriate records of education, training, skills and experience shall be established
and maintained.
9.3 Planning and organisation of the manufacturing activities.
9.3.1 As part of the overall project planning (see 4.3), a manufacturing plan shall be
established at the start of the project and shall be kept up to date throughout the project.
9.3.2 Interfaces between different groups involved in the design and development shall be
managed to ensure effective communication, clear definition of and assignment of
responsibility for all aspects of the equipment relevant to the manufacturing process.
9.3.3 Effective arrangements for communicating with customers or inspectors shall be
established to define and schedule manufacturing steps and the associated inspections,
audits or controls.
9.4 Input data
9.4.1 Manufacturing inputs shall be established during the design and development phase in
order to provide appropriate information for purchasing, production and quality controls
including product acceptance criteria.
The input data shall include the following information:
– the need for independence between manufacturing activities and the associated
processes documented formally;
– any requirements for the customer approval of changes during manufacture to the
sourcing of components or manufacturing consumables (e.g. solder);
– any requirements for the customer approval of the substitution during manufacture of
components or manufacturing consumables (e.g. solder);
– any special training as a consequence of the equipment having a nuclear application.
9.4.2 Any requirements specified during the design process which have an impact on the
manufacturing process shall be taken into account. This includes any statutory or regulatory
requirements applicable to the product as well as physical and technical characteristics.
NOTE Commonly used manufacturing standards may be considered based on the safety Class of the functions
being performed by the hardware components. (e.g. ISO and ISA manufacturing standards, NEMA enclosures and
protections standards, fire ratings standards, material processes standards, wiring techniques standards, etc.).
9.4.3 Input documents shall be reviewed prior to initiating purchasing activities and
manufacturing activities. The review shall ensure that product requirements are defined and
that the defined requirements can be met. The findings of the review shall be recorded.
60987 Amend. 1 © IEC:2013 – 5 –
9.5 Purchasing and procurement
9.5.1 Purchasing and procurement process
9.5.1.1 Specific purchase requirements shall be established based upon the effect of the
purchased product on subsequent product realization or the final product. The requirement
shall include a list of documents or access to documents necessary to achieve the
qualification of the equipment.
9.5.2 Procurement process of commercially available components
9.5.2.1 Adequate demonstration or other suitable evidence shall be provided, that all the
equipment components, including electronic components boards and housings meet the
specified requirements (e.g. functionality, environmental withstand, reliability and lifetime).
9.5.2.2 Demonstration shall be provided that the selected components fulfil the expected
characteristics.
The demonstration may be based on:
– data provided by the supplier of the components (nature and results of testing after
manufacture, feedback, results of periodic tests, audits, approvals know-how, etc.),
– or self-established, formalized and documented feedback obtained through checks
performed on successive batches, results of periodic tests conducted on samples, and
operating results (such as operating time, failures of components),
– analysis (e.g. circuit level FMEA), component level operating history assessment, design
quality assurance process and records, previous product/component certifications or
qualifications,
– or results obtained during type test previously performed.
9.5.2.3 Adequate means shall be established to demonstrate the quality of the purchased
component. This quality demonstration shall be commensurate with the safety Class of the
intended function(s) of the component(s).
NOTE 1 Related means can consist of type tests of the component itself or of a sub-assembly including it.
NOTE 2 The expected quality includes the physical behaviour, static and dynamic electrical behaviour, under
normal and extreme environmental conditions as well as the expected reliability.
For programmable electronic equipment, refer to specific product selection and qualification
criteria in IEC 60880 and IEC 61513 and its related sub-tier standards such as IEC 62671, or
IEC 62566 as appropriate.
9.5.3 Procurement process of parts used in the I&C equipment
9.5.3.1 The type and extent of control applied to the supplier and the purchased product
shall be defined and contractually established with the supplier.
When the purchased products consist of programmable electronic components, specific
additional requirements shall be in place to ensure strict configuration management and
version control on hardware and software revisions as per approved qualification and
manufacturing records. Any and all changes shall be reported by the manufacturer and a
safety impact assessment provided.
9.5.3.2 Records of the results of evaluations and any necessary actions arising from the
evaluation shall be maintained.
9.5.3.3 Purchasing information shall describe the product to be purchased, including, where
appropriate:
– 6 – 60987 Amend. 1 © IEC:2013
– technical specification, (e.g. as schematics, drawings, control programs, test programs),
– requirements for approvals (e.g. processes, procedures, product and equipment),
– requirements for qualification of personnel,
– quality management system requirements.
9.5.4 Verification of purchased product
9.5.4.1 Inspection or other activities shall be established and performed to ensure that the
purchased product, including the related expected documentation, meets the specified
purchase requirements (see 4.2 and Clause 7).
9.5.4.2 Where verification at the supplier's premises is intended to be performed, verification
arrangements and verification methods used shall be stated in the purchasing information.
Requirements for preparation and acceptance of factory acceptance test plan(s),
requirements for supervision and witnessing of acceptance testing, and requirements for final
factory surveillance and inspection activities (i.e. to address any previously identified non-
conformance issues and to confirm they have been resolved prior to shipment to site) shall be
established.
9.5.4.3 The verification arrangements shall contain statements related to follow-up and
control steps such as sampling tests, on-site observation or breakpoints.
9.5.4.4 Strict quality control shall be ensured of the incoming goods, including the use of
bonded stores where appropriate. The controls on the incoming goods shall include non-
intrusive controls (e.g. visual inspection) and, where appropriate, intrusive controls, such as
electrical tests and functional behaviour.
9.5.4.5 Dimensional controls and sampling plans for inspection shall conform to those
specified in ISO 2768-1, ISO 2768-2, ISO 3951-1 and ISO 3951-2.
9.6 Production
9.6.1 Control of production
9.6.1.1 The overall manufacturing activity shall be defined in a reference process description
as part of the overall product life cycle.
9.6.1.2 Production shall be planned and carried out under controlled conditions.
Controlled conditions shall include, as applicable,
– availability of information that describes the characteristics of the product,
– availability of work instructions,
– availability of quality instruction,
– use and availability of suitable equipment and tools,
– full traceability of component parts,
– full recording of the dates and personnel involved for each production operation,
– implementation of product release, delivery and post-delivery activities.
9.6.2 Specification and control of production environmental conditions
9.6.2.1 Requirements for the environmental conditions for production and control areas shall
be defined as necessary.
9.6.2.2 Area access conditions such as rights to enter, procedures to follow and clothing to
be worn shall be defined as necessary.
60987 Amend. 1 © IEC:2013 – 7 –
9.6.2.3 Control plans for the environmental conditions of, and the access control to, the
manufacturing facilities shall be established (e.g. dust in the atmosphere, creating an inert
atmosphere, humidity or temperature regulation, control of chemical composition of water,
control of electrostatic discharges).
9.6.3 Validation of processes for production
9.6.3.1 Specific processes for production provision shall be validated where the resulting
output cannot be verified by subsequent monitoring or measurement and where, as a
consequence, deficiencies become apparent only after the product has been in use or
delivered.
9.6.3.2 Validation shall demonstrate the ability of these processes to be robust in order to
achieve planned and repeatable results.
Arrangements shall be established for these processes including, as applicable:
– defined criteria for review and approval of the processes,
– approval of equipment and qualification of personnel,
– use of specific methods and procedures,
– requirements for records and validation,
– handling of defective parts including possible consequences for the production process.
9.6.4 Assessment of the manufactured I&C equipment acceptance and reproducibility
9.6.4.1 The equipment produced shall be assessed and stated to be accepted by the
customer.
9.6.4.2 The acceptance shall be based on the quality assurance management, the overall
hardware qualification process and successful qualification results of the component, modules
or equipment which usually are the first of a kind.
9.6.4.3 The designer of the I&C system shall be deemed able to reproduce series equipment
identical to the qualified hardware either by means of internal manufacture and assembly, or
by means of sub-contract manufacture and assembly.
9.6.4.4 The evaluation of manufacturing should be based on surveys focusing on the I&C
system manufacturer's organization and the technical means to manufacture the products.
9.6.4.5 When changes occur after the qualification of the initial item, an impact analysis
shall be performed by the designer of the I&C equipment and conclusions shall be evaluated
to decide if a new qualification has to be done or if the results of the previous qualification
remain unchanged.
9.6.5 Control of production tools, monitoring and measuring devices
9.6.5.1 The tools necessary to manufacture the product shall be determined.
9.6.5.2 Monitoring and measurement processes to be undertaken on the product shall be
determined to provide evidence that the product conforms to its requirements.
9.6.5.3 Processes shall be established to ensure that production, monitoring and
measurement are carried out in a manner that is consistent with the production, monitoring
and measurement requirements.
9.6.5.4 Where necessary to ensure valid results, tools and measuring devices shall:
– 8 – 60987 Amend. 1 © IEC:2013
– be calibrated or verified, at specified intervals or prior to use, against measurement
standards or established basis used for calibration or verification which are recorded;
– be adjusted or re-adjusted when necessary;
– have identification in order to determine their calibration status;
– be safeguarded from adjustments that would invalidate the measurement result;
– be protected from damage and deterioration during handling, maintenance and storage.
9.6.5.5 Quality assurance processes shall ensure that if manufactured equipment is found
not to conform to requirements due to faults in the manufacturing process that adequate
corrective action is taken.
9.6.5.6 Records of the results of calibration and verification shall be maintained.
9.6.5.7 When software based devices are used in the monitoring and measurement
activities, the ability of the device to satisfy the intended application shall be confirmed. This
shall be undertaken prior to initial use and reconfirmed as necessary.
NOTE Confirmation of the ability of computer software to satisfy the intended application would typically include
its verification and configuration management to maintain its suitability for use.
9.6.6 Identification and traceability
9.6.6.1 The manufactured system shall be identified, as well as the parts and materials used
to manufacture the system, by suitable means throughout product realization.
9.6.6.2 The manufactured system status shall be monitored throughout the overall
production process.
9.6.6.3 A unique identification of the system, and of the included parts, shall be ensured and
records of changes shall be maintained for traceability purposes.
9.6.6.4 An identification file shall be established for each equipment and/or subassembly in
order to define the reference model including the description of the equipment, the internal
assemblies, components and versions. These files may typically include a list of sub-
assemblies, plans, drawings, diagrams, data sheets, references to sub-tier detailed files in
order give an exhaustive description of a version of the system and/or sub-assemblies.
9.6.7 Preservation of product
9.6.7.1 The system, and the included parts, shall be preserved during internal processing in
order to maintain conformity to requirements. Preservation shall include identification and as
applicable, handling, packaging, storage and protection conditions given before the
acceptance test of the equipment.
9.6.8 Sustainability of tools and skills
9.6.8.1 Requirements for the maintenance of tools and other means used during the
manufacturing, testing, and validation activities shall be defined during the planning of the
manufacturing activity and commensurate with the safety class of the functions being
performed by the components.
9.6.8.2 Requirements shall be defined for maintaining the skills involved in manufacturing,
validation and testing activities.
60987 Amend. 1 © IEC:2013 – 9 –
9.6.9 Resolution and control
...








Questions, Comments and Discussion
Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.
Loading comments...