The present document defines measurement and monitoring of power, energy and environmental parameters for ICT equipment in telecommunications or datacenter or customer premises.
It defines the power, energy and environmental parameters monitoring interface of ICT equipment based on generic ETSI ES 202 336-1 [1] interface so that correlations can be made with ICT equipment parameters (traffic, flowrate, number of connected lines, radio setting, QoS KPI, etc.) in the network management system.
Correlations of monitored data (power, energy consumption and environmental values) with the ICT equipment parameters and settings are not in the scope of the present document.
The monitoring interface covers:
• Internal power consumption measurement on the ICT equipment powered in DC and AC.
• Power consumption measurement external to the ICT equipment (if not implemented internally, e.g. legacy equipment).
• Energy metering based on power consumption measurement.
• Environmental parameters of the ICT equipment (e.g. temperature at air inlet of equipment). The present document defines:
• The minimum set of exchanged information required at the interface, including parameters such as measurement type (e.g. RMS), accuracy, range, etc. and settings such as data acquisition and transmission period, etc. This includes the data preparation, recording and transmission functions.
• The testing method of some parameters and functions.
• Text tables in annexes A and B with data exchange described in "natural language".
• The XML files with tags and variables corresponding to the data in the tables of annexes A and B in complement to general rules defined in ETSI ES 202 336-1 [1] and ETSI ES 202 336-2 [3].

Okoljski inženiring (EE) - Nadzorovalni in krmilni vmesnik za infrastrukturno opremo (elektroenergetski, hladilni in stavbni okoljski sistemi v telekomunikacijskih omrežjih) - 12. del: Oprema za napajanje IKT, energija in okoljski parametri za nadzorovanje informacijskega modela

Ta dokument določa meritev in nadzor napajanja, energije in okoljskih parametrov za opremo IKT v telekomunikacijskih ali podatkovnih središčih oz. prostorih strank.
Opredeljuje nadzorovalni vmesnik za napajanje, energijo in okoljske parametre opreme IKT na podlagi splošnega vmesnika ETSI ES 202 336-1 [1], da je mogoče vzpostaviti korelacije s parametri opreme IKT (promet, pretok, število povezanih linij, radijska nastavitev, kakovost storitve, ključni indikator zmogljivosti (KPI) itd.) v sistemu za upravljanje omrežja.
Korelacije nadzorovanih podatkov (napajanje, poraba energije in okoljske vrednosti) s parametri in nastavitvami opreme IKT niso zajete v področje uporabe tega dokumenta.
Nadzorovalni vmesnik zajema:
• meritev porabe notranje energije v opremi IKT z enosmernim in izmeničnim napajanjem;
• meritev porabe zunanje energije opreme IKT (če ni na voljo notranje napajanje, npr. pri starejši opremi);
• merjenje energije na podlagi izmerjene porabe energije;
• okoljske parametre opreme IKT (npr. temperatura pri vstopni odprtini za zrak na opremi). Ta dokument določa:
• najmanjši nabor izmenjanih informacij, ki se zahtevajo na vmesniku, vključno s parametri, kot so vrsta meritve (npr. RMS), točnost, doseg itd., ter nastavitvami, kot sta obdobji zajemanja in prenosa podatkov itd. To vključuje funkcije za pripravo, zapisovanje in prenos podatkov;
• metodo preskušanja nekaterih parametrov in funkcij;
• besedilne preglednice v dodatkih A in B z izmenjavo podatkov, opisano v »naravnem jeziku«;
• datoteke XML z oznakami in spremenljivkami, ki ustrezajo podatkom v preglednicah dodatkov A in B ter dopolnjujejo splošna pravila, opredeljena v dokumentih ETSI ES 202 336-1 [1] in ETSI ES 202 336-2 [3].

General Information

Status
Published
Publication Date
26-Feb-2019
Current Stage
6060 - National Implementation/Publication (Adopted Project)
Start Date
25-Feb-2019
Due Date
02-May-2019
Completion Date
27-Feb-2019
Mandate

Buy Standard

Standardization document
SIST ES 202 336-12 V1.2.1:2019
English language
42 pages
sale - 10%
Preview
sale - 10%
Preview

Standards Content (sample)

SLOVENSKI STANDARD
SIST ES 202 336-12 V1.2.1:2019
01-april-2019
Okoljski inženiring (EE) - Nadzorovalni in krmilni vmesnik za infrastrukturno
opremo (elektroenergetski, hladilni in stavbni okoljski sistemi v
telekomunikacijskih omrežjih) - 12. del: Oprema za napajanje IKT, energija in
okoljski parametri za nadzorovanje informacijskega modela

Environmental Engineering (EE) - Monitoring and control interface for infrastructure

equipment (power, cooling and building environment systems used in telecommunication

networks) - Part 12: ICT equipment power, energy and environmental parameters
monitoring information model
Ta slovenski standard je istoveten z: ETSI ES 202 336-12 V1.2.1 (2019-02)
ICS:
19.040 Preskušanje v zvezi z Environmental testing
okoljem
33.050.01 Telekomunikacijska Telecommunication terminal
terminalska oprema na equipment in general
splošno
SIST ES 202 336-12 V1.2.1:2019 en

2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.

---------------------- Page: 1 ----------------------
SIST ES 202 336-12 V1.2.1:2019
---------------------- Page: 2 ----------------------
SIST ES 202 336-12 V1.2.1:2019
ETSI ES 202 336-12 V1.2.1 (2019-02)
ETSI STANDARD
Environmental Engineering (EE);
Monitoring and control interface for infrastructure equipment
(power, cooling and building environment systems used in
telecommunication networks);
Part 12: ICT equipment power, energy and environmental
parameters monitoring information model
---------------------- Page: 3 ----------------------
SIST ES 202 336-12 V1.2.1:2019
2 ETSI ES 202 336-12 V1.2.1 (2019-02)
Reference
RES/EE-0266
Keywords
control, energy efficiency, interface,
management, network monitoring, power, system
ETSI
650 Route des Lucioles
F-06921 Sophia Antipolis Cedex - FRANCE
Tel.: +33 4 92 94 42 00 Fax: +33 4 93 65 47 16
Siret N° 348 623 562 00017 - NAF 742 C
Association à but non lucratif enregistrée à la
Sous-Préfecture de Grasse (06) N° 7803/88
Important notice
The present document can be downloaded from:
http://www.etsi.org/standards-search

The present document may be made available in electronic versions and/or in print. The content of any electronic and/or

print versions of the present document shall not be modified without the prior written authorization of ETSI. In case of any

existing or perceived difference in contents between such versions and/or in print, the prevailing version of an ETSI

deliverable is the one made publicly available in PDF format at www.etsi.org/deliver.

Users of the present document should be aware that the document may be subject to revision or change of status.

Information on the current status of this and other ETSI documents is available at

https://portal.etsi.org/TB/ETSIDeliverableStatus.aspx

If you find errors in the present document, please send your comment to one of the following services:

https://portal.etsi.org/People/CommiteeSupportStaff.aspx
Copyright Notification

No part may be reproduced or utilized in any form or by any means, electronic or mechanical, including photocopying

and microfilm except as authorized by written permission of ETSI.

The content of the PDF version shall not be modified without the written authorization of ETSI.

The copyright and the foregoing restriction extend to reproduction in all media.
© ETSI 2019.
All rights reserved.
TM TM TM

DECT , PLUGTESTS , UMTS and the ETSI logo are trademarks of ETSI registered for the benefit of its Members.

TM TM

3GPP and LTE are trademarks of ETSI registered for the benefit of its Members and

of the 3GPP Organizational Partners.

oneM2M™ logo is a trademark of ETSI registered for the benefit of its Members and

of the oneM2M Partners.
GSM and the GSM logo are trademarks registered and owned by the GSM Association.
ETSI
---------------------- Page: 4 ----------------------
SIST ES 202 336-12 V1.2.1:2019
3 ETSI ES 202 336-12 V1.2.1 (2019-02)
Contents

Intellectual Property Rights ................................................................................................................................ 5

Foreword ............................................................................................................................................................. 5

Modal verbs terminology .................................................................................................................................... 6

1 Scope ........................................................................................................................................................ 7

2 References ................................................................................................................................................ 7

2.1 Normative references ......................................................................................................................................... 7

2.2 Informative references ........................................................................................................................................ 8

3 Definition of terms, symbols and abbreviations ..................................................................................... 10

3.1 Terms ................................................................................................................................................................ 10

3.2 Symbols ............................................................................................................................................................ 11

3.3 Abbreviations ................................................................................................................................................... 11

4 ICT power, energy and environmental parameters monitoring system .................................................. 12

4.1 General description........................................................................................................................................... 12

4.2 Complementarity to existing site power and air-conditioning measurements .................................................. 14

4.3 Different site cases ........................................................................................................................................... 15

4.3.1 Simple site case ........................................................................................................................................... 15

4.3.2 Complex site case ....................................................................................................................................... 16

4.4 Measurement and monitoring description ........................................................................................................ 17

4.4.0 General description ..................................................................................................................................... 17

4.4.1 Internal measurements type 1 (Built-in in ICT equipment) ........................................................................ 18

4.4.2 External measurements type 2 (external sensors) for ICT equipment ........................................................ 19

4.4.3 Common requirements for external (type 2) and internal (type 1) measurement ....................................... 19

4.4.3.0 Principle of PEE measurement .............................................................................................................. 19

4.4.3.1 Power and energy consumption measurement ...................................................................................... 19

4.4.3.2 Voltage, current measurement............................................................................................................... 20

4.4.3.3 Accuracy of PEE measurement ............................................................................................................. 20

4.4.3.4 Local acquisition record ........................................................................................................................ 21

4.4.3.5 Accuracy verification ............................................................................................................................ 22

4.4.3.6 Data transmission period ....................................................................................................................... 23

4.4.3.7 Local record saving ............................................................................................................................... 23

4.5 PEE data analysis services................................................................................................................................ 23

Annex A (normative): Summary of mandatory monitoring / supervision information and

f unctions .......................................................................................................... 25

A.0 General description of mandatory monitoring / supervision information and functions tables ............. 25

A.1 Table for ICT equipment power, energy and environmental parameters measurements ....................... 25

Annex B (informative): Summary of non-mandatory monitoring / supervision information

and functions .................................................................................................. 28

B.0 General description of non mandatory monitoring / supervision information and functions tables ...... 28

B.1 Table for ICT equipment power, energy and environmental parameters ............................................... 28

Annex C (normative): Mandatory XML structure and elements .................................................... 30

C.1 Structure of an XML document for ICT Power/Energy/Environment metering (PEE) ......................... 30

Annex D (informative): 3GPP and E-UTRAN Management reference model and unified

interface Itf-N ................................................................................................. 32

Annex E (informative): Fixed network Management reference model and unified interface......... 33

ETSI
---------------------- Page: 5 ----------------------
SIST ES 202 336-12 V1.2.1:2019
4 ETSI ES 202 336-12 V1.2.1 (2019-02)

Annex F (informative): State of the art of power, energy measurement and monitoring

systems ............................................................................................................ 34

F.0 Introduction ............................................................................................................................................ 34

F.1 Acquisition and remote metering principles........................................................................................... 34

F.2 General description of measurement ...................................................................................................... 36

F.2.1 General principle .............................................................................................................................................. 36

F.2.2 Measurement sensors ....................................................................................................................................... 36

Annex G (informative): Bibliography ................................................................................................... 41

History .............................................................................................................................................................. 42

ETSI
---------------------- Page: 6 ----------------------
SIST ES 202 336-12 V1.2.1:2019
5 ETSI ES 202 336-12 V1.2.1 (2019-02)
Intellectual Property Rights
Essential patents

IPRs essential or potentially essential to normative deliverables may have been declared to ETSI. The information

pertaining to these essential IPRs, if any, is publicly available for ETSI members and non-members, and can be found

in ETSI SR 000 314: "Intellectual Property Rights (IPRs); Essential, or potentially Essential, IPRs notified to ETSI in

respect of ETSI standards", which is available from the ETSI Secretariat. Latest updates are available on the ETSI Web

server (https://ipr.etsi.org/).

Pursuant to the ETSI IPR Policy, no investigation, including IPR searches, has been carried out by ETSI. No guarantee

can be given as to the existence of other IPRs not referenced in ETSI SR 000 314 (or the updates on the ETSI Web

server) which are, or may be, or may become, essential to the present document.
Trademarks

The present document may include trademarks and/or tradenames which are asserted and/or registered by their owners.

ETSI claims no ownership of these except for any which are indicated as being the property of ETSI, and conveys no

right to use or reproduce any trademark and/or tradename. Mention of those trademarks in the present document does

not constitute an endorsement by ETSI of products, services or organizations associated with those trademarks.

Foreword

This ETSI Standard (ES) has been produced by ETSI Technical Committee Environmental Engineering (EE).

The present document is part 12 of a multi-part deliverable covering monitoring and control interface for infrastructure

equipment (power, cooling and building environment systems used in telecommunication networks), as identified

below:
Part 1: "Generic Interface";
Part 2: "DC power system control and monitoring information model";
Part 3: "AC UPS power system control and monitoring information model";
Part 4: "AC distribution power system control and monitoring information model";

Part 5: "AC diesel back-up generator system control and monitoring information model";

Part 6: "Air Conditioning System control and monitoring information model";
Part 7: "Other utilities system control and monitoring information model";
Part 8: "Remote Power Feeding System control and monitoring information model";
Part 9: "Alternative Power Systems";
Part 10: "AC inverter power system control and monitoring information model";

Part 11: "Battery system with integrated control and monitoring information model";

Part 12: "ICT equipment power, energy and environmental parameters monitoring information model".

ETSI
---------------------- Page: 7 ----------------------
SIST ES 202 336-12 V1.2.1:2019
6 ETSI ES 202 336-12 V1.2.1 (2019-02)

The goal of the present document is to define the measurement of electrical power and energy consumption of ICT

equipment as well as environmental parameters (temperature, hygrometry) in order to improve energy monitoring and

to correlate the power consumption to equipment operation activity (telecom traffic, computation, etc.). It is also to

define the transfer protocol of this measurement data from site to network operation centre. Knowing power

consumption gives the possibilities to reduce energy consumption of equipment and/or network. Granularity,

measurement period and accuracies are defined to meet these targets. They may depend on equipment types and

location in the different segments of a network (customer termination, access, core, data-center, etc.). In addition, these

measurements can be used to improve engineering and operation including more accurate dimensioning of power

systems, network evolution modelling and prevision, audit on field, etc.
Modal verbs terminology

In the present document "shall", "shall not", "should", "should not", "may", "need not", "will", "will not", "can" and

"cannot" are to be interpreted as described in clause 3.2 of the ETSI Drafting Rules (Verbal forms for the expression of

provisions).

"must" and "must not" are NOT allowed in ETSI deliverables except when used in direct citation.

ETSI
---------------------- Page: 8 ----------------------
SIST ES 202 336-12 V1.2.1:2019
7 ETSI ES 202 336-12 V1.2.1 (2019-02)
1 Scope

The present document defines measurement and monitoring of power, energy and environmental parameters for ICT

equipment in telecommunications or datacenter or customer premises.

It defines the power, energy and environmental parameters monitoring interface of ICT equipment based on generic

ETSI ES 202 336-1 [1] interface so that correlations can be made with ICT equipment parameters (traffic, flowrate,

number of connected lines, radio setting, QoS KPI, etc.) in the network management system.

Correlations of monitored data (power, energy consumption and environmental values) with the ICT equipment

parameters and settings are not in the scope of the present document.
The monitoring interface covers:

• Internal power consumption measurement on the ICT equipment powered in DC and AC.

• Power consumption measurement external to the ICT equipment (if not implemented internally, e.g. legacy

equipment).
• Energy metering based on power consumption measurement.

• Environmental parameters of the ICT equipment (e.g. temperature at air inlet of equipment).

The present document defines:

• The minimum set of exchanged information required at the interface, including parameters such as

measurement type (e.g. RMS), accuracy, range, etc. and settings such as data acquisition and transmission

period, etc. This includes the data preparation, recording and transmission functions.

• The testing method of some parameters and functions.

• Text tables in annexes A and B with data exchange described in "natural language".

• The XML files with tags and variables corresponding to the data in the tables of annexes A and B in

complement to general rules defined in ETSI ES 202 336-1 [1] and ETSI ES 202 336-2 [3].

2 References
2.1 Normative references

References are either specific (identified by date of publication and/or edition number or version number) or

non-specific. For specific references, only the cited version applies. For non-specific references, the latest version of the

referenced document (including any amendments) applies.

Referenced documents which are not found to be publicly available in the expected location might be found at

https://docbox.etsi.org/Reference.

NOTE: While any hyperlinks included in this clause were valid at the time of publication, ETSI cannot guarantee

their long term validity.

The following referenced documents are necessary for the application of the present document.

[1] ETSI ES 202 336-1: "Environmental Engineering (EE); Monitoring and Control Interface for

Infrastructure Equipment (Power, Cooling and Building Environment Systems used in

Telecommunication Networks); Part 1: Generic Interface".

[2] ETSI ETS 300 132-1: "Equipment Engineering (EE); Power supply interface at the input to

telecommunications equipment; Part 1: Operated by alternating current (ac) derived from direct

current (dc) sources".
ETSI
---------------------- Page: 9 ----------------------
SIST ES 202 336-12 V1.2.1:2019
8 ETSI ES 202 336-12 V1.2.1 (2019-02)

[3] ETSI ES 202 336-2: "Environmental Engineering (EE); Monitoring and control interface for

infrastructure equipment (Power, Cooling and environment systems used in telecommunication

networks); Part 2: DC power system control and monitoring information model".

[4] ETSI ES 202 336-3: "Environmental Engineering (EE); Monitoring and Control Interface for

Infrastructure Equipment (Power, Cooling and Building Environment Systems used in

Telecommunication Networks); Part 3: AC UPS power system control and monitoring information

model".

[5] ETSI ES 202 336-10: "Environmental Engineering (EE); Monitoring and Control Interface for

Infrastructure Equipment (Power, Cooling and Building Environment Systems used in

Telecommunication Networks); Part 10: AC inverter power system control and monitoring

information model".

[6] ETSI EN 300 132-2: "Environmental Engineering (EE); Power supply interface at the input to

telecommunications and datacom (ICT) equipment; Part 2: Operated by -48 V direct current (dc)".

[7] ETSI ES 202 336-4: "Environmental Engineering (EE); Monitoring and Control Interface for

Infrastructure Equipment (Power, Cooling and Building Environment Systems used in

Telecommunication Networks); Part 4: AC distribution power system control and monitoring

information model".

[8] ETSI ES 202 336-6: "Environmental Engineering (EE); Monitoring and Control Interface for

Infrastructure Equipment (Power, Cooling and Building Environment Systems used in

Telecommunication Networks); Part 6: Air Conditioning System control and monitoring

information model".

[9] ETSI EN 300 019-2 (all subparts): "Environmental Engineering (EE); Environmental conditions

and environmental tests for telecommunications equipment; Part 2: Specification of environmental

tests".

[10] ETSI EN 300 019-1-3: "Environmental Engineering (EE); Environmental conditions and

environmental tests for telecommunications equipment; Part 1-3: Classification of environmental

conditions; Stationary use at weatherprotected locations".
2.2 Informative references

References are either specific (identified by date of publication and/or edition number or version number) or

non-specific. For specific references, only the cited version applies. For non-specific references, the latest version of the

referenced document (including any amendments) applies.

NOTE: While any hyperlinks included in this clause were valid at the time of publication, ETSI cannot guarantee

their long term validity.

The following referenced documents are not necessary for the application of the present document but they assist the

user with regard to a particular subject area.

[i.1] IEEE 802.1™ to 802.11™: "IEEE Standard for Local & Metropolican Area Network".

[i.2] ISO/IEC 8879: "Information processing -- Text and office systems -- Standard Generalized

Markup Language (SGML)".

[i.3] ETSI ES 203 215: "Environmental Engineering (EE); Measurement Methods and Limits for Power

Consumption in Broadband Telecommunication Networks Equipment".

[i.4] ETSI ES 202 706: "Environmental Engineering (EE); Measurement method for power

consumption and energy efficiency of wireless access network equipment".
NOTE: ETSI ES 202 706 is revision of the ETSI TS 102 706.

[i.5] ETSI ES 201 554: "Environmental Engineering (EE); Measurement method for Energy efficiency

of Mobile Core network and Radio Access Control equipment".
ETSI
---------------------- Page: 10 ----------------------
SIST ES 202 336-12 V1.2.1:2019
9 ETSI ES 202 336-12 V1.2.1 (2019-02)

[i.6] ETSI ES 203 184: "Environmental Engineering (EE); Measurement Methods for Power

Consumption in Transport Telecommunication Networks Equipment".

[i.7] ETSI ES 203 136: "Environmental Engineering (EE); Measurement methods for energy efficiency

of router and switch equipment".

[i.8] ETSI EN 301 575: "Environmental Engineering (EE); Measurement method for energy

consumption of Customer Premises Equipment (CPE)".

[i.9] ETSI ES 203 237: "Environmental Engineering (EE); Green Abstraction Layer (GAL); Power

management capabilities of the future energy telecommunication fixed network nodes".

[i.10] ETSI ES 203 228: "Environmental Engineering (EE); Assessment of Mobile Network Energy

Efficiency".

[i.11] Recommendation ITU-T M.3000 series: "TMN and network maintenance: international

transmission systems, telephone circuits, telegraphy, facsimile and leased circuits

Telecommunications management network".

[i.12] Recommendation ITU-T M.3010 series: "TMN and network maintenance: international

transmission systems, telephone circuits, telegraphy, facsimile and leased circuits

Telecommunications management network - Principles for a telecommunications management

network".

[i.13] ETSI TS 132 101 (V15.0.0) (09-2018): "Digital cellular telecommunications system (Phase 2+);

Universal Mobile Telecommunications System (UMTS); LTE; Telecommunication management;

Principles and high level requirements (3GPP TS 32.101 version 15.0.0 Release 12)".

[i.14] ETSI EN 302 099: "Environmental Engineering (EE); Powering of equipment in access network".

[i.15] ETSI EN 300 132-3-1: "Environmental Engineering (EE); Power supply interface at the input to

telecommunications and datacom (ICT) equipment; Part 3: Operated by rectified current source,

alternating current source or direct current source up to 400 V; Sub-part 1: Direct current source

up to 400 V".

NOTE: ETSI EN 300 132-3 is currently under revision and will replace ETSI EN 300 132-3-1.

[i.16] ETSI ES 202 336 (all parts): "Environmental Engineering (EE); Monitoring and Control Interface

for Infrastructure Equipment (Power, Cooling and Building Environment Systems used in

Telecommunication Networks)".

[i.17] LT0511 RevB datasheet: "Linear Technology LTC 1966 precision micropower RMS to DC

converter".

[i.18] Mark Strzegowski: "Realizing the Full Potential of Your AMI Deployment with Meter Diagnostic

Data", Analog Device.

NOTE: Availablet at http://www.analog.com/en/technical-articles/full-potential-of-ami-deployment-with-meter-

diagnostic-data.html.

[i.19] ETSI EN 300 019-1-4: "Environmental Engineering (EE); Environmental conditions and

environmental tests for telecommunications equipment; Part 1-4: Classification of environmental

conditions; Stationary use at non-weatherprotected locations".
ETSI
---------------------- Page: 11 ----------------------
SIST ES 202 336-12 V1.2.1:2019
10 ETSI ES 202 336-12 V1.2.1 (2019-02)
3 Definition of terms, symbols and abbreviations
3.1 Terms
For the purposes of the present document, the following terms apply:

NOTE: Terms referring to energy interface, equipment and distribution are described in power distribution

standards ETSI ETS 300 132-1 [2], ETSI EN 300 132-3-1 [i.15], ETSI EN 300 132-2 [6] for ac and dc

interface A and A3 and ETSI EN 302 099 [i.14] for access network equipment powering.

AC distribution power system: device or system that distribute AC voltage or convert DC voltage to AC voltage and

provides electrical power without interruption in the event that commercial power drops to an unacceptable voltage

level

alarm: any information signalling abnormal state, i.e. different to specified normal state of hardware, software,

environment condition (temperature, humidity, etc.)

NOTE: The alarm signal should be understood by itself by an operator and should always have at least one

severity qualification or codification (colour, level, etc.). alarm message structure are defined in ETSI

ES 202 336-1 [1].
EXAMPLE: Rectifier failure, battery low voltage, etc.
board: electronic part of an equipment (e.g. a blade server)
cabinet: closed enclosure including several shelves or racks

Control Unit (CU): integrated unit in an equipment to monitor and control this equipment through sensors and

actuators
Data Gathering Unit (DGU): functional unit used for several functions:
• collect serial, digital, and analog data from several equipment;
• option to send (output) serial or digital commands;

• forward/receive information to/from the Local/Remote Management Application via agreed protocols;

• mediation between interfaces and protocols.
NOTE: This function may be integrated as part of specific equipment.

DC back-up system: device or system that provides electrical power without interruption in the event that commercial

power drops to an unacceptable voltage level
DC distribution power system: device or system to distribute DC voltage
ethernet: LAN protocol
NOTE: Equivalent to IEEE 802.1 to 802.11 [i.1].

event: any information signalling a change of state which is not an alarm: e.g. battery test, change of state of battery

charge

NOTE: The event signal should be understood by itself by an operator It should be transmitted in a formatted

structure with text message and other fields like for alarm. An event can be coded as an alarm with

severity "0".

eXtensible Mark-up Language (XML): application profile or restricted form of SGML

NOTE: By construction, XML documents are conforming SGML the Standard Generalized Markup Language

(ISO/IEC 8879 [i.2]) documents. XML is designed to describe data and focus on what data is. XML

should be discerned from the well known Hypertext Transfer Mark-up Language (HTML) which was

designed to display data and to focus on how data looks.
ETSI
---------------------- Page: 12 ----------------------
SIST ES 202 336-12 V1.2.1:2019
11 ETSI ES 202 336-12 V1.2.1 (2019-02)

infrastructure equipment: power, cooling and building environment systems used in telecommunications centres and

Access Networks locations
EXAMPLE: Cabinets, shelters, underground locations, etc.

module: closed unit including electronic boards forming part of a larger system (e.g. sub-unit of a base station in a

cabinet or separated)
rack: sub part of the cabinet including ICT equipment rest
shelf: level in a cabinet
warning: low severity alarm

World Wide Web Consortium (W3C): consortium founded in October 1994 to develop common interoperable

protocols and promote World Wide Web
NOTE: See http://www.w3c.org.

XML enabled CU (XCU): CU enabled to communicate using XML interface as defined in the present document

xDSL: global designation of the digital subscriber line (DSL) technologies
3.2 Symbols
For the purposes of the present document, the following symbols apply:
C Capacitor
E electric energy
I electric current
f frequency
P electric power
R Resistance
RC time constant of a timer circuit
T temperature
U electric voltage or difference of potential
T Voltage and Current acquisition period
acq
T PEE record time period for remote transmission
rec
T RMS integration period
rms
T Transmission period of data records
trans
3.3 Abbreviations
For the purposes of the present document, the following abbreviations apply:
µC Microcontr
...

Questions, Comments and Discussion

Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.