Standard Practice for Installation and Use of Radiant Barrier Systems (RBS) in Commercial/Industrial Building Construction

SIGNIFICANCE AND USE
4.1 In this practice it is recognized that effectiveness, safety, and durability of an RBS depends not only on the quality of the materials, but also on proper installation.  
4.2 Improper installation of an RBS will reduce the thermal effectiveness, cause fire risks and other unsafe conditions, and promote deterioration of the structure in which it is installed. Improper installations include fires caused by: (1) heat buildup in recessed lighting fixtures, (2) deterioration or failure of electrical wiring components, and (3) deterioration in wood structures and paint failure as a result of moisture accumulation.  
4.3 This practice provides direction for the installation of RBS products in a safe and effective manner. Actual conditions in existing buildings vary greatly and care shall be taken to ensure safe and effective installation.  
4.4 In this practice, requirements are presented that are both general and specific in nature and practical. They are not intended as specific instructions unless so indicated. The user shall consult the manufacturer for application and installation methods. The requirements in this practice shall be the minimum material and installation requirements for RBS.
SCOPE
1.1 This practice has been prepared for use by the designer, specifier, builder, and the installer of radiant barrier systems (RBS) for use in commercial/industrial building construction not otherwise restricted from use. The scope is limited to instruction relative to the use and installation of RBS, including a surface(s) normally having an emittance of 0.1 or less, such as metallic foil or metallic foil deposits, mounted on substrates. Some examples that this practice is intended to address include: (1) low-emittance surfaces in vented building envelope cavities intended to retard radiant transfer across the airspace: (2) low-emittance surfaces at interior building surfaces intended to retard radiant transfer to, or from, building inhabitants; and (3) low-emittance surface at interior building surfaces intended to reduce radiant transfer to, or from, radiant heating or cooling systems.  
1.2 This practice covers the installation process from pre-installation inspection through the post-installation procedure. It does not cover the production of the radiant barrier materials. (See Specification C1313.)  
1.3 This practice is not intended to replace the manufacturer’s installation instructions but shall be used in conjunction with such instructions. This practice is not intended to supercede local, state, federal, or international codes.  
1.4 This practice assumes that the installer possesses a good working knowledge of the applicable codes and regulations, safety practices, tools, equipment, and methods necessary for installation of radiant barrier materials. It also assumes that the installer understands the fundamentals of commercial/industrial building construction that affect the installation of RBS.  
1.5 The values stated in inch-pound units are to be regarded as standard. The values given in parentheses are mathematical conversions to SI units that are provided for information only and are not considered standard.  
1.6 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to establish appropriate safety, health, and environmental practices and determine the applicability of regulatory limitations prior to use. For specific precautionary statements see Sections 5 and 7.  
1.7 When the installation or use of radiant barrier materials, accessories, and systems has the potential to pose safety or health problems, the manufacturer shall provide the user appropriate current information regarding any known problems associated with the use of the product of the company and shall also specify protective measures.  
1.8 This international standard was developed in accordance with inte...

General Information

Status
Historical
Publication Date
14-Oct-2019
Technical Committee
Current Stage
Ref Project

Relations

Buy Standard

Standard
ASTM C1744-19 - Standard Practice for Installation and Use of Radiant Barrier Systems (RBS) in Commercial/Industrial Building Construction
English language
6 pages
sale 15% off
Preview
sale 15% off
Preview
Standard
REDLINE ASTM C1744-19 - Standard Practice for Installation and Use of Radiant Barrier Systems (RBS) in Commercial/Industrial Building Construction
English language
6 pages
sale 15% off
Preview
sale 15% off
Preview
Standard
ASTM C1744-19 - Standard Practice for Installation and Use of Radiant Barrier Systems (RBS) in Commercial/Industrial Building Construction
English language
6 pages
sale 15% off
Preview
sale 15% off
Preview

Standards Content (Sample)

This international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for the
Development of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.
Designation: C1744 − 19
Standard Practice for
Installation and Use of Radiant Barrier Systems (RBS) in
1
Commercial/Industrial Building Construction
This standard is issued under the fixed designation C1744; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision.Anumber in parentheses indicates the year of last reapproval.A
superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
1. Scope 1.6 This standard does not purport to address all of the
safety concerns, if any, associated with its use. It is the
1.1 This practice has been prepared for use by the designer,
responsibility of the user of this standard to establish appro-
specifier, builder, and the installer of radiant barrier systems
priate safety, health, and environmental practices and deter-
(RBS) for use in commercial/industrial building construction
mine the applicability of regulatory limitations prior to use.
not otherwise restricted from use. The scope is limited to
For specific precautionary statements see Sections 5 and 7.
instruction relative to the use and installation of RBS, includ-
1.7 When the installation or use of radiant barrier
ing a surface(s) normally having an emittance of 0.1 or less,
materials, accessories, and systems has the potential to pose
such as metallic foil or metallic foil deposits, mounted on
safety or health problems, the manufacturer shall provide the
substrates. Some examples that this practice is intended to
user appropriate current information regarding any known
address include: (1) low-emittance surfaces in vented building
problems associated with the use of the product of the company
envelope cavities intended to retard radiant transfer across the
and shall also specify protective measures.
airspace: (2) low-emittance surfaces at interior building sur-
1.8 This international standard was developed in accor-
faces intended to retard radiant transfer to, or from, building
dance with internationally recognized principles on standard-
inhabitants; and (3) low-emittance surface at interior building
ization established in the Decision on Principles for the
surfaces intended to reduce radiant transfer to, or from, radiant
Development of International Standards, Guides and Recom-
heating or cooling systems.
mendations issued by the World Trade Organization Technical
1.2 This practice covers the installation process from pre-
Barriers to Trade (TBT) Committee.
installation inspection through the post-installation procedure.
Itdoesnotcovertheproductionoftheradiantbarriermaterials.
2. Referenced Documents
(See Specification C1313.)
2
2.1 ASTM Standards:
1.3 This practice is not intended to replace the manufactur-
C168Terminology Relating to Thermal Insulation
er’s installation instructions but shall be used in conjunction
C1313Specification for Sheet Radiant Barriers for Building
with such instructions. This practice is not intended to super-
Construction Applications
cede local, state, federal, or international codes.
3
2.2 NFPA Standards:
1.4 Thispracticeassumesthattheinstallerpossessesagood
NFPA 54National Fuel Gas Code
working knowledge of the applicable codes and regulations,
NFPA 211Standard for Chimneys, Fireplaces and Vents
4
safety practices, tools, equipment, and methods necessary for
2.3 Other Document:
installationofradiantbarriermaterials.Italsoassumesthatthe
CPSCProduct Safety Fact Sheet No. 18 “The Home Elec-
installer understands the fundamentals of commercial/
trical System”
industrial building construction that affect the installation of
RBS.
3. Terminology
1.5 The values stated in inch-pound units are to be regarded 3.1 Definitions—For definitions of terms used in this
as standard. The values given in parentheses are mathematical
practice, refer to Terminology C168.
conversions to SI units that are provided for information only
and are not considered standard.
2
For referenced ASTM standards, visit the ASTM website, www.astm.org, or
contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM
1
This practice is under the jurisdiction of ASTM Committee C16 on Thermal Standards volume information, refer to the standard’s Document Summary page on
Insulation and is the direct responsibility of Subcommittee C16.21 on Reflective the ASTM website.
3
Insulation. Available from National Fire Protection Association (NFPA), 1 Batterymarch
Current edition approved Oct. 15, 2019. Published November 2019. Originally Park, Quincy, MA 02169-7471, http://www.nfpa.org.
4
approved in 2010. Last previous edition approved in 2012 as C1744–12. DOI: AvailablefromU.S.ConsumerProduc
...

This document is not an ASTM standard and is intended only to provide the user of an ASTM standard an indication of what changes have been made to the previous version. Because
it may not be technically possible to adequately depict all changes accurately, ASTM recommends that users consult prior editions as appropriate. In all cases only the current version
of the standard as published by ASTM is to be considered the official document.
Designation: C1744 − 12 C1744 − 19
Standard Practice for
Installation and Use of Radiant Barrier Systems (RBS) in
1
Commercial/Industrial Building Construction
This standard is issued under the fixed designation C1744; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
1. Scope
1.1 This practice has been prepared for use by the designer, specifier, builder, and the installer of radiant barrier systems (RBS)
for use in commercial/industrial building construction not otherwise restricted from use. The scope is limited to instruction relative
to the use and installation of RBS, including a surface(s) normally having an emittance of 0.1 or less, such as metallic foil or
metallic foil deposits, mounted on substrates. Some examples that this practice is intended to address include: (1) low-emittance
surfaces in vented building envelope cavities intended to retard radiant transfer across the airspace: (2) low-emittance surfaces at
interior building surfaces intended to retard radiant transfer to, or from, building inhabitants; and (3) low-emittance surface at
interior building surfaces intended to reduce radiant transfer to, or from, radiant heating or cooling systems.
1.2 This practice covers the installation process from pre-installation inspection through the post-installation procedure. It does
not cover the production of the radiant barrier materials. (See Specification C1313.)
1.3 This practice is not intended to replace the manufacturer’s installation instructions but shall be used in conjunction with such
instructions. This practice is not intended to supercede local, state, federal, or international codes.
1.4 This practice assumes that the installer possesses a good working knowledge of the applicable codes and regulations, safety
practices, tools, equipment, and methods necessary for installation of radiant barrier materials. It also assumes that the installer
understands the fundamentals of commercial/industrial building construction that affect the installation of RBS.
1.5 The values stated in inch-pound units are to be regarded as standard. The values given in parentheses are mathematical
conversions to SI units that are provided for information only and are not considered standard.
1.6 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility
of the user of this standard to establish appropriate safety, health, and environmental practices and determine the applicability of
regulatory limitations prior to use. For specific precautionary statements see Sections 5 and 7.
1.7 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility
of the user of this standard to establish appropriate safety and health practices and determine the applicability of regulatory
limitations prior to use. For specific precautionary statements see Sections When the installation or use of radiant barrier
materials, accessories, and systems has the potential to pose safety or health problems, the manufacturer shall provide the user
appropriate current information regarding any known problems associated with the use of the product of the company and shall
also specify protective measures.5 and 7.
1.6.1 When the installation or use of radiant barrier materials, accessories, and systems has the potential to pose safety or
health problems, the manufacturer shall provide the user appropriate current information regarding any known problems
associated with the use of the product of the company and shall also specify protective measures.
1.8 This international standard was developed in accordance with internationally recognized principles on standardization
established in the Decision on Principles for the Development of International Standards, Guides and Recommendations issued
by the World Trade Organization Technical Barriers to Trade (TBT) Committee.
2. Referenced Documents
2
2.1 ASTM Standards:
C168 Terminology Relating to Thermal Insulation
1
This practice is under the jurisdiction of ASTM Committee C16 on Thermal Insulation and is the direct responsibility of Subcommittee C16.21 on Reflective Insulation.
Current edition approved May 1, 2012Oct. 15, 2019. Published May 2012November 2019. Originally approved in 2010.
...

NOTICE: This standard has either been superseded and replaced by a new version or withdrawn.
Contact ASTM International (www.astm.org) for the latest information
Designation: C1744 − 19
Standard Practice for
Installation and Use of Radiant Barrier Systems (RBS) in
1
Commercial/Industrial Building Construction
This standard is issued under the fixed designation C1744; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
1. Scope 1.6 This standard does not purport to address all of the
safety concerns, if any, associated with its use. It is the
1.1 This practice has been prepared for use by the designer,
responsibility of the user of this standard to establish appro-
specifier, builder, and the installer of radiant barrier systems
priate safety, health, and environmental practices and deter-
(RBS) for use in commercial/industrial building construction
mine the applicability of regulatory limitations prior to use.
not otherwise restricted from use. The scope is limited to
For specific precautionary statements see Sections 5 and 7.
instruction relative to the use and installation of RBS, includ-
1.7 When the installation or use of radiant barrier
ing a surface(s) normally having an emittance of 0.1 or less,
materials, accessories, and systems has the potential to pose
such as metallic foil or metallic foil deposits, mounted on
safety or health problems, the manufacturer shall provide the
substrates. Some examples that this practice is intended to
user appropriate current information regarding any known
address include: (1) low-emittance surfaces in vented building
problems associated with the use of the product of the company
envelope cavities intended to retard radiant transfer across the
and shall also specify protective measures.
airspace: (2) low-emittance surfaces at interior building sur-
1.8 This international standard was developed in accor-
faces intended to retard radiant transfer to, or from, building
dance with internationally recognized principles on standard-
inhabitants; and (3) low-emittance surface at interior building
ization established in the Decision on Principles for the
surfaces intended to reduce radiant transfer to, or from, radiant
Development of International Standards, Guides and Recom-
heating or cooling systems.
mendations issued by the World Trade Organization Technical
1.2 This practice covers the installation process from pre-
Barriers to Trade (TBT) Committee.
installation inspection through the post-installation procedure.
It does not cover the production of the radiant barrier materials.
2. Referenced Documents
(See Specification C1313.)
2
2.1 ASTM Standards:
1.3 This practice is not intended to replace the manufactur-
C168 Terminology Relating to Thermal Insulation
er’s installation instructions but shall be used in conjunction
C1313 Specification for Sheet Radiant Barriers for Building
with such instructions. This practice is not intended to super-
Construction Applications
cede local, state, federal, or international codes.
3
2.2 NFPA Standards:
1.4 This practice assumes that the installer possesses a good
NFPA 54 National Fuel Gas Code
working knowledge of the applicable codes and regulations,
NFPA 211 Standard for Chimneys, Fireplaces and Vents
4
safety practices, tools, equipment, and methods necessary for
2.3 Other Document:
installation of radiant barrier materials. It also assumes that the
CPSC Product Safety Fact Sheet No. 18 “The Home Elec-
installer understands the fundamentals of commercial/
trical System”
industrial building construction that affect the installation of
RBS. 3. Terminology
1.5 The values stated in inch-pound units are to be regarded
3.1 Definitions—For definitions of terms used in this
as standard. The values given in parentheses are mathematical practice, refer to Terminology C168.
conversions to SI units that are provided for information only
and are not considered standard.
2
For referenced ASTM standards, visit the ASTM website, www.astm.org, or
contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM
1
This practice is under the jurisdiction of ASTM Committee C16 on Thermal Standards volume information, refer to the standard’s Document Summary page on
Insulation and is the direct responsibility of Subcommittee C16.21 on Reflective the ASTM website.
3
Insulation. Available from National Fire Protection Association (NFPA), 1 Batterymarch
Current edition approved Oct. 15, 2019. Published November 2019. Originally Park, Quincy, MA 02169-7471, http://www.nfpa.org.
4
approved in 2010. Last previous edition approved in 2012 as C1744 – 12. DOI: Available from U.S. Consumer Product Safety Commission (CPSC), 4330 East
10.1520/C1744-19. West Hwy., Bethesda, MD 20814, http://www.cpsc.gov.
...

Questions, Comments and Discussion

Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.