ASTM D6599-00
(Practice)Standard Practice for Construction of Live Fascines on Slopes
Standard Practice for Construction of Live Fascines on Slopes
SIGNIFICANCE AND USE
Live fascines are used to provide erosion and sedimentation control by increasing infiltration, slowing or redirecting runoff, and trapping seed and sediments. The method provides shallow mechanical surface slope stabilization, and provides enhanced values through vegetative growth and additional shallow soil reinforcement through the development of the roots. The ability of live fascines to function properly depends on the quality and choice of the materials used to construct the live fascine, the means and methods of fabrication and installation, and proper consideration of site characteristics and time of year. For the live fascine to function completely, it is important that the live fascine develops suitable growth.
SCOPE
1.1 This practice covers the material, fabrication and installation work to construct live fascines.
1.2 The values in this standard are in SI units and are to be regarded as the standard. The inch-pound units given in parentheses are for information only.
1.3 This practice offers a set of instructions for performing one or more specific operations. This document cannot replace education or experience and should be used in conjunction with professional judgement. Not all aspects of this practice may be applicable in all circumstances. This ASTM standard is not intended to represent or replace standard of care by which the adequacy of a given professional service must be judged, nor should this document be applied without considerations of a project's many unique aspects. The word "Standard" in the title of this document means only that the document has been approved through the ASTM consensus process.
1.4 This standard may involve hazardous materials, operations, and equipment. This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to establish appropriate safety and health practices and determine the applicability of regulatory limitations prior to use.
General Information
Relations
Standards Content (Sample)
NOTICE: This standard has either been superseded and replaced by a new version or withdrawn.
Contact ASTM International (www.astm.org) for the latest information
Designation:D6599–00
Standard Practice for
Construction of Live Fascines on Slopes
This standard is issued under the fixed designation D 6599; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (e) indicates an editorial change since the last revision or reapproval.
1. Scope 2.1.4 live stake, n—a woody stem or branch of vegetatively
self-propagating woody plant species. Live stakes are approxi-
1.1 This practice covers the material, fabrication and instal-
mately 2.5 to 4 cm (.59 to 1.59) in diameter and 60 to 75 cm
lation work to construct live fascines.
(249–309) in length with the terminal end sharpened to a point
1.2 The values in this standard are in SI units and are to be
orasteepangularcut.Uselivestakesasadditionalanchorsand
regarded as the standard. The inch-pound units given in
propagating material on the downslope side of live fascine
parentheses are for information only.
bundles.
1.3 This practice offers a set of instructions for performing
one or more specific operations. This document cannot replace
3. Summary of Practice
educationorexperienceandshouldbeusedinconjunctionwith
3.1 A live fascine is comprised of live cut plant stems and
professional judgement. Not all aspects of this practice may be
branches, typically of woody plant species (e.g., willow,
applicable in all circumstances. This ASTM standard is not
dogwood, poplar, etc.) that are formed into linear bundles.
intended to represent or replace standard of care by which the
These bundles are installed in shallow trenches, secured in the
adequacy of a given professional service must be judged, nor
trench with wood stakes, then backfilled with enough soil to
should this document be applied without considerations of a
leaveasmallportionontopofthebranchbundleexposed.Live
project’smanyuniqueaspects.Theword“Standard”inthetitle
fascines assist to control erosion, encourage vegetative top
of this document means only that the document has been
growth establishment and rooting for shallow soil stabilization.
approved through the ASTM consensus process.
1.4 This standard may involve hazardous materials, opera-
4. Significance and Use
tions, and equipment. This standard does not purport to
4.1 Live fascines are used to provide erosion and sedimen-
address all of the safety concerns, if any, associated with its
tation control by increasing infiltration, slowing or redirecting
use. It is the responsibility of the user of this standard to
runoff, and trapping seed and sediments. The method provides
establish appropriate safety and health practices and deter-
shallow mechanical surface slope stabilization, and provides
mine the applicability of regulatory limitations prior to use.
enhanced values through vegetative growth and additional
shallow soil reinforcement through the development of the
2. Terminology
roots. The ability of live fascines to function properly depends
2.1 Definitions:
on the quality and choice of the materials used to construct the
2.1.1 live fascine, n—a linear bundle of live cut branches of
live fascine, the means and methods of fabrication and instal-
woody plant material that propagates easily from cuttings. The
lation, and proper consideration of site characteristics and time
bundle is anchored in a shallow trench and partially covered
of year. For the live fascine to function completely, it is
with soil.
important that the live fascine develops suitable growth.
2.1.2 rolled erosion control product, n—a material manu-
factured into rolls designed to reduce erosion and assist in the
5. Materials
germination, establishment and/or anchorage of vegetation.
5.1 Live Woody Plant Material—are woody stems and
2.1.3 dead stout stake, n—a wood stake approximately .75
branch cuttings of vegetatively self-propagating woody plant
to 1 m (2.5 to 3 ft) in length. Construct dead stout stakes from
species.
3.8 3 8.9 cm (29 3 49) dimensional lumber cut diagonally
When constructing a live fascine, use only fresh or well-
along the 8.9 cm face.
preserved viable cuttings. Do not use dead plant material in
live fascines. The stems or branches should be long, straight
and flexible to allow easy assembly into bundles. Typically,
This practice is under the jurisdiction of ASTM Committee D18 on Soil and
plants are harvested near the project site within the same
Rock and is the direct responsibility of Subcommittee D18.25 on Erosion and
climatic zone. Cut the plant material in lengths ranging from 2
Sediment Control Technology.
Current edition approved Nov.10,2000. Published March 2001. to4m(68 to 138). Greater lengths may be used if handling and
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.
D6599
site conditions allow. The caliper (diameter) of cuttings gen- 6.4 The installation of live woody plant material bundles
erally range from 1.2 to 2.5 cm (.59 to 19).The greatest success normally begins at the bottom of the slope and proceeds
results from cutting and installing vegetation during the dor- upward, however alternate procedures may also be employed.
mant season. To minimize live fascine damage whil
...
Questions, Comments and Discussion
Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.