Standard Practice for Measuring Life-Cycle Costs of Buildings and Building Systems

SIGNIFICANCE AND USE
5.1 LCC analysis is an economic method for evaluating a project or project alternatives over a designated study period. The method entails computing the LCC for alternative building designs or system specifications having the same purpose and then comparing them to determine which has the lowest LCC over the study period.  
5.2 The LCC method is particularly suitable for determining whether the higher initial cost of a building or building system is economically justified by reductions in future costs (for example, operating, maintenance, repair, or replacement costs) when compared with an alternative that has a lower initial cost but higher future costs. If a building design or system specification has both a lower initial cost and lower future costs relative to an alternative, an LCC analysis is not needed to show that the former is the economically preferable choice.  
5.3 If an investment project is not essential to the building operation (for example, replacement of existing single-pane windows with new double-pane windows), the project must be compared against the “do nothing” alternative (that is, keeping the single pane windows) in order to determine if it is cost effective. Typically the “do nothing” alternative entails no initial investment cost but has higher future costs than the proposed project.
SCOPE
1.1 This practice establishes a procedure for evaluating the life-cycle cost (LCC) of a building or building system and comparing the LCCs of alternative building designs or systems that satisfy the same functional requirements.  
1.2 The LCC method measures, in present-value or annual-value terms, the sum of all relevant costs associated with owning and operating a building or building system over a specified time period.  
1.3 The basic premise of the LCC method is that to an investor or decision maker all costs arising from an investment decision are potentially important to that decision, including future as well as present costs. Applied to buildings or building systems, the LCC encompasses all relevant costs over a designated study period, including the costs of designing, purchasing/leasing, constructing/installing, operating, maintaining, repairing, replacing, and disposing of a particular building design or system.  
1.4 The values stated in inch-pound units are to be regarded as standard. The values given in parentheses are mathematical conversions to SI units that are provided for information only and are not considered standard.  
1.5 This international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for the Development of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.

General Information

Status
Historical
Publication Date
31-Aug-2017
Technical Committee
Drafting Committee
Current Stage
Ref Project

Relations

Buy Standard

Standard
ASTM E917-17 - Standard Practice for Measuring Life-Cycle Costs of Buildings and Building Systems
English language
23 pages
sale 15% off
Preview
sale 15% off
Preview
Standard
REDLINE ASTM E917-17 - Standard Practice for Measuring Life-Cycle Costs of Buildings and Building Systems
English language
23 pages
sale 15% off
Preview
sale 15% off
Preview

Standards Content (Sample)

NOTICE: This standard has either been superseded and replaced by a new version or withdrawn.
Contact ASTM International (www.astm.org) for the latest information
Designation: E917 − 17
Standard Practice for
Measuring Life-Cycle Costs of Buildings and Building
1
Systems
This standard is issued under the fixed designation E917; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision.Anumber in parentheses indicates the year of last reapproval.A
superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
INTRODUCTION
Several methods of economic evaluation are available to measure the economic performance of a
building or building system over a specified time period. These methods include, but are not limited
to, life-cycle cost (LCC) analysis, the benefit-to-cost ratio, internal rate of return, net benefits,
payback, multi-attribute decision analysis, risk analysis, and related measures (see Practices E964,
E1057,E1074,E1121,E1765,andE1946).Thesemethodsdifferintheirmeasureand,tosomeextent,
in their applicability to particular types of problems. Guide E1185 directs you to the appropriate
method for a particular economic problem. One of these methods, life-cycle cost (LCC) analysis, is
the subject of this practice. The LCC method sums, in either present-value or annual-value terms, all
relevant costs associated with a building or building system over a specified time period.Alternative
(mutually exclusive) designs or systems for a given functional requirement can be compared on the
basis of their LCCs to determine which is the least-cost means of satisfying that requirement over a
specified study period.
1. Scope conversions to SI units that are provided for information only
and are not considered standard.
1.1 This practice establishes a procedure for evaluating the
1.5 This international standard was developed in accor-
life-cycle cost (LCC) of a building or building system and
dance with internationally recognized principles on standard-
comparingtheLCCsofalternativebuildingdesignsorsystems
ization established in the Decision on Principles for the
that satisfy the same functional requirements.
Development of International Standards, Guides and Recom-
1.2 The LCC method measures, in present-value or annual-
mendations issued by the World Trade Organization Technical
value terms, the sum of all relevant costs associated with
Barriers to Trade (TBT) Committee.
owning and operating a building or building system over a
specified time period.
2. Referenced Documents
1.3 The basic premise of the LCC method is that to an
2
2.1 ASTM Standards:
investorordecisionmakerallcostsarisingfromaninvestment
E631Terminology of Building Constructions
decision are potentially important to that decision, including
E833Terminology of Building Economics
futureaswellaspresentcosts.Appliedtobuildingsorbuilding
E964Practice for Measuring Benefit-to-Cost and Savings-
systems, the LCC encompasses all relevant costs over a
to-Investment Ratios for Buildings and Building Systems
designated study period, including the costs of designing,
E1057Practice for Measuring Internal Rate of Return and
purchasing/leasing, constructing/installing, operating,
Adjusted Internal Rate of Return for Investments in
maintaining, repairing, replacing, and disposing of a particular
Buildings and Building Systems
building design or system.
E1074Practice for Measuring Net Benefits and Net Savings
1.4 Thevaluesstatedininch-poundunitsaretoberegarded
for Investments in Buildings and Building Systems
as standard. The values given in parentheses are mathematical
E1121Practice for Measuring Payback for Investments in
Buildings and Building Systems
1
This practice is under the jurisdiction of ASTM Committee E06 on Perfor-
mance of Buildings and is the direct responsibility of Subcommittee E06.81 on
2
Building Economics. For referenced ASTM standards, visit the ASTM website, www.astm.org, or
Current edition approved Sept. 1, 2017. Published November 2017. Originally contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM
approved in 1983. Last previous edition approved in 2015 as E917–15. DOI: Standards volume information, refer to the standard’s Document Summary page on
10.1520/E0917-17. the ASTM website.
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
1

---------------------- Page: 1 ----------------------
E917 − 17
E1185Guide for Selecting Economic Methods for Evaluat- 5.2 TheLCCmethodisparticularlysuitablefordetermining
ing Investments in Buildings and Building Systems whether the higher initial cost of a building or building system
E1369Guide for Selecting Techniques for Treating Uncer- is economically justified by reductions in future costs (for
tainty and Risk in the Economic Evaluation of Buildings example, operating, maintenance, repair, or replacement costs)
and
...

This document is not an ASTM standard and is intended only to provide the user of an ASTM standard an indication of what changes have been made to the previous version. Because
it may not be technically possible to adequately depict all changes accurately, ASTM recommends that users consult prior editions as appropriate. In all cases only the current version
of the standard as published by ASTM is to be considered the official document.
Designation: E917 − 15 E917 − 17
Standard Practice for
Measuring Life-Cycle Costs of Buildings and Building
1
Systems
This standard is issued under the fixed designation E917; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
INTRODUCTION
Several methods of economic evaluation are available to measure the economic performance of a
building or building system over a specified time period. These methods include, but are not limited
to, life-cycle cost (LCC) analysis, the benefit-to-cost ratio, internal rate of return, net benefits,
payback, multiattributemulti-attribute decision analysis, risk analysis, and related measures (see
Practices E964, E1057, E1074, E1121, E1765, and E1946). These methods differ in their measure and,
to some extent, in their applicability to particular types of problems. Guide E1185 directs you to the
appropriate method for a particular economic problem. One of these methods, life-cycle cost (LCC)
analysis, is the subject of this practice. The LCC method sums, in either present-value or annual-value
terms, all relevant costs associated with a building or building system over a specified time period.
Alternative (mutually exclusive) designs or systems for a given functional requirement can be
compared on the basis of their LCCs to determine which is the least-cost means of satisfying that
requirement over a specified study period.
1. Scope
1.1 This practice establishes a procedure for evaluating the life-cycle cost (LCC) of a building or building system and comparing
the LCCs of alternative building designs or systems that satisfy the same functional requirements.
1.2 The LCC method measures, in present-value or annual-value terms, the sum of all relevant costs associated with owning
and operating a building or building system over a specified time period.
1.3 The basic premise of the LCC method is that to an investor or decision maker all costs arising from an investment decision
are potentially important to that decision, including future as well as present costs. Applied to buildings or building systems, the
LCC encompasses all relevant costs over a designated study period, including the costs of designing, purchasing/leasing,
constructing/installing, operating, maintaining, repairing, replacing, and disposing of a particular building design or system.
1.4 The values stated in inch-pound units are to be regarded as standard. The values given in parentheses are mathematical
conversions to SI units that are provided for information only and are not considered standard.
1.5 This international standard was developed in accordance with internationally recognized principles on standardization
established in the Decision on Principles for the Development of International Standards, Guides and Recommendations issued
by the World Trade Organization Technical Barriers to Trade (TBT) Committee.
2. Referenced Documents
2
2.1 ASTM Standards:
E631 Terminology of Building Constructions
E833 Terminology of Building Economics
E964 Practice for Measuring Benefit-to-Cost and Savings-to-Investment Ratios for Buildings and Building Systems
1
This practice is under the jurisdiction of ASTM Committee E06 on Performance of Buildings and is the direct responsibility of Subcommittee E06.81 on Building
Economics.
Current edition approved Oct. 1, 2015Sept. 1, 2017. Published October 2015November 2017. Originally approved in 1983. Last previous edition approved in 20132015
as E917 – 13.E917 – 15. DOI: 10.1520/E0917-15.10.1520/E0917-17.
2
For referenced ASTM standards, visit the ASTM website, www.astm.org, or contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM Standards
volume information, refer to the standard’s Document Summary page on the ASTM website.
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
1

---------------------- Page: 1 ----------------------
E917 − 17
E1057 Practice for Measuring Internal Rate of Return and Adjusted Internal Rate of Return for Investments in Buildings and
Building Systems
E1074 Practice for Measuring Net Benefits and Net Savings for Investments in Buildings and Building Systems
E1121 Practice for Measuring Payback for Investments in Buildings and Building Systems
E1185 Guide for Selecting Economic Methods for Eva
...

Questions, Comments and Discussion

Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.