Standard Test Method for Evaluating Asphalt-Covered Concrete Bridge Decks Using Ground Penetrating Radar

SCOPE
1.1 This test method covers several radar evaluation procedures that can be used to evaluate the condition of concrete bridge decks overlaid with asphaltic concrete wearing surfaces. Specifically, this test method predicts the presence or absence of delamination.
1.2 The most serious form of deterioration is that which is caused by corrosion of embedded reinforcement. Corrosion is initiated by deicing salts, used for snow and ice control in the winter months, penetrating the concrete. In arid climates, the corrosion can be initiated by chloride ions contained in the mix ingredients.
1.2.1 As the reinforcing steel corrodes, it expands and creates a crack or subsurface fracture plane in the concrete at or just above the level of the reinforcement. The fracture plane, or delamination, may be localized or may extend over a substantial area, especially if the concrete cover to the reinforcement is small. It is not uncommon for more than one delamination to occur on different planes between the concrete surface and the reinforcing steel. Delaminations are not visible on the concrete surface. However, if repairs are not made, the delaminations progress to open spalls and, with continued corrosion, eventually affect the structural integrity of the deck.
1.3 This test method may not be suitable for evaluating bridges with delamination which are localized over the diameter of the reinforcement, or for those bridges which have cathodic protection (coke breeze as cathode) installed on the bridge or for which a conductive aggregate has been used in the asphalt (that is, blast furnace slag). This is because metals are perfect reflectors of EM waves, since the wave impedances for metals are zero.
1.4 The values stated in SI units are to be regarded as the standard. The inch-pound units given in parentheses are for information only. Specific precautionary statements are given in Section 5.
1.5 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to establish appropriate safety and health practices and determine the applicability of regulatory limitations prior to use.

General Information

Status
Historical
Publication Date
09-Mar-1997
Current Stage
Ref Project

Relations

Buy Standard

Standard
ASTM D6087-97(2001) - Standard Test Method for Evaluating Asphalt-Covered Concrete Bridge Decks Using Ground Penetrating Radar
English language
4 pages
sale 15% off
Preview
sale 15% off
Preview

Standards Content (Sample)

NOTICE: This standard has either been superceded and replaced by a new version or discontinued.
Contact ASTM International (www.astm.org) for the latest information.
Designation: D 6087 – 97 (Reapproved 2001)
Standard Test Method for
Evaluating Asphalt-Covered Concrete Bridge Decks Using
1
Ground Penetrating Radar
This standard is issued under the fixed designation D 6087; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (e) indicates an editorial change since the last revision or reapproval.
1. Scope priate safety and health practices and determine the applica-
bility of regulatory limitations prior to use.
1.1 This test method covers several radar evaluation proce-
dures that can be used to evaluate the condition of concrete
2. Summary of Test Method
bridge decks overlaid with asphaltic concrete wearing surfaces.
2.1 A vehicle equipped with a short-pulse ground penetrat-
Specifically, this test method predicts the presence or absence
ing radar, data acquisition device, recording device, and data
of delamination.
processing and interpretation equipment makes repeated
1.2 The most serious form of deterioration is that which is
passes, parallel to centerline across an asphalt covered bridge
caused by corrosion of embedded reinforcement. Corrosion is
deck at specified locations. Bridge deck condition is quantified
initiated by deicing salts, used for snow and ice control in the
based on the data obtained.
winter months, penetrating the concrete. In arid climates, the
corrosion can be initiated by chloride ions contained in the mix
3. Significance and Use
ingredients.
3.1 This test method provides information on the condition
1.2.1 As the reinforcing steel corrodes, it expands and
of concrete bridge decks overlaid with asphaltic concrete
creates a crack or subsurface fracture plane in the concrete at
without necessitating removal of the overlay, or other destruc-
or just above the level of the reinforcement. The fracture plane,
tive procedures.
or delamination, may be localized or may extend over a
3.2 A systematic approach to bridge deck rehabilitation
substantial area, especially if the concrete cover to the rein-
requires considerable data on the condition of the decks. In the
forcement is small. It is not uncommon for more than one
past, data has been collected using the traditional methods of
delamination to occur on different planes between the concrete
visual inspection supplemented by physical testing and coring.
surface and the reinforcing steel. Delaminations are not visible
Such methods have proven to be tedious, expensive and of
on the concrete surface. However, if repairs are not made, the
limited accuracy. Consequently, radar provides a mechanism to
delaminations progress to open spalls and, with continued
rapidly survey bridges in a non-contact, non-destructive man-
corrosion, eventually affect the structural integrity of the deck.
ner.
1.3 This test method may not be suitable for evaluating
3.3 Information on the condition of asphalt-covered, con-
bridges with delaminations which are localized over the
crete bridge decks is needed to estimate bridge deck condition
diameter of the reinforcement, or for those bridges which have
for maintenance and rehabilitation, to provide cost-effective
cathodic protection (coke breeze as cathode) installed on the
information necessary for rehabilitation contracts.
bridge or for which a conductive aggregate has been used in the
asphalt (that is, blast furnace slag). This is because metals are
4. Apparatus
perfect reflectors of EM waves, since the wave impedances for
4.1 Radar System—Air-coupled, short-pulse monostatic ra-
metals are zero.
dar(s) with a monocycle pulse, 150 mm (6 in.) free space
1.4 The values stated in SI units are to be regarded as the
resolution and a 50 scan/s data rate, minimum.
standard. The inch-pound units given in parentheses are for
4.2 Data Acquisition System—A data acquisition system,
information only. Specific precautionary statements are given
consisting of equipment for gathering radar data at the maxi-
in Section 5.
mum data rate of the radar system(s), 50 kHz for one radar, 100
1.5 This standard does not purport to address all of the
kHz for two radars, and 150 kHz for three radars. The system
safety concerns, if any, associated with its use. It is the
shall be capable of accurately acquiring radar data with a 60 dB
responsibility of the user of this standard to establish appro-
dynamic range.
4.3 Distance Measurement System—A distance measure-
1
This test method is under the jurisdiction of ASTM Committee D04 on Road
ment system consisting of a fifth-wheel or appropriate distance
and Paving Materials and is the direct responsibility of Subcommittee D04.32 on
measurement instrument (DMI) with accuracy of 6100
Bridges and Structures.
Current edition approve
...

Questions, Comments and Discussion

Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.