EN 54-25:2008
(Main)Fire detection and fire alarm systems - Part 25: Components using radio links
Fire detection and fire alarm systems - Part 25: Components using radio links
This European Standard specifies requirements, test methods and performance criteria for components used in fire alarms systems, installed in and around buildings, which use radio frequency links (RF links) to communicate. It also provides requirements for the evaluation of conformity of the components to the requirements of this European Standard.
Where components work together and this requires knowledge of the system design, this document also specifies requirements on the system.
When the fire detection and fire alarm systems (FDAS) use wired and RF links, the relevant parts of EN 54 apply together with this document. Requirements relevant to wire links are superseded or modified by those included in this European Standard.
This document does not restrict:
the intended use of radio spectrum, e.g. frequency, power output of devices;
the allowed maximum number of the components using RF links within the FDAS or one transmission path and/or RF link;
the allowed maximum number of the components affected by loss of one transmission path and/or RF link.
These requirements relate to national regulations and can vary from member state to member state.
Brandmeldeanlagen - Teil 25: Bestandteile, die Hochfrequenz-Verbindungen nutzen
Diese Europäische Norm legt Anforderungen, Prüfverfahren und Leistungsmerkmale für Bestandteile von Brandmeldeanlagen fest, die innerhalb und außerhalb von Gebäuden installiert werden und Hochfrequenz-Verbindungen (HF-Verbindungen) zur Kommunikation nutzen. Anforderungen an die Bewertung der Konformität der Bestandteile hinsichtlich der Anforderungen in dieser Europäischen Norm werden ebenfalls zur Verfügung gestellt.
Da das Zusammenwirken der Bestandteile Kenntnisse über das Brandmeldesystem erfordert, enthält dieses Dokument ebenfalls Systemanforderungen.
Werden in Brandmeldeanlagen (BMA) sowohl Leitungen als auch HF-Verbindungen verwendet, gelten die entsprechenden Teile von EN 54 zusammen mit diesem Dokument. Anforderungen an drahtgebundene Verbindungen werden ersetzt oder modifiziert durch die Anforderungen in dieser Europäischen Norm.
Dieses Dokument gibt keine Einschränkungen hinsichtlich:
der vorgesehenen Anwendung des Funkspektrums, z. B. Frequenz, Geräte-Ausgangsleistung,
der zulässigen Höchstanzahl der Bestandteile, die HF-Verbindungen innerhalb der BMA oder eines
Übertragungsweges und/oder auf einer HF-Verbindung nutzen,
der zulässigen Höchstanzahl der Bestandteile, die durch den Verlust eines Übertragungsweges und/oder einer HF-Verbindung beeinflusst werden.
Diese Anforderungen unterliegen nationalen Vorschriften und können von Land zu Land unterschiedlich sein.
Systèmes de détection et d'alarme incendie - Partie 25: Composants utilisant des liaisons radioélectriques
La présente Norme européenne définit les exigences, les méthodes d'essai et les critères de performance pour les composants utilisés dans les systèmes d'alarme incendie installés dans les bâtiments et autour de ceux-ci, qui utilisent des liaisons radioélectriques pour communiquer. Elle spécifie également les exigences pour l'évaluation de la conformité des composants aux exigences de la présente Norme européenne.
Lorsque les composants fonctionnent ensemble et que cela nécessite la connaissance de la conception du système, le présent document spécifie également les exigences relatives au système.
Lorsque les systèmes de détection et d'alarme incendie (SDAI) emploient des liaisons radioélectriques et filaires, les parties concernées de la série EN 54 s'appliquent. Les exigences spécifiées dans la présente Norme européenne annulent et remplacent ou modifient les exigences concernant les liaisons filaires.
Le présent document ne traite pas les éléments suivants :
l'usage prévu du spectre radioélectrique, par exemple la fréquence, la puissance de sortie des dispositifs ;
le nombre maximal autorisé de composants utilisant des liaisons radioélectriques dans le SDAI ou une voie de transmission et/ou liaison radioélectrique ;
le nombre maximal autorisé de composants affectés par la perte d'une voie de transmission et/ou liaison radioélectrique.
Ces exigences se rapportent aux réglementations nationales et peuvent varier d'un Etat membre à l'autre.
Sistemi za odkrivanje in javljanje požara ter alarmiranje - 25. del: Sestavni deli za radijske povezave
Ta evropski standard določa zahteve, preskusne metode in merila za delovanje za sestavne dele, ki se uporabljajo v sistemih za javljanje požara ter alarmiranje, nameščene v in okoli stavb, ki uporabljajo radijsko frekvenčne povezave (RF povezave) za komunikacijo. Prav tako podaja zahteve za vrednotenje skladnosti sestavnih delov z zahtevami tega evropskega standarda. Kadar sestavni deli delujejo skupaj, kar zahteva poznavanje načrtovanja sistema, ta dokument prav tako določa zahteve za sistem. Kadar sistemi za odkrivanje in javljanje požara ter alarmiranje (FDAS) uporabljajo ožičene in RF povezave, veljajo ustrezni deli EN 54 skupaj z tem dokumentom. Zahteve, ki se nanašajo na ožičene povezave, so izpodrinjene ali spremenjene z tistimi, ki so vključene v ta evropski standard. Ta dokument ne omejuje: - predvidene uporabe radijskega spektra, npr. frekvence, izhodno moč naprav; - dovoljenega največje števila sestavnih delov, ki uporabljajo RF povezave v okviru FSAD ali ene prenosne potu in/ali RF povezave; - dovoljeno največje število sestavnih delov, na katere vpliva izguba ene poti prenosa in/ali RF povezave. Te zahteve se nanašajo na nacionalne predpise in se lahko razlikujejo med državami članicami.
General Information
Relations
Standards Content (Sample)
SLOVENSKI STANDARD
01-julij-2008
Sistemi za odkrivanje in javljanje požara ter alarmiranje - 25. del: Sestavni deli za
radijske povezave
Fire detection and fire alarm systems - Part 25: Components using radio links
Brandmeldeanlagen - Teil 25: Bestandteile, die Hochfrequenz-Verbindungen nutzen
Systèmes de détection et d'alarme incendie - Partie 25: Composants utilisant des
liaisons radioélectriques
Ta slovenski standard je istoveten z: EN 54-25:2008
ICS:
13.220.20 3RåDUQD]DãþLWD Fire protection
13.320 Alarmni in opozorilni sistemi Alarm and warning systems
2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.
EUROPEAN STANDARD
EN 54-25
NORME EUROPÉENNE
EUROPÄISCHE NORM
March 2008
ICS 13.220.20
English Version
Fire detection and fire alarm systems - Part 25: Components
using radio links
Systèmes de détection et d'alarme incendie - Partie 25: Brandmeldeanlagen - Teil 25: Bestandteile, die
Composants utilisant des liaisons radioélectriques Hochfrequenz-Verbindungen nutzen
This European Standard was approved by CEN on 20 January 2008.
CEN members are bound to comply with the CEN/CENELEC Internal Regulations which stipulate the conditions for giving this European
Standard the status of a national standard without any alteration. Up-to-date lists and bibliographical references concerning such national
standards may be obtained on application to the CEN Management Centre or to any CEN member.
This European Standard exists in three official versions (English, French, German). A version in any other language made by translation
under the responsibility of a CEN member into its own language and notified to the CEN Management Centre has the same status as the
official versions.
CEN members are the national standards bodies of Austria, Belgium, Bulgaria, Cyprus, Czech Republic, Denmark, Estonia, Finland,
France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta, Netherlands, Norway, Poland, Portugal,
Romania, Slovakia, Slovenia, Spain, Sweden, Switzerland and United Kingdom.
EUROPEAN COMMITTEE FOR STANDARDIZATION
COMITÉ EUROPÉEN DE NORMALISATION
EUROPÄISCHES KOMITEE FÜR NORMUNG
Management Centre: rue de Stassart, 36 B-1050 Brussels
© 2008 CEN All rights of exploitation in any form and by any means reserved Ref. No. EN 54-25:2008: E
worldwide for CEN national Members.
Contents Page
Foreword .4
Introduction.6
1 Scope.7
2 Normative references.7
3 Terms, definitions and abbreviations .8
3.1 Terms and definitions .8
3.2 Abbreviations.10
4 System requirements.10
4.1 General .10
4.2 Radio frequency links .10
4.2.1 Immunity to site attenuation .10
4.2.2 Alarm signal integrity.11
4.2.3 Identification of the RF linked component .11
4.2.4 Receiver performance.11
4.2.5 Immunity to interference .12
4.2.6 Loss of communication .12
4.2.7 Antenna .13
5 Components requirements.13
5.1 Compliance .13
5.2 General .13
5.3 Power supply equipment.13
5.4 Environmental related requirements.14
5.4.1 General .14
5.4.2 General test procedure .14
5.4.3 Provision for testing .15
6 Documentation .15
7 Marking.16
8 Tests .16
8.1 General requirements .16
8.1.1 General .16
8.1.2 Standard atmospheric conditions for testing .16
8.1.3 Operating conditions for tests.16
8.1.4 Mounting and orientation .16
8.1.5 Tolerances.16
8.2 System tests .17
8.2.1 Test schedule for system tests.17
8.2.2 Test for immunity to site attenuation .17
8.2.3 Test for alarm signal integrity.18
8.2.4 Test for identification of RF linked components.18
8.2.5 Test for the receiver performance .18
8.2.6 Test for mutual disturbance between systems of the same manufacturer.19
8.2.7 Test of compatibility with other band users.20
8.2.8 Test for the detection of a loss of communication on a link .21
8.2.9 Test of the antenna .22
8.3 Components tests .22
8.3.1 General .22
8.3.2 Test schedule for components tests.22
8.3.3 Verification of the service life of the autonomous power source(s) . 24
8.3.4 Test for the low power condition fault signal . 24
8.3.5 Test for the polarity reversal. 25
8.3.6 Repeatability test . 26
8.3.7 Reproducibility test. 26
8.3.8 Variation of supply parameters . 27
8.3.9 Dry heat (operational). 27
8.3.10 Dry heat (endurance) . 28
8.3.11 Cold (operational) . 28
8.3.12 Damp heat, cyclic (operational). 29
8.3.13 Damp heat, steady state (operational). 30
8.3.14 Damp heat, steady state (endurance) . 31
8.3.15 SO -corrosion (endurance) . 31
8.3.16 Shock (operational). 32
8.3.17 Impact (operational). 33
8.3.18 Vibration, sinusoidal (operational). 33
8.3.19 Vibration, sinusoidal (endurance) . 34
8.3.20 Electromagnetic Compatibility (EMC), Immunity tests (operational) . 35
Annex A (normative) Test configuration by using radio frequency shielded test equipment . 36
Annex B (normative) Immunity to site attenuation (path loss). 40
Annex C (informative) Data and calculation of the service life of the autonomous power source(s) . 41
Annex ZA (informative) Clauses of this European Standard addressing the provisions of the EU
Construction Products Directive (89/106/EEC). 43
Bibliography . 52
Foreword
This document (EN 54-25:2008) has been prepared by Technical Committee CEN/TC 72 “Fire detection and
fire alarm systems”, the secretariat of which is held by BSI.
This European Standard shall be given the status of a national standard, either by publication of an identical
text or by endorsement, at the latest by September 2008, and conflicting national standards shall be
withdrawn at the latest by March 2011.
Attention is drawn to the possibility that some of the elements of this document may be the subject of patent
rights. CEN [and/or CENELEC] shall not be held responsible for identifying any or all such patent rights.
This document has been prepared under a mandate given to CEN by the European Commission and the
European Free Trade Association, and supports essential requirements of EU Directive(s).
For relationship with EU Directive(s), see informative Annex ZA, which is an integral part of this document.
EN 54 Fire detection and fire alarm systems consists of the following parts:
Part 1: Introduction
Part 2: Control and indicating equipment
Part 3: Fire alarm devices – Sounders
Part 4: Power supply equipment
Part 5: Heat detectors – Point detectors
Part 7: Smoke detectors – Point detectors using scattered light, transmitted light or ionisation
Part 10: Flame detectors – Point detectors
Part 11: Manual call points
Part 12: Smoke detectors – Line detectors using an optical light beam
Part 13: Compatibility assessment of system components
Part 14: Guidelines for planning, design, installation, commissioning, use and maintenance
Part 15:
...
Questions, Comments and Discussion
Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.