Automation systems in the process industry - Factory acceptance test (FAT), site acceptance test (SAT) and site integration test (SIT)

defines procedures and specifications for the Factory Acceptance Test (FAT), the Site Acceptance Test (SAT), and the Site Integration Test (SIT). These tests are carried out to prove that the automation system is in accordance with the specification.

Automatisierungssysteme in der Prozessindustrie - Werksabnahme (FAT), Abnahme der installierten Anlage (SAT) und Integrationstest (SIT)

Systèmes d'automatisme dans les industries de processus - Essais d'acceptation en usine, essais d'acceptation sur site et essais d'intégration sur site

Avtomatizacijski sistemi v procesni industriji – Tovarniški prevzemni preskus (FAT), prevzemni preskus pri prevzemniku (SAT) in preskus integracije pri prevzemniku (SIT) (IEC 62381:2006)

General Information

Status
Withdrawn
Publication Date
15-Mar-2007
Withdrawal Date
31-Jan-2010
Current Stage
9960 - Withdrawal effective - Withdrawal
Start Date
28-Mar-2015
Completion Date
28-Mar-2015

Relations

Buy Standard

Standard
EN 62381:2007
English language
40 pages
sale 10% off
Preview
sale 10% off
Preview
e-Library read for
1 day

Standards Content (Sample)


SLOVENSKI STANDARD
01-julij-2007
Avtomatizacijski sistemi v procesni industriji – Tovarniški prevzemni preskus
(FAT), prevzemni preskus pri prevzemniku (SAT) in preskus integracije pri
prevzemniku (SIT) (IEC 62381:2006)
Automation systems in the process industry - Factory acceptance test (FAT), site
acceptance test (SAT) and site integration test (SIT) (IEC 62381:2006)
Automatisierungssysteme in der Prozessindustrie - Werksabnahme (FAT), Abnahme der
installierten Anlage (SAT) und Integrationstest (SIT)) (IEC 62381:2006)
Systemes d'automatisme dans les industries de processus - Essais d'acceptation en
usine, essais d'acceptation sur site et essais d'intégration sur site (IEC 62381:2006)
Ta slovenski standard je istoveten z: EN 62381:2007
ICS:
25.040.01 Sistemi za avtomatizacijo v Industrial automation
industriji na splošno systems in general
2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.

EUROPEAN STANDARD
EN 62381
NORME EUROPÉENNE
March 2007
EUROPÄISCHE NORM
ICS 25.040.01
English version
Automation systems in the process industry -
Factory acceptance test (FAT), site acceptance test (SAT)
and site integration test (SIT)
(IEC 62381:2006)
Systèmes d'automatisme  Automatisierungssysteme
dans les industries de processus - in der Prozessindustrie -
Essais d'acceptation en usine, Werksabnahme (FAT),
essais d'acceptation sur site Abnahme der installierten Anlage (SAT)
et essais d'intégration sur site und Integrationstest (SIT)
(CEI 62381:2006) (IEC 62381:2006)

This European Standard was approved by CENELEC on 2007-02-01. CENELEC members are bound to comply
with the CEN/CENELEC Internal Regulations which stipulate the conditions for giving this European Standard
the status of a national standard without any alteration.

Up-to-date lists and bibliographical references concerning such national standards may be obtained on
application to the Central Secretariat or to any CENELEC member.

This European Standard exists in three official versions (English, French, German). A version in any other
language made by translation under the responsibility of a CENELEC member into its own language and notified
to the Central Secretariat has the same status as the official versions.

CENELEC members are the national electrotechnical committees of Austria, Belgium, Bulgaria, Cyprus, the
Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia,
Lithuania, Luxembourg, Malta, the Netherlands, Norway, Poland, Portugal, Romania, Slovakia, Slovenia, Spain,
Sweden, Switzerland and the United Kingdom.

CENELEC
European Committee for Electrotechnical Standardization
Comité Européen de Normalisation Electrotechnique
Europäisches Komitee für Elektrotechnische Normung

Central Secretariat: rue de Stassart 35, B - 1050 Brussels

© 2007 CENELEC - All rights of exploitation in any form and by any means reserved worldwide for CENELEC members.
Ref. No. EN 62381:2007 E
Foreword
The text of document 65/385/FDIS, future edition 1 of IEC 62381, prepared by IEC TC 65,
Industrial-process measurement and control, was submitted to the IEC-CENELEC parallel vote and was
approved by CENELEC as EN 62381 on 2007-02-01.
The following dates were fixed:
– latest date by which the EN has to be implemented
at national level by publication of an identical
national standard or by endorsement (dop) 2007-11-01
– latest date by which the national standards conflicting
with the EN have to be withdrawn (dow) 2010-02-01
__________
Endorsement notice
The text of the International Standard IEC 62381:2006 was approved by CENELEC as a European
Standard without any modification.
__________
INTERNATIONAL IEC
STANDARD 62381
First edition
2006-11
Automation systems in the process industry –
Factory acceptance test (FAT), site acceptance
test (SAT), and site integration test (SIT)
© IEC 2006 ⎯ Copyright - all rights reserved
No part of this publication may be reproduced or utilized in any form or by any means, electronic or
mechanical, including photocopying and microfilm, without permission in writing from the publisher.
International Electrotechnical Commission, 3, rue de Varembé, PO Box 131, CH-1211 Geneva 20, Switzerland
Telephone: +41 22 919 02 11 Telefax: +41 22 919 03 00 E-mail: inmail@iec.ch Web: www.iec.ch
PRICE CODE
Commission Electrotechnique Internationale w
International Electrotechnical Commission
МеждународнаяЭлектротехническаяКомиссия
For price, see current catalogue

– 2 – 62381 © IEC:2006(E)
CONTENTS
INTRODUCTION.5
FOREWORD.3

1 Scope.6
2 Terms and definitions.9
3 Abbreviations .10
4 General preparation before conducting the FAT .11
4.1 Documents typically prepared by owner/contractor .11
4.2 Documents typically prepared by vendor .11
5 Factory acceptance test .12
5.1 General .12
5.2 FAT test schedule .12
5.3 Test procedure .13
5.4 FAT rework .16
5.5 Documentation of FAT in accordance with Annex A.16
6 Site acceptance test .16
6.1 General .16
6.2 SAT test schedule .16
7 Site integration test .17
7.1 General .17
7.2 SIT test schedule .17

Annex A (informative) FAT checklists.18
Annex B (informative) SAT checklist .30
Annex C (informative) SIT checklist .31
Annex D (informative) FAT certificate .32
Annex E (informative) SAT certificate .33
Annex F (informative) SIT certificate .34
Annex G (informative) Automation system acceptance certificate.35
Annex H (informative) FAT punch list.36
Annex I (informative) SAT punch list .37
Annex J (informative) SIT punch list.38

Figure 1 – Diagram depicting typical sequence of events for FAT, SAT and SIT with
respect to the project milestones .7
Figure 2 – Diagram depicting the relationship for the SAT and SIT between the DCS
and subsystems.8
Figure 3 – Diagram depicting the relationship between the FAT, SAT and SIT with the
relevant plant levels.9

62381 © IEC:2006(E) – 3 –
INTERNATIONAL ELECTROTECHNICAL COMMISSION
____________
AUTOMATION SYSTEMS IN THE PROCESS INDUSTRY –
FACTORY ACCEPTANCE TEST (FAT),
SITE ACCEPTANCE TEST (SAT), AND SITE INTEGRATION TEST (SIT)

FOREWORD
1) The International Electrotechnical Commission (IEC) is a worldwide organization for standardization comprising
all national electrotechnical committees (IEC National Committees). The object of IEC is to promote
international co-operation on all questions concerning standardization in the electrical and electronic fields. To
this end and in addition to other activities, IEC publishes International Standards, Technical Specifications,
Technical Reports, Publicly Available Specifications (PAS) and Guides (hereafter referred to as “IEC
Publication(s)”). Their preparation is entrusted to technical committees; any IEC National Committee interested
in the subject dealt with may participate in this preparatory work. International, governmental and non-
governmental organizations liaising with the IEC also participate in this preparation. IEC collaborates closely
with the International Organization for Standardization (ISO) in accordance with conditions determined by
agreement between the two organizations.
2) The formal decisions or agreements of IEC on technical matters express, as nearly as possible, an international
consensus of opinion on the relevant subjects since each technical committee has representation from all
interested IEC National Committees.
3) IEC Publications have the form of recommendations for international use and are accepted by IEC National
Committees in that sense. While all reasonable efforts are made to ensure that the technical content of IEC
Publications is accurate, IEC cannot be held responsible for the way in which they are used or for any
misinterpretation by any end user.
4) In order to promote international uniformity, IEC National Committees undertake to apply IEC Publications
transparently to the maximum extent possible in their national and regional publications. Any divergence
between any IEC Publication and the corresponding national or regional publication shall be clearly indicated in
the latter.
5) IEC provides no marking procedure to indicate its approval and cannot be rendered responsible for any
equipment declared to be in conformity with an IEC Publication.
6) All users should ensure that they have the latest edition of this publication.
7) No liability shall attach to IEC or its directors, employees, servants or agents including individual experts and
members of its technical committees and IEC National Committees for any personal injury, property damage or
other damage of any nature whatsoever, whether direct or indirect, or for costs (including legal fees) and
expenses arising out of the publication, use of, or reliance upon, this IEC Publication or any other IEC
Publications.
8) Attention is drawn to the Normative references cited in this publication. Use of the referenced publications is
indispensable for the correct application of this publication.
9) Attention is drawn to the possibility that some of the elements of this IEC Publication may be the subject of
patent rights. IEC shall not be held responsible for identifying any or all such patent rights.
International Standard IEC 62381 has been prepared by IEC technical committee 65:
Industrial-process measurement and control.
This standard cancels and replaces IEC/PAS 62381 published in 2004. This first edition
constitutes a technical revision.
The text of this standard is based on the following documents:
FDIS Report on voting
65/385/FDIS 65/394/RVD
Full information on the voting for the approval of this standard can be found in the report on
voting indicated in the above table.
This publication has been drafted in accordance with the ISO/IEC Directives, Part 2.

– 4 – 62381 © IEC:2006(E)
The committee has decided that the contents of this publication will remain unchanged until
the maintenance result date indicated on the IEC web site under "http://webstore.iec.ch" in
the data related to the specific publication. At this date, the publication will be
• reconfirmed,
• withdrawn,
• replaced by a revised edition, or
• amended.
A bilingual version of this publication may be issued at a later date.

62381 © IEC:2006(E) – 5 –
INTRODUCTION
There is an increasing trend in the process industry to shorten the time period for project
execution. At the same time, the complexity of automation systems is being increased due to
the number of connected systems and the use of new technologies, for example, fieldbus
systems.
Experience has shown that the owner, the contractor and the vendor have long and extensive
discussions to unambiguously lay down the scope of activities and responsibilities in order to
achieve a timely delivery and acceptance of automation systems.
This standard should lead to an improvement and acceleration of the negotiation phase and to
a mutual understanding about the scope of activities of each party
The annexes of this standard contain forms which may be used in the test procedures. Buyers
of this standard may copy these forms for their own purposes only in the required amount.
For application in the pharmaceutical or other highly specialized industries, additional
guidelines (for example, Good Automated Manufacturing Practice (GAMP
...