Hydraulic road binders - Part 3: Assessment and verification of constancy of performance

This document specifies the scheme for the assessment and verification of constancy of performance (AVCP) of hydraulic road binders, including certification of conformity of the factory production control.
This document provides technical rules for factory production control, further testing of samples taken at the manufacturing plant (autocontrol testing), assessment of the performance of the hydraulic road binder, initial inspection of the manufacturing plant and of factory production control and continuing surveillance, assessment and evaluation of factory production control.
This document is intended to be linked with the Annexes ZA of the European Standards covering hydraulic road binders, i.e. EN 13282-1 and EN 13282-2.
NOTE   The reason for having drafted this separate document is that the provisions it includes are applicable to different products covered by different European Standards.

Hydraulische Tragschichtbinder - Teil 3: Bewertung und Überprüfung der Leistungsbeständigkeit

Dieses Dokument legt das Verfahren zur Bewertung und Überprüfung der Leistungsbeständigkeit (AVCP) von hydraulischen Tragschichtbindern einschließlich der Zertifizierung der Konformität der werkseigenen Produktionskontrolle fest.
Dieses Dokument enthält technische Regeln für die werkseigene Produktionskontrolle, die zusätzliche Prüfung von im Herstellungsbetrieb entnommenen Proben (interne Überwachungsprüfung), die Bewertung der Leistung des hydraulischen Tragschichtbinders, die Erstinspektion des Herstellungsbetriebs und der werkseigenen Produktionskontrolle sowie die kontinuierliche Überwachung, Bewertung und Evaluierung der werkseigenen Produktionskontrolle.
Dieses Dokument ist dafür vorgesehen, in Verbindung mit Anhang ZA der Europäischen Normen zu hydraulischen Tragschichtbindern, d. h. EN 13282 1 und EN 13282 2, gelesen zu werden.
ANMERKUNG   Dieses gesonderte Dokument wurde aus dem Grund erarbeitet, dass die darin enthaltenen Bestimmungen auf unterschiedliche Produkte, die von unterschiedlichen Europäischen Normen abgedeckt werden, anwendbar sind.

Liants hydrauliques routiers - Partie 3: Évaluation et vérification de la constance des performances

Le présent document spécifie le système d’évaluation et de vérification de la constance des performances (EVCP) des liants hydrauliques routiers, qui inclut une certification de conformité du contrôle de la production en usine.
Le présent document fournit les règles techniques pour le contrôle de la production en usine, les essais complémentaires sur des échantillons prélevés dans l’établissement de fabrication (essais d’autocontrôle), l’évaluation des performances du liant hydraulique routier, l’inspection initiale de l’établissement de fabrication et du contrôle de la production en usine, et la surveillance, l’évaluation et l’appréciation permanentes du contrôle de la production en usine.
Le présent document est destiné à être mis en relation avec les Annexes ZA des Normes européennes traitant des liants hydrauliques routiers, à savoir l’EN 13282 1 et l’EN 13282 2.
NOTE   La raison pour laquelle ce document séparé a été rédigé est que les dispositions qu’il contient sont applicables à différents produits couverts par des Normes européennes différentes.

Hidravlična veziva za ceste - 3. del: Ocenjevanje in preverjanje nespremenljivosti lastnosti

General Information

Status
Not Published
Publication Date
28-Jan-2025
Current Stage
4599 - Dispatch of FV draft to CMC - Finalization for Vote
Start Date
18-Aug-2023
Due Date
30-Apr-2024
Completion Date
18-Aug-2023

Relations

Buy Standard

Draft
prEN 13282-3:2023
English language
12 pages
sale 10% off
Preview
sale 10% off
Preview
e-Library read for
1 day

Standards Content (Sample)

SLOVENSKI STANDARD
oSIST prEN 13282-3:2023
01-april-2023
Hidravlična veziva za ceste - 3. del: Ocenjevanje in preverjanje nespremenljivosti
lastnosti
Hydraulic road binders - Part 3: Assessment and verification of constancy of
performance
Hydraulische Tragschichtbinder - Teil 3: Bewertung und Überprüfung der
Leistungsbeständigkeit
Liants hydrauliques routiers - Partie 3: Évaluation et vérification de la constance des
performances
Ta slovenski standard je istoveten z: prEN 13282-3
ICS:
91.100.50 Veziva. Tesnilni materiali Binders. Sealing materials
93.080.20 Materiali za gradnjo cest Road construction materials
oSIST prEN 13282-3:2023 en,fr,de
2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.

---------------------- Page: 1 ----------------------
oSIST prEN 13282-3:2023

---------------------- Page: 2 ----------------------
oSIST prEN 13282-3:2023


DRAFT
EUROPEAN STANDARD
prEN 13282-3
NORME EUROPÉENNE

EUROPÄISCHE NORM

January 2023
ICS 93.080.20 Will supersede EN 13282-3:2015
English Version

Hydraulic road binders - Part 3: Assessment and
verification of constancy of performance
Liants hydrauliques routiers - Partie 3: Évaluation et Hydraulische Tragschichtbinder - Teil 3: Bewertung
vérification de la constance des performances und Überprüfung der Leistungsbeständigkeit
This draft European Standard is submitted to CEN members for enquiry. It has been drawn up by the Technical Committee
CEN/TC 51.

If this draft becomes a European Standard, CEN members are bound to comply with the CEN/CENELEC Internal Regulations
which stipulate the conditions for giving this European Standard the status of a national standard without any alteration.

This draft European Standard was established by CEN in three official versions (English, French, German). A version in any other
language made by translation under the responsibility of a CEN member into its own language and notified to the CEN-CENELEC
Management Centre has the same status as the official versions.

CEN members are the national standards bodies of Austria, Belgium, Bulgaria, Croatia, Cyprus, Czech Republic, Denmark, Estonia,
Finland, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta, Netherlands, Norway,
Poland, Portugal, Republic of North Macedonia, Romania, Serbia, Slovakia, Slovenia, Spain, Sweden, Switzerland, Türkiye and
United Kingdom.

Recipients of this draft are invited to submit, with their comments, notification of any relevant patent rights of which they are
aware and to provide supporting documentation.

Warning : This document is not a European Standard. It is distributed for review and comments. It is subject to change without
notice and shall not be referred to as a European Standard.


EUROPEAN COMMITTEE FOR STANDARDIZATION
COMITÉ EUROPÉEN DE NORMALISATION

EUROPÄISCHES KOMITEE FÜR NORMUNG

CEN-CENELEC Management Centre: Rue de la Science 23, B-1040 Brussels
© 2023 CEN All rights of exploitation in any form and by any means reserved Ref. No. prEN 13282-3:2023 E
worldwide for CEN national Members.

---------------------- Page: 3 ----------------------
oSIST prEN 13282-3:2023
prEN 13282-3:2023 (E)
Contents Page
European foreword . 3
1 Scope . 4
2 Normative references . 4
3 Terms and definitions . 4
4 Factory production control . 6
4.1 General requirements . 6
4.1.1 Concept . 6
4.1.2 Works' quality documentation. 6
4.1.3 Quality management system . 7
4.1.4 System of documentation . 7
4.2 Internal quality control. 7
4.2.1 Process control. 7
4.2.2 Measuring and testing . 8
4.2.3 Handling, storage, packaging and delivery . 8
5 Assessment of the performance of the hydraulic road binder . 8
6 Autocontrol testing of samples . 9
6.1 Sampling and testing . 9
6.2 Corrective action . 9
6.3 Measuring and test equipment for autocontrol testing . 9
6.4 Quality records . 9
7 Tasks for the purpose of certification . 10
7.1 Initial inspection of the manufacturing plant and the factory production control . 10
7.1.1 Inspection of a new factory . 10
7.1.2 Inspection of an existing factory . 10
7.1.3 Criteria for the assessment of the production equipment . 10
7.1.4 Criteria for the assessment of laboratories . 10
7.2 Continuing surveillance, assessment and evaluation of factory production control . 11
7.2.1 Inspection of the factory production control . 11
7.3 Reports . 11
7.4 Actions to be taken in the event of non-conformity . 11
8 Procedure for certification of conformity of the factory production control . 11
Bibliography . 12

2

---------------------- Page: 4 ----------------------
oSIST prEN 13282-3:2023
prEN 13282-3:2023 (E)
European foreword
This document (prEN 13282-3:2023) has been prepared by Technical Committee CEN/TC 51 “Cement
and building limes”, the secretariat of which is held by NBN.
This document is currently submitted to the CEN Enquiry.
This document will supersede EN 13282-3:2015.
This document has been prepared under a Standardization Request given to CEN by the European
Commission and the European Free Trade Association.
EN 13282, Hydraulic road binders consists of the following parts:
— Part 1: Rapid hardening hydraulic road binders — Composition, specifications and conformity criteria
— Part 2: Normal hardening hydraulic road binders — Composition, specifications and conformity
criteria
— Part 3: Assessment and verification of constancy of performance
Compared to the version EN 13282-3:2015, the following major changes have been included in this
document:
a) use of the terminology given by the Delegated Regulation (EU) No 568/2014 amending Annex V to
Regulation (EU) No 305/2011 (Construction Products Regulation), in particular adoption of the
tasks defined in the Delegated Regulation for AVCP system 1+ for a re-arrangement of the clauses of
this document;
b) numbering of the clauses according to the order of the tasks specified in this Delegated Regulation;
c) removal of the rules for dispatching centres;
d) clarification/specification of the rules for depots;
e) replacement of the term “Works’ quality manual” by “Works’ quality documentation”;
f) replacement of the term “management representative” by “quality manager”;
g) editorial revision of the document.
3

---------------------- Page: 5 ----------------------
oSIST prEN 13282-3:2023
prEN 13282-3:2023 (E)
1 Scope
This document specifies the scheme for the assessment and verification of constancy of performance
(AVCP) of hydraulic road binders, including certification of conformity of the factory production
control.
This document provides technical rules for factory production control, further testing of samples taken
at the manufacturing plant (autocontrol testing), assessment of the performance of the hydraulic road
binder, initial inspection of the manufacturing plant and of factory production control and continuing
surveillance, assessment and evaluation of factory production control.
This document is intended to be linked with the Annexes ZA of the European Standards covering
hydraulic road binders, i.e. EN 13282-1 and EN 13282-2.
NOTE The reason for having drafted this separate document is that the provisions it includes are applicable
to different products covered by different European Standards.
2 Normative references
The following documents are referred to in the text in such a way that some or all of their content
constitutes requirements of this document. For dated references, only the edition cited applies. For
undated references, the latest edition of the referenced document (including any amendments) applies.
EN 196-7, Methods of testing cement - Part 7: Methods of taking and preparing samples of cement
3 Terms and definitions
For the purposes of this document, the following terms and definitions apply.
ISO and IEC maintain terminology databases for use in standardization at the following addresses:
— IEC Electropedia: available at https://www.electropedia.org/
— ISO Online browsing platform: available at https://www.iso.org/obp
NOTE In the context of this document the term, “construction product” refers to hydraulic road binder.
3.1
AVCP
abbreviation for assessment and verification of constancy of performance
3.2
certificate of conformity of the factory production control
document issued under the rules of this scheme for the AVCP indicating that adequate confidence is
provided that factory production control is in conformity with the relevant product specification
standard
3.3
factory production control certification body
body notified in accordance with Chapter VII of Regulation (EU) No 305/2011 to carry out factory
production control certification
3.4
factory production control
documented, permanent and internal control of production in a factory, in accordance with the relevant
harmonised technical specifications
[SOURCE: Regulation (EU) No 305/2011, Article 2 (Construction Product Regulation)]
4

---------------------- Page: 6 ----------------------
oSIST prEN 13282-3:2023
prEN 13282-3:2023 (E)
3.5
factory
facility used by a manufacturer for the production of hydraulic road binders using equipment which is
suitable for continuous mass production of hydraulic road binder including, in particular, equipment for
adequate grinding and homogenisation and the necessary silo capacity for the storage and dispatch of
each hydraulic road binder produced
Note 1 to entry: This equipment and the production control applied allow the control of production with
sufficient accuracy.
3.6
new factory
factory for which the conformity of the factory production control has not been certified using this
European Standard
3.7
existing factory
factory for which the conformity of the factory production control has already been certified using this
European Standard
3.8
depot
bulk hydraulic road binder handling facility (not located at the factory) used for the dispatch of
hydraulic road binder, whether in bulk or bagged, after transfer or storage where the manufacturer has
full responsibility for all aspects of the quality of the hydraulic road binder
3.9
distributor
natural or legal person in the supply chain, other than the manufacturer or the importer, who makes a
construction product available on the market
[SOURCE: Regulation (EU) No 305/2011, Article 2 (Construction Product Regulation)]
3.10
importer
natural or legal person established within the European Union, who places a construction product from
a third country on the European Union market
[SOURCE: Regulation (EU) No 305/2011, Article 2 (Construction Product Regulation)]
3.11
assessment of the performance
determination of the essential characteristics of a construction product, on the basis of testing
(including sampling), calculation, tabulated values or descriptive documentation of the product
3.12
work's quality documentation
documentation that provides information on the factory production control which is applied by a
manufacturer at a particular factory to ensure constancy of performance of the hydraulic road binder
5

---------------------- Page: 7 ----------------------
oSIST prEN 13282-3:2023
prEN 13282-3:2023 (E)
4 Factory production control
4.1 General requirements
4.1.1 Concept
Factory production control means the permanent internal control of hydraulic road binder production
and consists of internal quality control (see 4.2) complemented by an assessment of the performance of
the hydraulic road binder on the basis of testing (including sampling) or descriptive documentation of
1
this product (see Clause 5) and by autocontrol testing of samples taken at the point of release
(see Clause 6).
NOTE 1 The requirements specified in this document as regards factory production control apply to factories
and their depots.
NOTE 2 The requirements of this European Standard as regards factory production control take account of
those clauses of EN ISO 9001 [3] which are relevant to the production, process control and testing of hydraulic
road binder.
4.1.2 Works' quality documentation
The manufacturer’s documentation and procedures for factory production control shall be described in
a Work's quality documentation, which shall adequately describe, among other things, for each factory
and depot:
a) the quality aims and the organizational structure, responsibilities and powers of the management
with regard to product quality and the means to monitor the achievement of the required product
quality and the effective operation of the internal quality control (see 4.1.3 and 4.2);
b) the manufacturing and quality control techniques, processes and systematic actions that will be
used (see 4.2.1, 4.2.2 and 6.2);
c) the inspections and tests that will be carried out before, during and after manufacture, and the
frequency with which they will be carried out (see 4.2.2, 6.1 and 6.3).
The Work's quality documentation shall include an adequate system of documentation (see 4.1.4 and
6.4).
The Work's quality documentation
...