Industrial communication networks - Profiles - Part 5-2: Installation of fieldbuses - Installation profiles for CPF 2

IEC 61784-5-2:2013 specifies the installation profiles for CPF 2 (CIPTM1). Each CP installation profile is specified in a separate annex of this standard. The IEC 61784 series is produced to facilitate the use of communication networks in industrial control systems. This third edition cancels and replaces the second edition published in 2010 and constitutes a technical revision. It includes the following changes:
- updates pertaining to current installation practices;
- addition of new technology that has become recently available;
- errors have been corrected;
- improved alignment with IEC 61918.
This publication is to be read in conjunction with  IEC 61918:2013.

Réseaux de communication industriels - Profils - Partie 5-2: Installation des bus de terrain - Profils d'installation pour CPF 2

La CEI 61784-5-2:2013 définit les profils d'installation pour la CPF 2 (CIPTM1). Chaque profil d'installation de CP est spécifié dans une annexe séparée de la présente norme. Cette norme fait partie d'une série élaborée pour faciliter l'utilisation des réseaux de communication dans des systèmes de contrôle-commande industriels. Cette troisième édition annule et remplace la deuxième édition publiée en 2010, dont elle constitue une révision technique. Cette édition inclut les modifications suivantes:
- mises à jour tenant compte des pratiques d'installation actuelles;
- ajout de nouvelles technologies devenues récemment disponibles;
- correction d'erreurs;
- meilleure adéquation avec la CEI 61918.
Cette publication doit être lue conjointement avec la  CEI 61918:2013.

General Information

Status
Published
Publication Date
08-Sep-2013
Technical Committee
Drafting Committee
Current Stage
DELPUB - Deleted Publication
Completion Date
30-Aug-2018
Ref Project

Relations

Buy Standard

Standard
IEC 61784-5-2:2013 - Industrial communication networks - Profiles - Part 5-2: Installation of fieldbuses - Installation profiles for CPF 2 Released:9/9/2013
English and French language
336 pages
sale 15% off
Preview
sale 15% off
Preview

Standards Content (Sample)

IEC 61784-5-2


®


Edition 3.0 2013-09



INTERNATIONAL



STANDARD



NORME
INTERNATIONALE
colour
inside


Industrial communication networks – Profiles –
Part 5-2: Installation of fieldbuses – Installation profiles for CPF 2

Réseaux de communication industriels – Profils –
Partie 5-2: Installation des bus de terrain – Profils d'installation pour CPF 2


IEC 61784-5-2:2013

---------------------- Page: 1 ----------------------
THIS PUBLICATION IS COPYRIGHT PROTECTED


Copyright © 2013 IEC, Geneva, Switzerland


All rights reserved. Unless otherwise specified, no part of this publication may be reproduced or utilized in any form

or by any means, electronic or mechanical, including photocopying and microfilm, without permission in writing from
either IEC or IEC's member National Committee in the country of the requester.
If you have any questions about IEC copyright or have an enquiry about obtaining additional rights to this publication,

please contact the address below or your local IEC member National Committee for further information.



Droits de reproduction réservés. Sauf indication contraire, aucune partie de cette publication ne peut être reproduite ni
utilisée sous quelque forme que ce soit et par aucun procédé, électronique ou mécanique, y compris la photocopie et les

microfilms, sans l'accord écrit de la CEI ou du Comité national de la CEI du pays du demandeur.

Si vous avez des questions sur le copyright de la CEI ou si vous désirez obtenir des droits supplémentaires sur cette

publication, utilisez les coordonnées ci-après ou contactez le Comité national de la CEI de votre pays de résidence.

IEC Central Office Tel.: +41 22 919 02 11
3, rue de Varembé Fax: +41 22 919 03 00
CH-1211 Geneva 20 info@iec.ch
Switzerland www.iec.ch

About the IEC
The International Electrotechnical Commission (IEC) is the leading global organization that prepares and publishes
International Standards for all electrical, electronic and related technologies.

About IEC publications
The technical content of IEC publications is kept under constant review by the IEC. Please make sure that you have the
latest edition, a corrigenda or an amendment might have been published.

Useful links:

IEC publications search - www.iec.ch/searchpub Electropedia - www.electropedia.org
The advanced search enables you to find IEC publications The world's leading online dictionary of electronic and
by a variety of criteria (reference number, text, technical electrical terms containing more than 30 000 terms and
committee,…). definitions in English and French, with equivalent terms in
It also gives information on projects, replaced and additional languages. Also known as the International
withdrawn publications. Electrotechnical Vocabulary (IEV) on-line.

IEC Just Published - webstore.iec.ch/justpublished Customer Service Centre - webstore.iec.ch/csc
Stay up to date on all new IEC publications. Just Published If you wish to give us your feedback on this publication
details all new publications released. Available on-line and or need further assistance, please contact the
also once a month by email. Customer Service Centre: csc@iec.ch.


A propos de la CEI
La Commission Electrotechnique Internationale (CEI) est la première organisation mondiale qui élabore et publie des
Normes internationales pour tout ce qui a trait à l'électricité, à l'électronique et aux technologies apparentées.

A propos des publications CEI
Le contenu technique des publications de la CEI est constamment revu. Veuillez vous assurer que vous possédez
l’édition la plus récente, un corrigendum ou amendement peut avoir été publié.


Liens utiles:

Recherche de publications CEI - www.iec.ch/searchpub Electropedia - www.electropedia.org
La recherche avancée vous permet de trouver des Le premier dictionnaire en ligne au monde de termes
publications CEI en utilisant différents critères (numéro de électroniques et électriques. Il contient plus de 30 000
référence, texte, comité d’études,…). termes et définitions en anglais et en français, ainsi que
Elle donne aussi des informations sur les projets et les les termes équivalents dans les langues additionnelles.
publications remplacées ou retirées. Egalement appelé Vocabulaire Electrotechnique
International (VEI) en ligne.
Just Published CEI - webstore.iec.ch/justpublished
Service Clients - webstore.iec.ch/csc
Restez informé sur les nouvelles publications de la CEI.
Just Published détaille les nouvelles publications parues. Si vous désirez nous donner des commentaires sur
Disponible en ligne et aussi une fois par mois par email. cette publication ou si vous avez des questions
contactez-nous: csc@iec.ch.

---------------------- Page: 2 ----------------------
IEC 61784-5-2



®



Edition 3.0 2013-09







INTERNATIONAL





STANDARD







NORME



INTERNATIONALE
colour

inside










Industrial communication networks – Profiles –

Part 5-2: Installation of fieldbuses – Installation profiles for CPF 2




Réseaux de communication industriels – Profils –

Partie 5-2: Installation des bus de terrain – Profils d'installation pour CPF 2

















INTERNATIONAL

ELECTROTECHNICAL

COMMISSION


COMMISSION

ELECTROTECHNIQUE

PRICE CODE
INTERNATIONALE

CODE PRIX XH


ICS 25.040.40; 35.100.40 ISBN 978-2-8322-1060-4



Warning! Make sure that you obtained this publication from an authorized distributor.

Attention! Veuillez vous assurer que vous avez obtenu cette publication via un distributeur agréé.

® Registered trademark of the International Electrotechnical Commission
Marque déposée de la Commission Electrotechnique Internationale

---------------------- Page: 3 ----------------------
– 2 – 61784-5-2 © IEC:2013


CONTENTS



FOREWORD . 9

INTRODUCTION . 11

1 Scope . 12


2 Normative references . 12

3 Terms, definitions and abbreviated terms . 12

4 CPF 2: Overview of installation profiles . 12


5 Installation profile conventions . 13
6 Conformance to installation profiles . 14
Annex A (normative) CP 2/1 (ControlNet™) specific installation profile . 15
A.1 Installation profile scope . 15
A.2 Normative references . 15
A.3 Installation profile terms, definitions, and abbreviated terms . 15
A.3.1 Terms and definitions . 15
A.3.2 Abbreviated terms . 15
A.3.3 Conventions for installation profiles . 15
A.4 Installation planning . 16
A.4.1 General . 16
A.4.2 Planning requirements . 17
A.4.3 Network capabilities . 18
A.4.4 Selection and use of cabling components . 24
A.4.5 Cabling planning documentation . 41
A.4.6 Verification of planning specification . 41
A.5 Installation implementation . 41
A.5.1 General requirements . 41
A.5.2 Cable installation . 41
A.5.3 Connector installation . 43
A.5.4 Terminator installation . 53
A.5.5 Device installation . 53
A.5.6 Coding and labelling . 55
A.5.7 Earthing and bonding of equipment and devices and shield cabling . 56
A.5.8 As-implemented cabling documentation . 57

A.6 Installation verification and installation acceptance test . 57
A.6.1 General . 57
A.6.2 Installation verification . 57
A.6.3 Installation acceptance test . 60
A.7 Installation administration . 62
A.8 Installation maintenance and installation troubleshooting . 62
A.8.1 General . 62
A.8.2 Maintenance . 62
A.8.3 Troubleshooting . 62
A.8.4 Specific requirements for maintenance and troubleshooting . 67
Annex B (normative) CP 2/2 (EtherNet/IP™) specific installation profile . 68
B.1 Installation profile scope . 68
B.2 Normative references . 68

---------------------- Page: 4 ----------------------
61784-5-2 © IEC:2013 – 3 –


B.3 Installation profile terms, definitions, and abbreviated terms . 68

B.3.1 Terms and definitions . 68


B.3.2 Abbreviated terms . 68

B.3.3 Conventions for installation profiles . 68

B.4 Installation planning . 69

B.4.1 General . 69

B.4.2 Planning requirements . 70

B.4.3 Network capabilities . 70


B.4.4 Selection and use of cabling components . 74

B.4.5 Cabling planning documentation . 86
B.4.6 Verification of cabling planning specification . 87
B.5 Installation implementation . 87
B.5.1 General requirements . 87
B.5.2 Cable installation . 87
B.5.3 Connector installation . 88
B.5.4 Terminator installation . 89
B.5.5 Device installation . 89
B.5.6 Coding and labelling . 89
B.5.7 Earthing and bonding of equipment and devices and shield cabling . 89
B.5.8 As-implemented cabling documentation . 91
B.6 Installation verification and installation acceptance test . 91
B.6.1 General . 91
B.6.2 Installation verification . 91
B.6.3 Installation acceptance test . 93
B.7 Installation administration . 94
B.8 Installation maintenance and installation troubleshooting . 94
Annex C (normative) CP 2/3 (DeviceNet™) specific installation profile . 95
C.1 Installation profile scope . 95
C.2 Normative references . 95
C.3 Installation profile terms, definitions, and abbreviated terms . 95
C.3.1 Terms and definitions . 95
C.3.2 Abbreviated terms . 95
C.3.3 Conventions for installation profiles . 95
C.4 Installation planning . 96

C.4.1 General . 96
C.4.2 Planning requirements . 97
C.4.3 Network capabilities . 98
C.4.4 Selection and use of cabling components . 112
C.4.5 Cabling planning documentation . 121
C.4.6 Verification of cabling planning specification . 121
C.5 Installation implementation . 121
C.5.1 General requirements . 121
C.5.2 Cable installation . 121
C.5.3 Connector installation . 124
C.5.4 Terminator installation . 136
C.5.5 Device installation . 138
C.5.6 Coding and labelling . 141

---------------------- Page: 5 ----------------------
– 4 – 61784-5-2 © IEC:2013


C.5.7 Earthing and bonding of equipment and devices and shield cabling . 141

C.5.8 As-implemented cabling documentation . 142

C.6 Installation verification and installation acceptance test . 142


C.6.1 General . 142

C.6.2 Installation verification . 142

C.6.3 Installation acceptance test . 145

C.7 Installation administration . 146

C.8 Installation maintenance and installation troubleshooting . 146


C.8.1 General . 146

C.8.2 Maintenance . 146
C.8.3 Troubleshooting . 146
C.8.4 Specific requirements for maintenance and troubleshooting . 146
Annex D (informative) Additional information . 150
D.1 Network validation check sheet for CP 2/3 (DeviceNet) . 150
Bibliography . 154

Figure 1 – Standards relationships . 11
Figure A.1 – Interconnection of CPF 2 networks . 16
Figure A.2 – Overview of CPF 2/1 networks . 17
Figure A.3 – Drop cable requirements . 19
Figure A.4 – Placement of BNC/TNC plugs . 19
Figure A.5 – Placement of terminators . 20
Figure A.6 – Extending a network using repeaters . 20
Figure A.7 – Extending a network using active star topology . 21
Figure A.8 – Links . 21
Figure A.9 – Extending the network beyond 99 nodes . 22
Figure A.10 – Maximum allowable taps per segment . 30
Figure A.11 – Example of repeaters in star configuration . 31
Figure A.12 – Repeaters in parallel . 32
Figure A.13 – Repeaters in combination series and parallel . 33
Figure A.14 – Ring repeater . 33
Figure A.15 – Installing bulkheads . 34

Figure A.16 – Coaxial BNC and TNC terminators . 35
Figure A.17 – Terminator placement in a segment . 35
Figure A.18 – Redundant network icons . 37
Figure A.19 – Redundant coax media . 38
Figure A.20 – Redundant fibre media . 38
Figure A.21 – Repeaters in series versus length difference for coax media . 39
Figure A.22 – Repeaters in series versus length difference for fibre media . 39
Figure A.23 – Example of redundant coax network with repeaters . 40
Figure A.24 – Example of improper redundant node connection . 40
Figure A.25 – Example tool kit for installing BNC connectors . 44
Figure A.26 – Calibration of coaxial stripper . 45
Figure A.27 – Coax PVC strip length detail (informative) . 45

---------------------- Page: 6 ----------------------
61784-5-2 © IEC:2013 – 5 –


Figure A.28 – Memory cartridge and blade . 46

Figure A.29 – Cable position . 47


Figure A.30 – Locking the cable . 47

Figure A.31 – Stripping the cable . 47

Figure A.32 – Install the crimp ferrule . 48


Figure A.33 – Cable preparation for PVC type cables (informative) . 48

Figure A.34 – Cable preparation for FEP type cables (informative) . 49

Figure A.35 – Strip guides . 49


Figure A.36 – Using the flare tool . 50
Figure A.37 – Expanding the shields . 50
Figure A.38 – Install the centre pin . 50
Figure A.39 – Crimping the centre pin . 51
Figure A.40 – Installing the connector body . 51
Figure A.41 – Installing the ferrule . 51
Figure A.42 – Crimp tool . 52
Figure A.43 – Sealed IP65/67 cable . 53
Figure A.44 – Terminator placement . 53
Figure A.45 – Mounting the taps . 54
Figure A.46 – Mounting the tap assembly using the universal mounting bracket . 55
Figure A.47 – Mounting the tap using tie wraps or screws . 55
Figure A.48 – Redundant network icons . 56
Figure A.49 – Network test tool . 58
Figure A.50 – Shorting the cable to test for continuity . 59
Figure A.51 – Testing fibre segments . 61
Figure A.52 – Multi-fibre backbone cable housing . 63
Figure A.53 – Repeater adapter module . 63
Figure A.54 – Short and medium distance fibre module LEDs . 65
Figure A.55 – Long and extra long repeater module LEDs . 66
Figure B.1 – Interconnection of CPF 2 networks . 69
Figure B.2 – Redundant linear bus . 71
Figure B.3 – Peer to peer connections . 71

Figure B.4 – Mated connections . 74
Figure B.5 – The 8-way modular sealed jack & plug (plastic housing) . 78
Figure B.6 – The 8-way modular sealed jack & plug (metal housing) . 79
Figure B.7 – M12-4 connectors . 79
Figure B.8 – Simplex LC connector . 80
Figure B.9 – Duplex LC connector . 80
Figure B.10 – IP65/67 sealed duplex LC connector . 81
Figure B.11 – IP65/67 sealed duplex SC-RJ connector . 81
Figure B.12 – M12-4 to 8-way modular bulkhead . 83
Figure B.13 – The 8-way modular sealed jack & plug (plastic housing) . 88
Figure B.14 – The 8-way modular sealed jack & plug (metal housing) . 89
Figure B.15 – M12-4 connectors . 89

---------------------- Page: 7 ----------------------
– 6 – 61784-5-2 © IEC:2013


Figure B.16 – Earthing of cable shield . 91

Figure C.1 – Interconnection of CPF 2 networks . 96


Figure C.2 – Connection to generic cabling . 97

Figure C.3 – DeviceNet cable system uses a trunk/drop line topology . 98

Figure C.4 – Measuring the trunk length . 100


Figure C.5 – Measuring the trunk and drop length . 101

Figure C.6 – Measuring drop cable in a network with multiports . 101

Figure C.7 – Removable device using open-style connectors . 102


Figure C.8 – Fixed connection using open-style connector . 102
Figure C.9 – Open-style connector pin out . 102
Figure C.10 – Open-style connector pin out 10 position . 103
Figure C.11 – Power supply sizing example . 106
Figure C.12 – Current limit for thick cable for one power supply . 107
Figure C.13 – Current limit for thick cable and two power supplies . 108
Figure C.14 – Worst case scenario . 109
Figure C.15 – Example using the lookup method . 109
Figure C.16 – One power supply end connected .
...

Questions, Comments and Discussion

Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.