Planning for functional performance testing for building commissioning — Part 1: Secondary hydronic pump, system and associated controls

This document specifies a planning method for functional performance testing (FPT). This document is applicable to the planning of the FPT during the design phase of new buildings and retrofit projects, which is defined in ISO 16813. This document establishes how to design building environmental systems when the FPT is being carried out. This document defines the following: — what kind of information regarding the system is required (for example, design documents, drawings and product specifications); — what kind of data should be measured (though concrete measurement techniques are not specified in this document); — how the measured data is analysed. Such clear definition of the FPT makes it possible for building designers to prepare and plan for FPT throughout the design process. This document specifies an FPT method for secondary hydronic pump, system and associated controls in heating, ventilation and air conditioning (HVAC) systems.

Planification des essais de performance fonctionnelle pour la mise en service des bâtiments — Partie 1: Titre manque

General Information

Status
Published
Publication Date
14-Nov-2019
Current Stage
9020 - International Standard under periodical review
Start Date
15-Oct-2024
Completion Date
15-Oct-2024
Ref Project

Buy Standard

Standard
ISO 19455-1:2019 - Planning for functional performance testing for building commissioning
English language
14 pages
sale 15% off
Preview
sale 15% off
Preview
Standard
ISO 19455-1:2019 - Planning for functional performance testing for building commissioning — Part 1: Secondary hydronic pump, system and associated controls Released:11/15/2019
English language
14 pages
sale 15% off
Preview
sale 15% off
Preview

Standards Content (Sample)


INTERNATIONAL ISO
STANDARD 19455-1
First edition
2019-11
Planning for functional performance
testing for building commissioning —
Part 1:
Secondary hydronic pump, system and
associated controls
Reference number
©
ISO 2019
© ISO 2019
All rights reserved. Unless otherwise specified, or required in the context of its implementation, no part of this publication may
be reproduced or utilized otherwise in any form or by any means, electronic or mechanical, including photocopying, or posting
on the internet or an intranet, without prior written permission. Permission can be requested from either ISO at the address
below or ISO’s member body in the country of the requester.
ISO copyright office
CP 401 • Ch. de Blandonnet 8
CH-1214 Vernier, Geneva
Phone: +41 22 749 01 11
Fax: +41 22 749 09 47
Email: copyright@iso.org
Website: www.iso.org
Published in Switzerland
ii © ISO 2019 – All rights reserved

Contents Page
Foreword .iv
Introduction .v
1 Scope . 1
2 Normative references . 1
3 Terms and definitions . 1
4 Planning for functional performance testing . 3
4.1 Design of secondary hydronic pump system . 3
4.2 Data acquisition . 3
5 Functional performance testing method. 8
5.1 General . 8
5.2 Testing method for verifying relationship between water flow rate and number of
operating units (test 1) . 9
5.2.1 General. 9
5.2.2 Step 1) Measurement of operational data . 9
5.2.3 Step 2) Calculation of number of operating pumps . 9
5.2.4 Step 3) Analysis of relationship between water flow rate and number of
operation units . 9
5.2.5 Step 4) Clarification of the design specification . 9
5.2.6 Step 5) Comparison with the design values .10
5.3 Testing method for verifying relationship between water flow rate and pressure
(test 2, 3) .10
5.3.1 General.10
5.3.2 Step 1) Measurement of operational data .10
5.3.3 Step 2) Analysis of relationship between water flow rate and pressure .11
5.3.4 Step 3) Clarification of the design specification .11
5.3.5 Step 4) Comparison with the design values .11
5.4 Testing method for verifying relationship between water flow rate and energy
consumption (test 4) .11
5.4.1 General.11
5.4.2 Step 1) Measurement of operational data .12
5.4.3 Step 2) Analysis of relationship between water flow rate and energy
consumption .12
5.4.4 Step 3) Clarification of the design specification .12
5.4.5 Step 4) Comparison with the design values .12
Annex A (informative) Data acquisition planning .13
Bibliography .14
Foreword
ISO (the International Organization for Standardization) is a worldwide federation of national standards
bodies (ISO member bodies). The work of preparing International Standards is normally carried out
through ISO technical committees. Each member body interested in a subject for which a technical
committee has been established has the right to be represented on that committee. International
organizations, governmental and non-governmental, in liaison with ISO, also take part in the work.
ISO collaborates closely with the International Electrotechnical Commission (IEC) on all matters of
electrotechnical standardization.
The procedures used to develop this document and those intended for its further maintenance are
described in the ISO/IEC Directives, Part 1. In particular, the different approval criteria needed for the
different types of ISO documents should be noted. This document was drafted in accordance with the
editorial rules of the ISO/IEC Directives, Part 2 (see www .iso .org/ directives).
Attention is drawn to the possibility that some of the elements of this document may be the subject of
patent rights. ISO shall not be held responsible for identifying any or all such patent rights. Details of
any patent rights identified during the development of the document will be in the Introduction and/or
on the ISO list of patent declarations received (see www .iso .org/ patents).
Any trade name used in this document is information given for the convenience of users and does not
constitute an endorsement.
For an explanation of the voluntary nature of standards, the meaning of ISO specific terms and
expressions related to conformity assessment, as well as information about ISO's adherence to the
World Trade Organization (WTO) principles in the Technical Barriers to Trade (TBT) see www .iso .org/
iso/ foreword .html.
This document was prepared by Technical Committee ISO/TC 205, Building environment design.
A list of all parts in the ISO 19455 series can be found on the ISO website.
Any feedback or questions on this document should be directed to the user’s national standards body. A
complete listing of these bodies can be found at www .iso .org/ members .html.
iv © ISO 2019 – All rights reserved

Introduction
This document gives a methodology of planning for functional performance testing of secondary
hydronic pump, system and associated controls for building commissioning, and has been prepared for
building designers, i.e. architects, environmental designers and building system designers, as well as
building clients, contractors, commissioning providers, government officials, and academic staff.
The aim of this document is to assist the building designers in applying a commissioning plan and a
commissioning test, which are defined in ISO 16813. In order to achieve effective energy saving
in building equipment systems that consume a large amount of energy, it is important not only to
introduce energy efficient technologies to the system but also to verify their functional performance by
tests and adjustments after the completion whether the system works properly according to its design
intent. This document makes it possible to verify performance of secondary hydronic pump, system
and associated controls with clear and specific processes.
As well as the intended usage for heating, ventilation and air conditioning (HVAC) systems, the
secondary hydronic pump system targeted by this document is described in Figure 1.
Key
A farthest air handling unit 1 dPw_AHU: end-pressure difference (in Pa)
B air handling units 2 Tw_AHUin: inlet water temperature of air handling
o
units (in C)
C valve 3 Tw_AHUout: outlet water temperature of air handling
o
units (in C)
D secondary hydronic pumps 4 Vw_AHUout: water flow rate of air handling units
(in kg/s)
E reserve hydronic pumps 5 Qw _AHU: amount of heat exchanged in air handling
units (in kW)
F inverter 6 Pw_PSout: supply-side pressure (in Pa)
G heat source equipment 7 dPw_PS: pump pressure difference (in Pa)
H primary hydronic pump 8 Vw_PS: water flow rate of each secondary hydronic
pump (in kg/s)
9 E_PS: energy consumption of each secondary
hydronic pump (in kW)
Figure 1 — Secondary hydronic pump system targeted by this document
vi © ISO 2019 – All rights reserved

INTERNATIONAL STANDARD ISO 19455-1:2019(E)
Planning for functional performance testing for building
commissioning —
Part 1:
Secondary hydronic pump, system and associated controls
1 Scope
This document specifies a planning method for functional performance testing (FPT). This document
is applicable to the planning of the FPT during the design phase of new buildings and retrofit projects,
which is defined in ISO 16813.
This document establishes how to design building environmental systems when the FPT is being
carried out. This document defines the following:
— what kind of information regarding the system is required (for example, design documents,
drawings and product specifications);
— what kind of data should be measured (though concrete measurement techniques are not specified
in this document);
— how the measured data is analysed.
Such clear definition of the FPT makes it possible for building designers to prepare and plan for FPT
throughout the design process.
This document specifies an FPT method for secondary hydronic pump, system and associated controls
in heating, ventilation and air conditioning (HVAC) systems.
2 Normative references
The following documents are referred to in the text in such a way that some or all of their content
constitutes requirements of this document. For dated references, only the edition cited applies. For
undated references, the latest edition of the referenced document (including any amendments) applies.
ISO 16813, Building environment design — Indoor environment — General principles
ISO 16484-1, Building automation and control systems (BACS) — Part 1: Project specification and
implementation
3 Terms and definitions
For the purposes of this document, the terms and definitions given in ISO 16813, ISO 16484-1 and the
following apply.
ISO and IEC maintain terminological databases for use in standardization at the following addresses:
— ISO Online browsing platform: available at https:// www .iso .org/ obp
— IEC Electropedia: available at http:// www .electropedia .org/
3.1
basis of design
BoD
document that bridges the objectives conveyed in the owner project requirements (3.5) and the contract
documents (construction drawings and project specifications) which records through narrative, lists
and calculations, the technical concepts, performance, assumptions, decisions, and product selections
that fulfil the requirements of the owner project requirements
3.2
building control system
measures taken to ensure the system operates in accordance with the specified conditions
3.3
commissioning
quality-focused process for enhancing the delivery of a project which focuses upon verifying and
documenting that all of the commissioned systems and assemblies are planned, designed, installed,
tested, operated, and maintained to meet the owner project requirements (3.5)
3.4
design document
written description of the essential factors of every design stage, to be retained for future reference
3.5
owner project requirement
OPR
written document that details the ideas, concepts, and criteria that are required by the owner and
...


INTERNATIONAL ISO
STANDARD 19455-1
First edition
2019-11
Planning for functional performance
testing for building commissioning —
Part 1:
Secondary hydronic pump, system and
associated controls
Reference number
©
ISO 2019
© ISO 2019
All rights reserved. Unless otherwise specified, or required in the context of its implementation, no part of this publication may
be reproduced or utilized otherwise in any form or by any means, electronic or mechanical, including photocopying, or posting
on the internet or an intranet, without prior written permission. Permission can be requested from either ISO at the address
below or ISO’s member body in the country of the requester.
ISO copyright office
CP 401 • Ch. de Blandonnet 8
CH-1214 Vernier, Geneva
Phone: +41 22 749 01 11
Fax: +41 22 749 09 47
Email: copyright@iso.org
Website: www.iso.org
Published in Switzerland
ii © ISO 2019 – All rights reserved

Contents Page
Foreword .iv
Introduction .v
1 Scope . 1
2 Normative references . 1
3 Terms and definitions . 1
4 Planning for functional performance testing . 3
4.1 Design of secondary hydronic pump system . 3
4.2 Data acquisition . 3
5 Functional performance testing method. 8
5.1 General . 8
5.2 Testing method for verifying relationship between water flow rate and number of
operating units (test 1) . 9
5.2.1 General. 9
5.2.2 Step 1) Measurement of operational data . 9
5.2.3 Step 2) Calculation of number of operating pumps . 9
5.2.4 Step 3) Analysis of relationship between water flow rate and number of
operation units . 9
5.2.5 Step 4) Clarification of the design specification . 9
5.2.6 Step 5) Comparison with the design values .10
5.3 Testing method for verifying relationship between water flow rate and pressure
(test 2, 3) .10
5.3.1 General.10
5.3.2 Step 1) Measurement of operational data .10
5.3.3 Step 2) Analysis of relationship between water flow rate and pressure .11
5.3.4 Step 3) Clarification of the design specification .11
5.3.5 Step 4) Comparison with the design values .11
5.4 Testing method for verifying relationship between water flow rate and energy
consumption (test 4) .11
5.4.1 General.11
5.4.2 Step 1) Measurement of operational data .12
5.4.3 Step 2) Analysis of relationship between water flow rate and energy
consumption .12
5.4.4 Step 3) Clarification of the design specification .12
5.4.5 Step 4) Comparison with the design values .12
Annex A (informative) Data acquisition planning .13
Bibliography .14
Foreword
ISO (the International Organization for Standardization) is a worldwide federation of national standards
bodies (ISO member bodies). The work of preparing International Standards is normally carried out
through ISO technical committees. Each member body interested in a subject for which a technical
committee has been established has the right to be represented on that committee. International
organizations, governmental and non-governmental, in liaison with ISO, also take part in the work.
ISO collaborates closely with the International Electrotechnical Commission (IEC) on all matters of
electrotechnical standardization.
The procedures used to develop this document and those intended for its further maintenance are
described in the ISO/IEC Directives, Part 1. In particular, the different approval criteria needed for the
different types of ISO documents should be noted. This document was drafted in accordance with the
editorial rules of the ISO/IEC Directives, Part 2 (see www .iso .org/ directives).
Attention is drawn to the possibility that some of the elements of this document may be the subject of
patent rights. ISO shall not be held responsible for identifying any or all such patent rights. Details of
any patent rights identified during the development of the document will be in the Introduction and/or
on the ISO list of patent declarations received (see www .iso .org/ patents).
Any trade name used in this document is information given for the convenience of users and does not
constitute an endorsement.
For an explanation of the voluntary nature of standards, the meaning of ISO specific terms and
expressions related to conformity assessment, as well as information about ISO's adherence to the
World Trade Organization (WTO) principles in the Technical Barriers to Trade (TBT) see www .iso .org/
iso/ foreword .html.
This document was prepared by Technical Committee ISO/TC 205, Building environment design.
A list of all parts in the ISO 19455 series can be found on the ISO website.
Any feedback or questions on this document should be directed to the user’s national standards body. A
complete listing of these bodies can be found at www .iso .org/ members .html.
iv © ISO 2019 – All rights reserved

Introduction
This document gives a methodology of planning for functional performance testing of secondary
hydronic pump, system and associated controls for building commissioning, and has been prepared for
building designers, i.e. architects, environmental designers and building system designers, as well as
building clients, contractors, commissioning providers, government officials, and academic staff.
The aim of this document is to assist the building designers in applying a commissioning plan and a
commissioning test, which are defined in ISO 16813. In order to achieve effective energy saving
in building equipment systems that consume a large amount of energy, it is important not only to
introduce energy efficient technologies to the system but also to verify their functional performance by
tests and adjustments after the completion whether the system works properly according to its design
intent. This document makes it possible to verify performance of secondary hydronic pump, system
and associated controls with clear and specific processes.
As well as the intended usage for heating, ventilation and air conditioning (HVAC) systems, the
secondary hydronic pump system targeted by this document is described in Figure 1.
Key
A farthest air handling unit 1 dPw_AHU: end-pressure difference (in Pa)
B air handling units 2 Tw_AHUin: inlet water temperature of air handling
o
units (in C)
C valve 3 Tw_AHUout: outlet water temperature of air handling
o
units (in C)
D secondary hydronic pumps 4 Vw_AHUout: water flow rate of air handling units
(in kg/s)
E reserve hydronic pumps 5 Qw _AHU: amount of heat exchanged in air handling
units (in kW)
F inverter 6 Pw_PSout: supply-side pressure (in Pa)
G heat source equipment 7 dPw_PS: pump pressure difference (in Pa)
H primary hydronic pump 8 Vw_PS: water flow rate of each secondary hydronic
pump (in kg/s)
9 E_PS: energy consumption of each secondary
hydronic pump (in kW)
Figure 1 — Secondary hydronic pump system targeted by this document
vi © ISO 2019 – All rights reserved

INTERNATIONAL STANDARD ISO 19455-1:2019(E)
Planning for functional performance testing for building
commissioning —
Part 1:
Secondary hydronic pump, system and associated controls
1 Scope
This document specifies a planning method for functional performance testing (FPT). This document
is applicable to the planning of the FPT during the design phase of new buildings and retrofit projects,
which is defined in ISO 16813.
This document establishes how to design building environmental systems when the FPT is being
carried out. This document defines the following:
— what kind of information regarding the system is required (for example, design documents,
drawings and product specifications);
— what kind of data should be measured (though concrete measurement techniques are not specified
in this document);
— how the measured data is analysed.
Such clear definition of the FPT makes it possible for building designers to prepare and plan for FPT
throughout the design process.
This document specifies an FPT method for secondary hydronic pump, system and associated controls
in heating, ventilation and air conditioning (HVAC) systems.
2 Normative references
The following documents are referred to in the text in such a way that some or all of their content
constitutes requirements of this document. For dated references, only the edition cited applies. For
undated references, the latest edition of the referenced document (including any amendments) applies.
ISO 16813, Building environment design — Indoor environment — General principles
ISO 16484-1, Building automation and control systems (BACS) — Part 1: Project specification and
implementation
3 Terms and definitions
For the purposes of this document, the terms and definitions given in ISO 16813, ISO 16484-1 and the
following apply.
ISO and IEC maintain terminological databases for use in standardization at the following addresses:
— ISO Online browsing platform: available at https:// www .iso .org/ obp
— IEC Electropedia: available at http:// www .electropedia .org/
3.1
basis of design
BoD
document that bridges the objectives conveyed in the owner project requirements (3.5) and the contract
documents (construction drawings and project specifications) which records through narrative, lists
and calculations, the technical concepts, performance, assumptions, decisions, and product selections
that fulfil the requirements of the owner project requirements
3.2
building control system
measures taken to ensure the system operates in accordance with the specified conditions
3.3
commissioning
quality-focused process for enhancing the delivery of a project which focuses upon verifying and
documenting that all of the commissioned systems and assemblies are planned, designed, installed,
tested, operated, and maintained to meet the owner project requirements (3.5)
3.4
design document
written description of the essential factors of every design stage, to be retained for future reference
3.5
owner project requirement
OPR
written document that details the ideas, concepts, and criteria that are required by the owner and
...