Guide for procurement of power station equipment -- Part 6-9: Turbine auxiliaries - Cooling water systems

This standard gives guidance on writing the technical specification for the procurement of main and auxiliary cooling water systems for use in electricity generating stations (power stations). This Guide for procurement is not applicable to equipment for use in the nuclear reactor plant area of nuclear power stations. Other possible applications of such equipment have not been considered in the preparation of this Guide. This Guide covers: - pump intake screening plant (coarse and fine screens) and associated cleaning systems; - pressure filters; - pipework and valves; - penstock gates; - priming and venting equipment;...

Leitfaden für die Beschaffung von Ausrüstungen für Kraftwerke -- Teil 6-9: Turbinenhilfseinrichtungen - Kühlwassersysteme

Die vorliegende Norm ist eine Anleitung zur Erstellung der technischen Spezifikation für die Beschaffung von Haupt- und Nebenkühlwassersystemen für den Einsatz in Anlagen zur Erzeugung von elektrischer Energie (Kraftwerke). Dieser Leitfaden ist nicht anwendbar auf Ausrüstung zur Verwendung im Nuklearbereich von Kernkraftwerken. Bei der Erstellung des Leitfadens wurden keine weiteren Möglichkeiten zur Anwendung der beschriebenen Ausrüstung in Betracht gezogen. Dieser Leitfaden bezieht sich auf: - Rechenanlage im Kühlwassereinlauf (Grob- und Feinrechen) und damit verbundene Reinigungsanlagen; - Druckfilter;...

Guide pour l'acquisition d'équipements destinés aux centrales de production d'électricité -- Partie 6-9: Auxiliaires de turbine - Systèmes d'eau de refroidissement

La présente norme donne des recommandations pour la rédaction de la spécification technique nécessaire à l'acquisition des systèmes d'eau de refroidissement principaux et auxiliaires pour les centrales de production d'électricité. Ce guide d'achat n'est pas applicable à ce type d'équipement lorsque celui-ci est destiné à l'îlot nucléaire des centrales nucléaires. D'autres applications possibles de ce type d'équipement n'ont pas été prises en considération dans la préparation de ce guide.

Guide for procurement of power station equipment - Part 6-9: Turbine auxiliaries - Cooling water systems

General Information

Status
Published
Publication Date
31-May-2000
Technical Committee
Current Stage
6060 - National Implementation/Publication (Adopted Project)
Start Date
01-Jun-2000
Due Date
01-Jun-2000
Completion Date
01-Jun-2000

Buy Standard

Standard
EN 45510-6-9:2000
English language
25 pages
sale 10% off
Preview
sale 10% off
Preview
e-Library read for
1 day

Standards Content (Sample)

2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.Guide for procurement of power station equipment - Part 6-9: Turbine auxiliaries - Cooling water systemsLeitfaden für die Beschaffung von Ausrüstungen für Kraftwerke -- Teil 6-9: Turbinenhilfseinrichtungen - KühlwassersystemeGuide pour l'acquisition d'équipements destinés aux centrales de production d'électricité -- Partie 6-9: Auxiliaires de turbine - Systèmes d'eau de refroidissementGuide for procurement of power station equipment -- Part 6-9: Turbine auxiliaries - Cooling water systems27.100Elektrarne na splošnoPower stations in general27.040Plinske in parne turbine. Parni strojiGas and steam turbines. Steam enginesICS:Ta slovenski standard je istoveten
...

Questions, Comments and Discussion

Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.