SIST EN IEC 62381:2024
(Main)Automation systems in the process industry - Factory acceptance test (FAT), site acceptance test (SAT), and site integration test (SIT) (IEC 62381:2024)
Automation systems in the process industry - Factory acceptance test (FAT), site acceptance test (SAT), and site integration test (SIT) (IEC 62381:2024)
IEC 62381:2024 defines requirements and checklists for the factory acceptance test (FAT), the factory integration test (FIT), the site acceptance test (SAT), and the site integration test (SIT). These tests are carried out to demonstrate that the automation system meets the requirements of the applicable specification. This document provides a means for all parties, including the owner, the buyer, and the vendor, to clearly establish and agree on the scope of activities and responsibilities involved in performing these tests in order to achieve a timely delivery and acceptance of the automation system. The activities specified in this document can be used to develop test plans adapted to the specific requirements of the process/plant/equipment. The annexes of this document contain checklists which are available for consideration when preparing specific test procedures and documentation for a specific automation system.
This edition includes the following significant technical changes with respect to the previous edition:
a) General re-organization of the standard;
b) Current technology incorporated;
c) Optional factory integration test (FIT) added;
d) Replaced the forms in the annexes with detailed checklists of activities which can be used to develop project-specific test plans; and
e) Provided additional references to other applicable standards.
Automatisierungssysteme in der verfahrenstechnischen Industrie - Werksabnahme (FAT), Abnahme der installierten Anlage (SAT) und Integrationstest (SIT) (IEC 62381:2024)
Systèmes d'automatisation pour les procédés industriels - Essais d'acceptation en usine (FAT), essais d'acceptation sur site (SAT) et essais d'intégration sur site (SIT) (IEC 62381:2024)
L'IEC 62381:2024 définit les exigences et les listes de contrôle pour les essais d'acceptation en usine (FAT – factory acceptance test), les essais d’intégration en usine (FIT – factory integration test), les essais d'acceptation sur site (SAT – site acceptance test) et les essais d'intégration sur site (SIT – site integration test). Ces essais sont réalisés pour démontrer que le système d'automatisation satisfait aux exigences de la spécification applicable. Le présent document a pour objet de permettre à toutes les parties, y compris le maître d’ouvrage, l’acheteur et le fournisseur, de définir clairement et de convenir de l’étendue des activités et des responsabilités liées à l'exécution de ces essais, afin de finaliser la livraison et l'acceptation des systèmes d’automatisation dans les délais prévus. Les activités décrites dans le présent document peuvent être utilisées pour élaborer des plans d’essai adaptés aux exigences spécifiques du processus, de l'usine ou de l'équipement. Les annexes du présent document contiennent des listes de contrôle qui peuvent être prises en considération lors de l’élaboration des procédures et documents d’essai spécifiques pour un système d’automatisation particulier.
Les principales modifications par rapport à l'édition précédente sont les suivantes:
a) réorganisation générale de la norme;
b) intégration de la technologie actuelle;
c) ajout d’un essai d’intégration en usine (FIT) facultatif;
d) remplacement des formulaires dans les annexes par des listes de contrôle détaillées d’activités qui peuvent être utilisées pour élaborer des plans d’essai spécifiques à un projet; et
e) ajout de références supplémentaires à d’autres normes applicables.
Avtomatizacijski sistemi v procesni industriji - Tovarniški prevzemni preskus (FAT), prevzemni preskus pri prevzemniku (SAT) in preskus integracije pri prevzemniku (SIT) (IEC 62381:2024)
General Information
Relations
Standards Content (Sample)
SLOVENSKI STANDARD
01-december-2024
Avtomatizacijski sistemi v procesni industriji - Tovarniški prevzemni preskus
(FAT), prevzemni preskus pri prevzemniku (SAT) in preskus integracije pri
prevzemniku (SIT) (IEC 62381:2024)
Automation systems in the process industry - Factory acceptance test (FAT), site
acceptance test (SAT), and site integration test (SIT) (IEC 62381:2024)
Automatisierungssysteme in der verfahrenstechnischen Industrie - Werksabnahme
(FAT), Abnahme der installierten Anlage (SAT) und Integrationstest (SIT) (IEC
62381:2024)
Systèmes d'automatisation pour les procédés industriels - Essais d'acceptation en usine
(FAT), essais d'acceptation sur site (SAT) et essais d'intégration sur site (SIT) (IEC
62381:2024)
Ta slovenski standard je istoveten z: EN IEC 62381:2024
ICS:
25.040.40 Merjenje in krmiljenje Industrial process
industrijskih postopkov measurement and control
2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.
EUROPEAN STANDARD EN IEC 62381
NORME EUROPÉENNE
EUROPÄISCHE NORM September 2024
ICS 25.040.40 Supersedes EN 62381:2012
English Version
Automation systems in the process industry - Factory
acceptance test (FAT), site acceptance test (SAT), and site
integration test (SIT)
(IEC 62381:2024)
Systèmes d'automatisation dans l'industrie de Automatisierungssysteme in der verfahrenstechnischen
transformation - Essais d'acceptation en usine (FAT), Industrie - Werksabnahme (FAT), Abnahme der installierten
essais d'acceptation sur site (SAT) et essais d'intégration Anlage (SAT) und Integrationstest (SIT)
sur site (SIT) (IEC 62381:2024)
(IEC 62381:2024)
This European Standard was approved by CENELEC on 2024-09-03. CENELEC members are bound to comply with the CEN/CENELEC
Internal Regulations which stipulate the conditions for giving this European Standard the status of a national standard without any alteration.
Up-to-date lists and bibliographical references concerning such national standards may be obtained on application to the CEN-CENELEC
Management Centre or to any CENELEC member.
This European Standard exists in three official versions (English, French, German). A version in any other language made by translation
under the responsibility of a CENELEC member into its own language and notified to the CEN-CENELEC Management Centre has the
same status as the official versions.
CENELEC members are the national electrotechnical committees of Austria, Belgium, Bulgaria, Croatia, Cyprus, the Czech Republic,
Denmark, Estonia, Finland, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta, the
Netherlands, Norway, Poland, Portugal, Republic of North Macedonia, Romania, Serbia, Slovakia, Slovenia, Spain, Sweden, Switzerland,
Türkiye and the United Kingdom.
European Committee for Electrotechnical Standardization
Comité Européen de Normalisation Electrotechnique
Europäisches Komitee für Elektrotechnische Normung
CEN-CENELEC Management Centre: Rue de la Science 23, B-1040 Brussels
© 2024 CENELEC All rights of exploitation in any form and by any means reserved worldwide for CENELEC Members.
Ref. No. EN IEC 62381:2024 E
European foreword
The text of document 65E/1080/FDIS, future edition 3 of IEC 62381, prepared by SC 65E "Devices
and integration in enterprise systems" of IEC/TC 65 "Industrial-process measurement, control and
automation" was submitted to the IEC-CENELEC parallel vote and approved by CENELEC as
The following dates are fixed:
• latest date by which the document has to be implemented at national (dop) 2025-06-03
level by publication of an identical national standard or by endorsement
• latest date by which the national standards conflicting with the (dow) 2027-09-03
document have to be withdrawn
This document supersedes EN 62381:2012 and all of its amendments and corrigenda (if any).
Attention is drawn to the possibility that some of the elements of this document may be the subject of
patent rights. CENELEC shall not be held responsible for identifying any or all such patent rights.
Any feedback and questions on this document should be directed to the users’ national committee. A
complete listing of these bodies can be found on the CENELEC website.
Endorsement notice
The text of the International Standard IEC 62381:2024 was approved by CENELEC as a European
Standard without any modification.
In the official version, for Bibliography, the following notes have to be added for the standard indicated:
IEC 61511 series NOTE Approved as EN 61511 series
IEC 62443 series NOTE Approved as EN IEC 62443 series
IEC 62708 NOTE Approved as EN 62708
IEC 62881 NOTE Approved as EN IEC 62881
Annex ZA
(normative)
Normative references to international publications
with their corresponding European publications
The following documents are referred to in the text in such a way that some or all of their content
constitutes requirements of this document. For dated references, only the edition cited applies. For
undated references, the latest edition of the referenced document (including any amendments)
applies.
NOTE 1 Where an International Publication has been modified by common modifications, indicated by (mod),
the relevant EN/HD applies.
NOTE 2 Up-to-date information on the latest versions of the European Standards listed in this annex is available
here: www.cencenelec.eu.
Publication Year Title EN/HD Year
IEC 62382 - Control systems in the process industry - EN IEC 62382 -
Electrical and instrumentation loop check
IEC 62381 ®
Edition 3.0 2024-07
INTERNATIONAL
STANDARD
NORME
INTERNATIONALE
Automation systems in the process industry –
Factory acceptance test (FAT), site acceptance test (SAT), and site integration
test (SIT)
Systèmes d'automatisation dans l’industrie de transformation –
Essais d'acceptation en usine (FAT), essais d'acceptation sur site (SAT) et
essais d'intégration sur site (SIT)
INTERNATIONAL
ELECTROTECHNICAL
COMMISSION
COMMISSION
ELECTROTECHNIQUE
INTERNATIONALE
ICS 25.040.40 ISBN 978-2-8322-9418-5
– 2 – IEC 62381:2024 © IEC 2024
CONTENTS
FOREWORD . 6
INTRODUCTION . 8
1 Scope . 9
1.1 General applicability . 9
1.2 Exclusions . 9
1.2.1 Prior- and post-test activities . 9
1.2.2 Regulated industries . 9
1.2.3 Safety instrumented systems . 9
1.2.4 Manufacturing execution systems . 9
1.2.5 Advanced process control . 9
1.2.6 Security for industrial automation and control systems . 9
2 Normative references . 10
3 Terms, definitions and abbreviated terms . 10
3.1 Terms and definitions . 10
3.2 Abbreviated terms . 13
4 Overview of automation system testing . 13
4.1 General . 13
4.2 Methods of test performance . 14
4.3 Project design changes . 14
4.4 Adapted procedures in the event of modifications to existing systems . 14
5 Factory acceptance test (FAT) . 15
5.1 General . 15
5.2 Performance . 15
5.3 Pre-FAT activities . 15
5.3.1 General . 15
5.3.2 Vendor tests . 15
5.3.3 Documentation . 15
5.3.4 Test plan . 16
5.3.5 Test schedule . 16
5.4 FAT punch list . 17
5.4.1 General . 17
5.4.2 Correction . 17
5.4.3 Corrections after FAT . 17
5.5 Documentation of FAT . 18
5.5.1 General . 18
5.5.2 FAT report . 18
5.5.3 FAT final documentation . 18
5.6 FAT completion . 18
6 Factory integration test (FIT) . 19
6.1 General . 19
6.2 Performance . 19
6.3 Pre-FIT activities . 19
6.3.1 General . 19
6.3.2 Test plan . 19
6.3.3 Test schedule . 19
6.4 FIT punch list . 20
IEC 62381:2024 © IEC 2024 – 3 –
6.4.1 General . 20
6.4.2 Correction . 20
6.4.3 Correction after FIT . 20
6.5 Documentation of FIT. 21
6.5.1 General . 21
6.5.2 FIT report . 21
6.5.3 FIT final documentation . 21
6.6 FIT completion . 21
7 Site acceptance test (SAT) . 21
7.1 Performance . 21
7.2 Pre-SAT activities . 22
7.2.1 General . 22
7.2.2 Test plan . 22
7.2.3 Test schedule . 23
7.3 SAT punch list . 23
7.3.1 General .
...