Energy management system application program interface (EMS-API) - Part 600-2: Common Grid Model Exchange Specification (CGMES) - Exchange profiles specification

IEC 61970-600-2:2017(E) details the requirements of the exchange profiles belonging to the CGMES. The CGMES is defined using information on the Common Information Model (CIM) available in the public domain. The CGMES reflects TSO requirements for accurate modelling of the ENTSO-E area for power flow, short circuit and dynamics applications whilst also allowing for the exchange of any diagram layouts including GIS data of a grid model. Future editions of this technical specification will be released to describe following CGMES versions which reflect the additional requirements due to European network codes or guidelines.
Keyword: Smart Grid

General Information

Status
Published
Publication Date
25-Jul-2017
Drafting Committee
WG 13 - TC 57/WG 13
Current Stage
DELPUB - Deleted Publication
Start Date
04-Jun-2021
Completion Date
01-Nov-2018

Relations

Effective Date
05-Sep-2023

Overview

IEC TS 61970-600-2:2017 is a technical specification developed by the International Electrotechnical Commission (IEC) to standardize data exchange in the domain of power system modeling, specifically supporting Smart Grid functionalities. This standard defines the Common Grid Model Exchange Specification (CGMES) - Exchange Profiles, which play a critical role in ensuring seamless information exchange between different energy management systems (EMS) and transmission system operators (TSOs). The CGMES is based on the widely adopted Common Information Model (CIM), facilitating interoperability and consistent grid data representations across organizations and platforms.

This document outlines the essential requirements for the exchange profiles that constitute the CGMES, reflecting practical needs for accurate power flow, short circuit, and dynamic analyses within the ENTSO-E area. With the increasing integration of renewable energy resources and the growing complexity of power grids, IEC TS 61970-600-2:2017 serves as an important resource for Smart Grid stakeholders aiming to enhance reliability, efficiency, and innovation in grid operations.

Key Topics

  • CGMES Exchange Profiles
    Specification of the structures and data sets necessary for exchanging comprehensive grid models.
  • Integration with Common Information Model (CIM)
    Ensures exchange profiles are aligned with CIM standards, enabling interoperability and data consistency.
  • Power System Modeling Needs
    Supports requirements for power flow simulations, short circuit studies, and dynamic system evaluations.
  • Support for Geographical Information Systems (GIS)
    Allows the inclusion of diagram layouts, map-based visualizations, and grid spatial relationships.
  • TSO and ENTSO-E Compliance
    Addresses the specific data exchange needs of European transmission system operators and meets ENTSO-E’s regional regulatory requirements.
  • Future-Proofing for Network Codes
    Establishes a basis that can be further evolved in upcoming editions to align with revised European network codes or operational guidelines.

Applications

IEC TS 61970-600-2:2017 is pivotal in a range of practical Smart Grid and energy management scenarios:

  • Cross-Border Grid Coordination:
    Facilitates the exchange of accurate, standardized grid models among TSOs to safely and efficiently manage interconnected power systems.

  • Grid Planning and Operation:
    Enables transmission operators, utilities, and planning authorities to synchronize data for power flow, fault analysis, and network development, enhancing grid reliability and stability.

  • Integration of Renewable Resources:
    Provides robust support for modeling dynamic resource behavior, which is essential as the grid incorporates higher shares of wind, solar, and other renewables.

  • GIS-Based Visualization:
    Enhances operational decision-making through standardized exchange of diagram and geographical grid layouts.

  • Regulatory Reporting:
    Helps participants demonstrate compliance with ENTSO-E requirements and European network codes through consistent, verifiable data exchange.

Related Standards

To fully leverage the capabilities of IEC TS 61970-600-2:2017, consider these related standards:

  • IEC 61970 Series:
    A broader suite of standards for EMS-API, forming the technical backbone for system integration and interoperability in energy management.

  • IEC 61968 Series:
    Focuses on information exchanges for distribution management system (DMS) integration, complementing the transmission-level emphasis of IEC 61970.

  • IEC 62325 Series:
    Relevant for electricity market communications and data exchanges, aiding in aligning grid operational data with market activities.

  • ENTSO-E CIM Guidelines:
    Specifications and implementation guides tailored for the European Network of Transmission System Operators for Electricity.


By implementing IEC TS 61970-600-2:2017, organizations in the Smart Grid ecosystem can achieve greater interoperability, streamlined data management, and future-ready grid operation capabilities, supporting the ongoing digital transformation of power networks.

Buy Documents

Technical specification

IEC TS 61970-600-2:2017 - Energy management system application program interface (EMS-API) - Part 600-2: Common Grid Model Exchange Specification (CGMES) - Exchange profiles specification

English language (329 pages)
sale 15% off
Preview
sale 15% off
Preview
Technical specification

IEC TS 61970-600-2:2017 - Energy management system application program interface (EMS-API) - Part 600-2: Common Grid Model Exchange Specification (CGMES) - Exchange profiles specification Released:7/26/2017

ISBN:978-2-8322-4574-3
English language (329 pages)
sale 15% off
Preview
sale 15% off
Preview

Get Certified

Connect with accredited certification bodies for this standard

ANCE

Mexican certification and testing association.

EMA Mexico Verified

Intertek Slovenia

Intertek testing, inspection, and certification services in Slovenia.

UKAS Slovenia Verified

LNE (Laboratoire National de Métrologie et d'Essais)

French national laboratory for metrology and testing.

COFRAC France Verified

Sponsored listings

Frequently Asked Questions

IEC TS 61970-600-2:2017 is a technical specification published by the International Electrotechnical Commission (IEC). Its full title is "Energy management system application program interface (EMS-API) - Part 600-2: Common Grid Model Exchange Specification (CGMES) - Exchange profiles specification". This standard covers: IEC 61970-600-2:2017(E) details the requirements of the exchange profiles belonging to the CGMES. The CGMES is defined using information on the Common Information Model (CIM) available in the public domain. The CGMES reflects TSO requirements for accurate modelling of the ENTSO-E area for power flow, short circuit and dynamics applications whilst also allowing for the exchange of any diagram layouts including GIS data of a grid model. Future editions of this technical specification will be released to describe following CGMES versions which reflect the additional requirements due to European network codes or guidelines. Keyword: Smart Grid

IEC 61970-600-2:2017(E) details the requirements of the exchange profiles belonging to the CGMES. The CGMES is defined using information on the Common Information Model (CIM) available in the public domain. The CGMES reflects TSO requirements for accurate modelling of the ENTSO-E area for power flow, short circuit and dynamics applications whilst also allowing for the exchange of any diagram layouts including GIS data of a grid model. Future editions of this technical specification will be released to describe following CGMES versions which reflect the additional requirements due to European network codes or guidelines. Keyword: Smart Grid

IEC TS 61970-600-2:2017 is classified under the following ICS (International Classification for Standards) categories: 33.200 - Telecontrol. Telemetering. The ICS classification helps identify the subject area and facilitates finding related standards.

IEC TS 61970-600-2:2017 has the following relationships with other standards: It is inter standard links to IEC 61970-600-2:2021. Understanding these relationships helps ensure you are using the most current and applicable version of the standard.

IEC TS 61970-600-2:2017 is available in PDF format for immediate download after purchase. The document can be added to your cart and obtained through the secure checkout process. Digital delivery ensures instant access to the complete standard document.

Standards Content (Sample)


IEC TS 61970-600-2 ®
Edition 1.0 2017-07
TECHNICAL
SPECIFICATION
colour
inside
Energy management system application program interface (EMS-API) –
Part 600-2: Common Grid Model Exchange Specification (CGMES) – Exchange
profiles specification
All rights reserved. Unless otherwise specified, no part of this publication may be reproduced or utilized in any form
or by any means, electronic or mechanical, including photocopying and microfilm, without permission in writing from
either IEC or IEC's member National Committee in the country of the requester. If you have any questions about IEC
copyright or have an enquiry about obtaining additional rights to this publication, please contact the address below or
your local IEC member National Committee for further information.

IEC Central Office Tel.: +41 22 919 02 11
3, rue de Varembé Fax: +41 22 919 03 00
CH-1211 Geneva 20 info@iec.ch
Switzerland www.iec.ch
About the IEC
The International Electrotechnical Commission (IEC) is the leading global organization that prepares and publishes
International Standards for all electrical, electronic and related technologies.

About IEC publications
The technical content of IEC publications is kept under constant review by the IEC. Please make sure that you have the
latest edition, a corrigenda or an amendment might have been published.

IEC Catalogue - webstore.iec.ch/catalogue Electropedia - www.electropedia.org
The stand-alone application for consulting the entire The world's leading online dictionary of electronic and
bibliographical information on IEC International Standards, electrical terms containing 20 000 terms and definitions in
Technical Specifications, Technical Reports and other English and French, with equivalent terms in 16 additional
documents. Available for PC, Mac OS, Android Tablets and languages. Also known as the International Electrotechnical
iPad. Vocabulary (IEV) online.

IEC publications search - www.iec.ch/searchpub IEC Glossary - std.iec.ch/glossary
The advanced search enables to find IEC publications by a 65 000 electrotechnical terminology entries in English and
variety of criteria (reference number, text, technical French extracted from the Terms and Definitions clause of
committee,…). It also gives information on projects, replaced IEC publications issued since 2002. Some entries have been
and withdrawn publications. collected from earlier publications of IEC TC 37, 77, 86 and

CISPR.
IEC Just Published - webstore.iec.ch/justpublished

Stay up to date on all new IEC publications. Just Published IEC Customer Service Centre - webstore.iec.ch/csc
details all new publications released. Available online and If you wish to give us your feedback on this publication or
also once a month by email. need further assistance, please contact the Customer Service
Centre: csc@iec.ch.
IEC TS 61970-600-2 ®
Edition 1.0 2017-07
TECHNICAL
SPECIFICATION
colour
inside
Energy management system application program interface (EMS-API) –

Part 600-2: Common Grid Model Exchange Specification (CGMES) – Exchange

profiles specification
INTERNATIONAL
ELECTROTECHNICAL
COMMISSION
ICS 33.200 ISBN 978-2-8322-4574-3

– 2 – IEC TS 61970-600-2:2017 © IEC 2017
CONTENTS
FOREWORD . 24
1 Scope . 26
2 Normative references . 26
3 Terms, definitions and abbreviated terms . 27
3.1 Terms and definitions . 27
3.2 Abbreviated terms . 28
4 EquipmentBoundaryProfile . 28
4.1 General . 28
4.2 (Entsoe) EquipmentBoundaryVersion(Abstract) . 29
4.3 Core . 30
4.3.1 ConductingEquipment(Abstract) . 30
4.3.2 (Operation) ConnectivityNode . 31
4.3.3 ConnectivityNodeContainer(Abstract) . 33
4.3.4 Equipment(Abstract) . 33
4.3.5 EquipmentContainer(Abstract) . 34
4.3.6 PowerSystemResource(Abstract) . 34
4.3.7 Terminal . 35
4.3.8 BaseVoltage . 35
4.3.9 GeographicalRegion . 35
4.3.10 IdentifiedObject(Abstract) . 36
4.3.11 SubGeographicalRegion . 36
4.4 Wires . 37
4.4.1 Connector(Abstract). 37
4.4.2 (Entsoe) EnergySchedulingType . 38
4.4.3 EnergySource(Abstract) . 38
4.4.4 Junction . 39
4.4.5 Line . 40
4.5 Global Used Datatypes . 40
4.5.1 Datatypes – Voltage . 40
4.5.2 Enumerations . 41
4.5.3 Primitives . 42
5 TopologyBoundaryProfile . 42
5.1 General . 42
5.2 (Entsoe) TopologyBoundaryVersion(Abstract) . 43
5.3 Core . 44
5.3.1 BaseVoltage(Abstract) . 44
5.3.2 (Operation,Description) ConnectivityNode . 45
5.3.3 ConnectivityNodeContainer(Abstract) . 45
5.3.4 IdentifiedObject(Abstract) . 45
5.4 Topology – TopologicalNode . 46
5.5 Global Used Datatypes – Primitives . 48
5.5.1 String . 48
5.5.2 Date . 48
5.5.3 Boolean . 48
6 EquipmentProfile . 48
6.1 General . 48

6.2 (Entsoe) EquipmentVersion(Abstract) . 49
6.3 DC . 51
6.3.1 General . 51
6.3.2 ACDCConverter(Abstract) . 54
6.3.3 ACDCConverterDCTerminal . 56
6.3.4 CsConverter . 57
6.3.5 DCBaseTerminal(Abstract) . 59
6.3.6 DCBreaker . 60
6.3.7 DCBusbar . 60
6.3.8 DCChopper . 61
6.3.9 DCConductingEquipment(Abstract) . 62
6.3.10 DCConverterUnit . 63
6.3.11 DCDisconnector. 63
6.3.12 DCEquipmentContainer . 64
6.3.13 DCGround . 64
6.3.14 DCLine . 65
6.3.15 DCLineSegment . 66
6.3.16 DCNode . 67
6.3.17 DCSeriesDevice . 68
6.3.18 DCShunt . 69
6.3.19 DCSwitch . 69
6.3.20 DCTerminal . 70
6.3.21 PerLengthDCLineParameter . 71
6.3.22 VsCapabilityCurve . 71
6.3.23 VsConverter . 72
6.3.24 Enumerations . 74
6.4 Topology . 74
6.4.1 BusNameMarker . 74
6.5 Meas . 75
6.5.1 General . 75
6.5.2 (Operation) Accumulator . 78
6.5.3 (Operation) AccumulatorLimit . 79
6.5.4 (Operation) AccumulatorLimitSet . 80
6.5.5 (Operation) AccumulatorReset . 81
6.5.6 (Operation) AccumulatorValue . 82
6.5.7 (Operation) Analog . 82
6.5.8 (Operation) AnalogControl(Abstract) . 83
6.5.9 (Operation) AnalogLimit . 84
6.5.10 (Operation) AnalogLimitSet . 85
6.5.11 (Operation) AnalogValue . 86
6.5.12 (Operation) Command . 86
6.5.13 (Operation) Control(Abstract) . 87
6.5.14 (Operation) Discrete . 88
6.5.15 (Operation) DiscreteValue . 89
6.5.16 (Operation) Limit(Abstract) . 90
6.5.17 (Operation) LimitSet(Abstract) . 91
6.5.18 (Operation) Measurement(Abstract) . 91
6.5.19 (Operation) MeasurementValue(Abstract) . 93
6.5.20 (Operation) MeasurementValueQuality . 94

– 4 – IEC TS 61970-600-2:2017 © IEC 2017
6.5.21 (Operation) MeasurementValueSource . 94
6.5.22 (Operation) Quality61850(Abstract) . 95
6.5.23 (Operation) RaiseLowerCommand . 96
6.5.24 (Operation) SetPoint . 97
6.5.25 (Operation) StringMeasurement . 98
6.5.26 (Operation) StringMeasurementValue . 99
6.5.27 (Operation) ValueAliasSet . 100
6.5.28 (Operation) ValueToAlias . 101
6.5.29 Enumerations . 101
6.6 Production . 102
6.6.1 General . 102
6.6.2 (Entsoe) EnergySchedulingType . 104
6.6.3 EnergySource . 105
6.6.4 FossilFuel . 106
6.6.5 GeneratingUnit . 107
6.6.6 (Operation) GrossToNetActivePowerCurve . 109
6.6.7 HydroGeneratingUnit . 110
6.6.8 HydroPowerPlant . 111
6.6.9 HydroPump . 111
6.6.10 NuclearGeneratingUnit . 112
6.6.11 SolarGeneratingUnit . 113
6.6.12 ThermalGeneratingUnit . 114
6.6.13 WindGeneratingUnit . 115
6.6.14 Enumerations . 116
6.7 Core . 118
6.7.1 General . 118
6.7.2 ACDCTerminal(Abstract) . 120
6.7.3 BaseVoltage . 120
6.7.4 BasicIntervalSchedule(Abstract) . 121
6.7.5 (Operation) Bay . 121
6.7.6 ConductingEquipment(Abstract) . 122
6.7.7 (Operation) ConnectivityNode . 123
6.7.8 ConnectivityNodeContainer(Abstract) . 124
6.7.9 Curve(Abstract) . 124
6.7.10 CurveData . 125
6.7.11 Equipment(Abstract) . 125
6.7.12 EquipmentContainer(Abstract) . 126
6.7.13 GeographicalRegion . 127
6.7.14 IdentifiedObject(Abstract) . 127
6.7.15 PowerSystemResource(Abstract) . 128
6.7.16 RegularIntervalSchedule(Abstract) . 128
6.7.17 (Operation) RegularTimePoint . 129
6.7.18 ReportingGroup . 130
6.7.19 SubGeographicalRegion . 130
6.7.20 Substation . 131
6.7.21 Terminal . 131
6.7.22 VoltageLevel . 132
6.7.23 Enumerations . 133
6.8 OperationalLimits . 134

6.8.1 General . 134
6.8.2 (Operation) ActivePowerLimit . 136
6.8.3 (Operation) ApparentPowerLimit . 137
6.8.4 CurrentLimit . 138
6.8.5 OperationalLimit(Abstract) . 138
6.8.6 OperationalLimitSet . 139
6.8.7 OperationalLimitType . 140
6.8.8 VoltageLimit . 141
6.8.9 Enumerations . 142
6.9 Wires . 144
6.9.1 General . 144
6.9.2 ACLineSegment . 147
6.9.3 AsynchronousMachine . 149
6.9.4 Breaker. 151
6.9.5 BusbarSection . 152
6.9.6 Conductor(Abstract). 153
6.9.7 Connector(Abstract). 154
6.9.8 Disconnector . 154
6.9.9 (ShortCircuit) EarthFaultCompensator(Abstract) . 155
6.9.10 EnergyConsumer . 156
6.9.11 ExternalNetworkInjection . 157
6.9.12 (ShortCircuit,Operation) Ground . 160
6.9.13 (ShortCircuit,Operation) GroundDisconnector . 161
6.9.14 (ShortCircuit) GroundingImpedance . 162
6.9.15 Junction . 163
6.9.16 Line . 164
6.9.17 LinearShuntCompensator . 165
6.9.18 LoadBreakSwitch . 166
6.9.19 (ShortCircuit) MutualCoupling . 167
6.9.20 NonlinearShuntCompensator . 168
6.9.21 NonlinearShuntCompensatorPoint . 169
6.9.22 (ShortCircuit) PetersenCoil . 170
6.9.23 PhaseTapChanger(Abstract) . 172
6.9.24 PhaseTapChangerAsymmetrical . 172
6.9.25 PhaseTapChangerLinear . 173
6.9.26 PhaseTapChangerNonLinear(Abstract) . 174
6.9.27 PhaseTapChangerSymmetrical . 175
6.9.28 PhaseTapChangerTable . 176
6.9.29 PhaseTapChangerTablePoint . 177
6.9.30 PhaseTapChangerTabular . 177
6.9.31 PowerTransformer . 178
6.9.32 PowerTransformerEnd . 181
6.9.33 ProtectedSwitch(Abstract) . 183
6.9.34 RatioTapChanger . 184
6.9.35 RatioTapChangerTable . 185
6.9.36 RatioTapChangerTablePoint . 185
6.9.37 ReactiveCapabilityCurve . 186
6.9.38 RegulatingCondEq(Abstract). 187
6.9.39 RegulatingControl . 188

– 6 – IEC TS 61970-600-2:2017 © IEC 2017
6.9.40 (Operation) RegulationSchedule . 189
6.9.41 RotatingMachine(Abstract) . 190
6.9.42 SeriesCompensator . 191
6.9.43 ShuntCompensator(Abstract) . 192
6.9.44 StaticVarCompensator . 194
6.9.45 Switch . 195
6.9.46 (Operation) SwitchSchedule . 196
6.9.47 SynchronousMachine. 197
6.9.48 TapChanger(Abstract) . 201
6.9.49 TapChangerControl . 202
6.9.50 TapChangerTablePoint . 203
6.9.51 (Operation) TapSchedule . 204
6.9.52 TransformerEnd(Abstract). 204
6.9.53 Enumerations . 205
6.10 LoadModel . 207
6.10.1 General . 207
6.10.2 ConformLoad . 210
6.10.3 ConformLoadGroup . 211
6.10.4 ConformLoadSchedule . 212
6.10.5 (Operation) DayType . 213
6.10.6 (Operation) EnergyArea(Abstract) . 213
6.10.7 (Operation) LoadArea . 213
6.10.8 LoadGroup(Abstract) . 214
6.10.9 LoadResponseCharacteristic . 214
6.10.10 NonConformLoad. 216
6.10.11 NonConformLoadGroup . 218
6.10.12 NonConformLoadSchedule . 219
6.10.13 (Operation) Season . 220
6.10.14 (Operation) SeasonDayTypeSchedule(Abstract) . 220
6.10.15 (Operation) StationSupply . 221
6.10.16 (Operation) SubLoadArea . 222
6.11 Equivalents . 223
6.11.1 General . 223
6.11.2 EquivalentBranch . 224
6.11.3 EquivalentEquipment(Abstract) . 226
6.11.4 EquivalentInjection . 227
6.11.5 EquivalentNetwork . 229
6.11.6 EquivalentShunt . 229
6.12 ControlArea . 230
6.12.1 General . 230
6.12.2 ControlArea . 232
6.12.3 ControlAreaGeneratingUnit . 233
6.12.4 TieFlow. 233
6.12.5 Enumerations – ControlAreaTypeKind . 234
6.13 Global Used Datatypes . 234
6.13.1 ApparentPower . 234
6.13.2 ActivePower . 234
6.13.3 Voltage . 235
6.13.4 Resistance . 235

6.13.5 ActivePowerPerCurrentFlow . 235
6.13.6 AngleDegrees . 236
6.13.7 CurrentFlow . 236
6.13.8 Inductance . 236
6.13.9 Capacitance . 237
6.13.10 Length . 237
6.13.11 CapacitancePerLength . 237
6.13.12 InductancePerLength . 238
6.13.13 ResistancePerLength . 238
6.13.14 Simple_Float . 239
6.13.15 PerCent . 239
6.13.16 AngleRadians . 239
6.13.17 Reactance . 239
6.13.18 Money . 240
6.13.19 Seconds . 240
6.13.20 Susceptance . 240
6.13.21 Conductance . 241
6.13.22 Temperature . 241
6.13.23 Frequency . 241
6.13.24 RotationSpeed . 242
6.13.25 ReactivePower . 242
6.13.26 ActivePowerPerFrequency . 242
6.13.27 PU . 243
6.13.28 VoltagePerReactivePower . 243
6.13.29 Enumerations . 244
6.13.30 Primitives . 253
7 SteadyStateHypothesisProfile . 253
7.1 General . 253
7.2 (Entsoe) SteadyStateHypothesisVersion(Abstract) . 254
7.3 Core . 255
7.3.1 General . 255
7.3.2 ACDCTerminal(Abstract) . 256
7.3.3 ConductingEquipment(Abstract) . 257
7.3.4 Equipment(Abstract) . 257
7.3.5 IdentifiedObject(Abstract) . 257
7.3.6 PowerSystemResource(Abstract) . 258
7.3.7 (Description) Terminal . 258
7.4 ControlArea . 259
7.4.1 (Description) ControlArea . 259
7.5 DC . 259
7.5.1 General . 259
7.5.2 ACDCConverter(Abstract) . 260
7.5.3 (Description) ACDCConverterDCTerminal . 261
7.5.4 (Description) CsConverter . 261
7.5.5 DCBaseTerminal(Abstract) . 262
7.5.6 (Description) DCTerminal . 262
7.5.7 (Description) VsConverter . 263
7.5.8 Enumerations . 263
7.6 Equivalents . 264

– 8 – IEC TS 61970-600-2:2017 © IEC 2017
7.6.1 EquivalentEquipment(Abstract) . 264
7.6.2 (Description) EquivalentInjection . 265
7.7 Generation . 265
7.7.1 (Description) GeneratingUnit . 265
7.7.2 (Description) HydroGeneratingUnit . 266
7.7.3 (Description) NuclearGeneratingUnit . 266
7.7.4 (Description) SolarGeneratingUnit . 266
7.7.5 (Description) ThermalGeneratingUnit . 267
7.7.6 (Description) WindGeneratingUnit . 267
7.8 Wires . 267
7.8.1 (Description) AsynchronousMachine . 267
7.8.2 (Description) Breaker . 268
7.8.3 (Description) Disconnector. 268
7.8.4 (Description) EnergyConsumer . 269
7.8.5 (Description) EnergySource . 269
7.8.6 (Description) ExternalNetworkInjection . 270
7.8.7 (Operation,ShortCircuit,Description) GroundDisconnector. 270
7.8.8 (Description) LoadBreakSwitch . 270
7.8.9 PhaseTapChanger(Abstract) . 271
7.8.10 (Description) PhaseTapChangerAsymmetrical . 271
7.8.11 (Description) PhaseTapChangerLinear . 271
7.8.12 PhaseTapChangerNonLinear(Abstract) . 272
7.8.13 (Description) PhaseTapChangerSymmetrical . 272
7.8.14 (Description) PhaseTapChangerTabular . 273
7.8.15 ProtectedSwitch(Abstract) . 273
7.8.16 (Description) RatioTapChanger . 273
7.8.17 RegulatingCondEq(Abstract). 274
7.8.18 RotatingMachine(Abstract) . 274
7.8.19 (Description) StaticVarCompensator . 275
7.8.20 (Description) Switch . 275
7.8.21 (Description) SynchronousMachine . 275
7.8.22 (Description) TapChangerControl . 276
7.8.23 (Description) LinearShuntCompensator . 276
7.8.24 (Description) NonlinearShuntCompensator . 277
7.8.25 (Description) RegulatingControl . 277
7.8.26 ShuntCompensator(Abstract) . 278
7.8.27 TapChanger(Abstract) . 278
7.8.28 Enumerations . 279
7.9 LoadModel . 279
7.9.1 (Description) ConformLoad . 279
7.9.2 (Description) NonConformLoad . 280
7.9.3 (Operation,Description) StationSupply . 280
7.10 Global Used Datatypes . 281
7.10.1 Datatypes . 281
7.10.2 Enumerations . 284
7.10.3 Primitives . 286
8 TopologyProfile . 287
8.1 General . 287
8.2 (Entsoe) TopologyVersion(Abstract) . 288

8.3 Core . 289
8.3.1 General . 289
8.3.2 ACDCTerminal(Abstract) . 290
8.3.3 BaseVoltage(Abstract) . 290
8.3.4 (Operation,Description) ConnectivityNode . 291
8.3.5 ConnectivityNodeContainer(Abstract) . 291
8.3.6 ReportingGroup(Abstract) . 291
8.3.7 Identi
...


IEC TS 61970-600-2 ®
Edition 1.0 2017-07
TECHNICAL
SPECIFICATION
colour
inside
Energy management system application program interface (EMS-API) –
Part 600-2: Common Grid Model Exchange Specification (CGMES) – Exchange
profiles specification
All rights reserved. Unless otherwise specified, no part of this publication may be reproduced or utilized in any form

or by any means, electronic or mechanical, including photocopying and microfilm, without permission in writing from
either IEC or IEC's member National Committee in the country of the requester. If you have any questions about IEC
copyright or have an enquiry about obtaining additional rights to this publication, please contact the address below or

your local IEC member National Committee for further information.

IEC Central Office Tel.: +41 22 919 02 11
3, rue de Varembé Fax: +41 22 919 03 00

CH-1211 Geneva 20 info@iec.ch
Switzerland www.iec.ch
About the IEC
The International Electrotechnical Commission (IEC) is the leading global organization that prepares and publishes
International Standards for all electrical, electronic and related technologies.

About IEC publications
The technical content of IEC publications is kept under constant review by the IEC. Please make sure that you have the
latest edition, a corrigenda or an amendment might have been published.

IEC Catalogue - webstore.iec.ch/catalogue Electropedia - www.electropedia.org
The stand-alone application for consulting the entire The world's leading online dictionary of electronic and
bibliographical information on IEC International Standards, electrical terms containing 20 000 terms and definitions in
Technical Specifications, Technical Reports and other English and French, with equivalent terms in 16 additional
documents. Available for PC, Mac OS, Android Tablets and languages. Also known as the International Electrotechnical
iPad. Vocabulary (IEV) online.

IEC publications search - www.iec.ch/searchpub IEC Glossary - std.iec.ch/glossary
The advanced search enables to find IEC publications by a 65 000 electrotechnical terminology entries in English and
variety of criteria (reference number, text, technical French extracted from the Terms and Definitions clause of
committee,…). It also gives information on projects, replaced IEC publications issued since 2002. Some entries have been
and withdrawn publications. collected from earlier publications of IEC TC 37, 77, 86 and

CISPR.
IEC Just Published - webstore.iec.ch/justpublished

Stay up to date on all new IEC publications. Just Published IEC Customer Service Centre - webstore.iec.ch/csc
details all new publications released. Available online and If you wish to give us your feedback on this publication or
also once a month by email. need further assistance, please contact the Customer Service
Centre: csc@iec.ch.
IEC TS 61970-600-2 ®
Edition 1.0 2017-07
TECHNICAL
SPECIFICATION
colour
inside
Energy management system application program interface (EMS-API) –

Part 600-2: Common Grid Model Exchange Specification (CGMES) – Exchange

profiles specification
INTERNATIONAL
ELECTROTECHNICAL
COMMISSION
ICS 33.200 ISBN 978-2-8322-4574-3

– 2 – IEC TS 61970-600-2:2017 © IEC 2017

CONTENTS
FOREWORD . 24

1 Scope . 26

2 Normative references . 26

3 Terms, definitions and abbreviated terms . 27

3.1 Terms and definitions . 27

3.2 Abbreviated terms . 28

4 EquipmentBoundaryProfile . 28

4.1 General . 28
4.2 (Entsoe) EquipmentBoundaryVersion(Abstract) . 29
4.3 Core . 30
4.3.1 ConductingEquipment(Abstract) . 30
4.3.2 (Operation) ConnectivityNode . 31
4.3.3 ConnectivityNodeContainer(Abstract) . 33
4.3.4 Equipment(Abstract) . 33
4.3.5 EquipmentContainer(Abstract) . 34
4.3.6 PowerSystemResource(Abstract) . 34
4.3.7 Terminal . 35
4.3.8 BaseVoltage . 35
4.3.9 GeographicalRegion . 35
4.3.10 IdentifiedObject(Abstract) . 36
4.3.11 SubGeographicalRegion . 36
4.4 Wires . 37
4.4.1 Connector(Abstract). 37
4.4.2 (Entsoe) EnergySchedulingType . 38
4.4.3 EnergySource(Abstract) . 38
4.4.4 Junction . 39
4.4.5 Line . 40
4.5 Global Used Datatypes . 40
4.5.1 Datatypes – Voltage . 40
4.5.2 Enumerations . 41
4.5.3 Primitives . 42
5 TopologyBoundaryProfile . 42
5.1 General . 42

5.2 (Entsoe) TopologyBoundaryVersion(Abstract) . 43
5.3 Core . 44
5.3.1 BaseVoltage(Abstract) . 44
5.3.2 (Operation,Description) ConnectivityNode . 45
5.3.3 ConnectivityNodeContainer(Abstract) . 45
5.3.4 IdentifiedObject(Abstract) . 45
5.4 Topology – TopologicalNode . 46
5.5 Global Used Datatypes – Primitives . 48
5.5.1 String . 48
5.5.2 Date . 48
5.5.3 Boolean . 48
6 EquipmentProfile . 48
6.1 General . 48

6.2 (Entsoe) EquipmentVersion(Abstract) . 49

6.3 DC . 51

6.3.1 General . 51

6.3.2 ACDCConverter(Abstract) . 54

6.3.3 ACDCConverterDCTerminal . 56

6.3.4 CsConverter . 57

6.3.5 DCBaseTerminal(Abstract) . 59

6.3.6 DCBreaker . 60

6.3.7 DCBusbar . 60

6.3.8 DCChopper . 61

6.3.9 DCConductingEquipment(Abstract) . 62
6.3.10 DCConverterUnit . 63
6.3.11 DCDisconnector. 63
6.3.12 DCEquipmentContainer . 64
6.3.13 DCGround . 64
6.3.14 DCLine . 65
6.3.15 DCLineSegment . 66
6.3.16 DCNode . 67
6.3.17 DCSeriesDevice . 68
6.3.18 DCShunt . 69
6.3.19 DCSwitch . 69
6.3.20 DCTerminal . 70
6.3.21 PerLengthDCLineParameter . 71
6.3.22 VsCapabilityCurve . 71
6.3.23 VsConverter . 72
6.3.24 Enumerations . 74
6.4 Topology . 74
6.4.1 BusNameMarker . 74
6.5 Meas . 75
6.5.1 General . 75
6.5.2 (Operation) Accumulator . 78
6.5.3 (Operation) AccumulatorLimit . 79
6.5.4 (Operation) AccumulatorLimitSet . 80
6.5.5 (Operation) AccumulatorReset . 81
6.5.6 (Operation) AccumulatorValue . 82

6.5.7 (Operation) Analog . 82
6.5.8 (Operation) AnalogControl(Abstract) . 83
6.5.9 (Operation) AnalogLimit . 84
6.5.10 (Operation) AnalogLimitSet . 85
6.5.11 (Operation) AnalogValue . 86
6.5.12 (Operation) Command . 86
6.5.13 (Operation) Control(Abstract) . 87
6.5.14 (Operation) Discrete . 88
6.5.15 (Operation) DiscreteValue . 89
6.5.16 (Operation) Limit(Abstract) . 90
6.5.17 (Operation) LimitSet(Abstract) . 91
6.5.18 (Operation) Measurement(Abstract) . 91
6.5.19 (Operation) MeasurementValue(Abstract) . 93
6.5.20 (Operation) MeasurementValueQuality . 94

– 4 – IEC TS 61970-600-2:2017 © IEC 2017

6.5.21 (Operation) MeasurementValueSource . 94

6.5.22 (Operation) Quality61850(Abstract) . 95

6.5.23 (Operation) RaiseLowerCommand . 96

6.5.24 (Operation) SetPoint . 97

6.5.25 (Operation) StringMeasurement . 98

6.5.26 (Operation) StringMeasurementValue . 99

6.5.27 (Operation) ValueAliasSet . 100

6.5.28 (Operation) ValueToAlias . 101

6.5.29 Enumerations . 101

6.6 Production . 102

6.6.1 General . 102
6.6.2 (Entsoe) EnergySchedulingType . 104
6.6.3 EnergySource . 105
6.6.4 FossilFuel . 106
6.6.5 GeneratingUnit . 107
6.6.6 (Operation) GrossToNetActivePowerCurve . 109
6.6.7 HydroGeneratingUnit . 110
6.6.8 HydroPowerPlant . 111
6.6.9 HydroPump . 111
6.6.10 NuclearGeneratingUnit . 112
6.6.11 SolarGeneratingUnit . 113
6.6.12 ThermalGeneratingUnit . 114
6.6.13 WindGeneratingUnit . 115
6.6.14 Enumerations . 116
6.7 Core . 118
6.7.1 General . 118
6.7.2 ACDCTerminal(Abstract) . 120
6.7.3 BaseVoltage . 120
6.7.4 BasicIntervalSchedule(Abstract) . 121
6.7.5 (Operation) Bay . 121
6.7.6 ConductingEquipment(Abstract) . 122
6.7.7 (Operation) ConnectivityNode . 123
6.7.8 ConnectivityNodeContainer(Abstract) . 124
6.7.9 Curve(Abstract) . 124
6.7.10 CurveData . 125

6.7.11 Equipment(Abstract) . 125
6.7.12 EquipmentContainer(Abstract) . 126
6.7.13 GeographicalRegion . 127
6.7.14 IdentifiedObject(Abstract) . 127
6.7.15 PowerSystemResource(Abstract) . 128
6.7.16 RegularIntervalSchedule(Abstract) . 128
6.7.17 (Operation) RegularTimePoint . 129
6.7.18 ReportingGroup . 130
6.7.19 SubGeographicalRegion . 130
6.7.20 Substation . 131
6.7.21 Terminal . 131
6.7.22 VoltageLevel . 132
6.7.23 Enumerations . 133
6.8 OperationalLimits . 134

6.8.1 General . 134

6.8.2 (Operation) ActivePowerLimit . 136

6.8.3 (Operation) ApparentPowerLimit . 137

6.8.4 CurrentLimit . 138

6.8.5 OperationalLimit(Abstract) . 138

6.8.6 OperationalLimitSet . 139

6.8.7 OperationalLimitType . 140

6.8.8 VoltageLimit . 141

6.8.9 Enumerations . 142

6.9 Wires . 144

6.9.1 General . 144
6.9.2 ACLineSegment . 147
6.9.3 AsynchronousMachine . 149
6.9.4 Breaker. 151
6.9.5 BusbarSection . 152
6.9.6 Conductor(Abstract). 153
6.9.7 Connector(Abstract). 154
6.9.8 Disconnector . 154
6.9.9 (ShortCircuit) EarthFaultCompensator(Abstract) . 155
6.9.10 EnergyConsumer . 156
6.9.11 ExternalNetworkInjection . 157
6.9.12 (ShortCircuit,Operation) Ground . 160
6.9.13 (ShortCircuit,Operation) GroundDisconnector . 161
6.9.14 (ShortCircuit) GroundingImpedance . 162
6.9.15 Junction . 163
6.9.16 Line . 164
6.9.17 LinearShuntCompensator . 165
6.9.18 LoadBreakSwitch . 166
6.9.19 (ShortCircuit) MutualCoupling . 167
6.9.20 NonlinearShuntCompensator . 168
6.9.21 NonlinearShuntCompensatorPoint . 169
6.9.22 (ShortCircuit) PetersenCoil . 170
6.9.23 PhaseTapChanger(Abstract) . 172
6.9.24 PhaseTapChangerAsymmetrical . 172
6.9.25 PhaseTapChangerLinear . 173

6.9.26 PhaseTapChangerNonLinear(Abstract) . 174
6.9.27 PhaseTapChangerSymmetrical . 175
6.9.28 PhaseTapChangerTable . 176
6.9.29 PhaseTapChangerTablePoint . 177
6.9.30 PhaseTapChangerTabular . 177
6.9.31 PowerTransformer . 178
6.9.32 PowerTransformerEnd . 181
6.9.33 ProtectedSwitch(Abstract) . 183
6.9.34 RatioTapChanger . 184
6.9.35 RatioTapChangerTable . 185
6.9.36 RatioTapChangerTablePoint . 185
6.9.37 ReactiveCapabilityCurve . 186
6.9.38 RegulatingCondEq(Abstract). 187
6.9.39 RegulatingControl . 188

– 6 – IEC TS 61970-600-2:2017 © IEC 2017

6.9.40 (Operation) RegulationSchedule . 189

6.9.41 RotatingMachine(Abstract) . 190

6.9.42 SeriesCompensator . 191

6.9.43 ShuntCompensator(Abstract) . 192

6.9.44 StaticVarCompensator . 194

6.9.45 Switch . 195

6.9.46 (Operation) SwitchSchedule . 196

6.9.47 SynchronousMachine. 197

6.9.48 TapChanger(Abstract) . 201

6.9.49 TapChangerControl . 202

6.9.50 TapChangerTablePoint . 203
6.9.51 (Operation) TapSchedule . 204
6.9.52 TransformerEnd(Abstract). 204
6.9.53 Enumerations . 205
6.10 LoadModel . 207
6.10.1 General . 207
6.10.2 ConformLoad . 210
6.10.3 ConformLoadGroup . 211
6.10.4 ConformLoadSchedule . 212
6.10.5 (Operation) DayType . 213
6.10.6 (Operation) EnergyArea(Abstract) . 213
6.10.7 (Operation) LoadArea . 213
6.10.8 LoadGroup(Abstract) . 214
6.10.9 LoadResponseCharacteristic . 214
6.10.10 NonConformLoad. 216
6.10.11 NonConformLoadGroup . 218
6.10.12 NonConformLoadSchedule . 219
6.10.13 (Operation) Season . 220
6.10.14 (Operation) SeasonDayTypeSchedule(Abstract) . 220
6.10.15 (Operation) StationSupply . 221
6.10.16 (Operation) SubLoadArea . 222
6.11 Equivalents . 223
6.11.1 General . 223
6.11.2 EquivalentBranch . 224
6.11.3 EquivalentEquipment(Abstract) . 226

6.11.4 EquivalentInjection . 227
6.11.5 EquivalentNetwork . 229
6.11.6 EquivalentShunt . 229
6.12 ControlArea . 230
6.12.1 General . 230
6.12.2 ControlArea . 232
6.12.3 ControlAreaGeneratingUnit . 233
6.12.4 TieFlow. 233
6.12.5 Enumerations – ControlAreaTypeKind . 234
6.13 Global Used Datatypes . 234
6.13.1 ApparentPower . 234
6.13.2 ActivePower . 234
6.13.3 Voltage . 235
6.13.4 Resistance . 235

6.13.5 ActivePowerPerCurrentFlow . 235

6.13.6 AngleDegrees . 236

6.13.7 CurrentFlow . 236

6.13.8 Inductance . 236

6.13.9 Capacitance . 237

6.13.10 Length . 237

6.13.11 CapacitancePerLength . 237

6.13.12 InductancePerLength . 238

6.13.13 ResistancePerLength . 238

6.13.14 Simple_Float . 239

6.13.15 PerCent . 239
6.13.16 AngleRadians . 239
6.13.17 Reactance . 239
6.13.18 Money . 240
6.13.19 Seconds . 240
6.13.20 Susceptance . 240
6.13.21 Conductance . 241
6.13.22 Temperature . 241
6.13.23 Frequency . 241
6.13.24 RotationSpeed . 242
6.13.25 ReactivePower . 242
6.13.26 ActivePowerPerFrequency . 242
6.13.27 PU . 243
6.13.28 VoltagePerReactivePower . 243
6.13.29 Enumerations . 244
6.13.30 Primitives . 253
7 SteadyStateHypothesisProfile . 253
7.1 General . 253
7.2 (Entsoe) SteadyStateHypothesisVersion(Abstract) . 254
7.3 Core . 255
7.3.1 General . 255
7.3.2 ACDCTerminal(Abstract) . 256
7.3.3 ConductingEquipment(Abstract) . 257
7.3.4 Equipment(Abstract) . 257
7.3.5 IdentifiedObject(Abstract) . 257

7.3.6 PowerSystemResource(Abstract) . 258
7.3.7 (Description) Terminal . 258
7.4 ControlArea . 259
7.4.1 (Description) ControlArea . 259
7.5 DC . 259
7.5.1 General . 259
7.5.2 ACDCConverter(Abstract) . 260
7.5.3 (Description) ACDCConverterDCTerminal . 261
7.5.4 (Description) CsConverter . 261
7.5.5 DCBaseTerminal(Abstract) . 262
7.5.6 (Description) DCTerminal . 262
7.5.7 (Description) VsConverter . 263
7.5.8 Enumerations . 263
7.6 Equivalents . 264

– 8 – IEC TS 61970-600-2:2017 © IEC 2017

7.6.1 EquivalentEquipment(Abstract) . 264

7.6.2 (Description) EquivalentInjection . 265

7.7 Generation . 265

7.7.1 (Description) GeneratingUnit . 265

7.7.2 (Description) HydroGeneratingUnit . 266

7.7.3 (Description) NuclearGeneratingUnit . 266

7.7.4 (Description) SolarGeneratingUnit . 266

7.7.5 (Description) ThermalGeneratingUnit . 267

7.7.6 (Description) WindGeneratingUnit . 267

7.8 Wires . 267

7.8.1 (Description) AsynchronousMachine . 267
7.8.2 (Description) Breaker . 268
7.8.3 (Description) Disconnector. 268
7.8.4 (Description) EnergyConsumer . 269
7.8.5 (Description) EnergySource . 269
7.8.6 (Description) ExternalNetworkInjection . 270
7.8.7 (Operation,ShortCircuit,Description) GroundDisconnector. 270
7.8.8 (Description) LoadBreakSwitch . 270
7.8.9 PhaseTapChanger(Abstract) . 271
7.8.10 (Description) PhaseTapChangerAsymmetrical . 271
7.8.11 (Description) PhaseTapChangerLinear . 271
7.8.12 PhaseTapChangerNonLinear(Abstract) . 272
7.8.13 (Description) PhaseTapChangerSymmetrical . 272
7.8.14 (Description) PhaseTapChangerTabular . 273
7.8.15 ProtectedSwitch(Abstract) . 273
7.8.16 (Description) RatioTapChanger . 273
7.8.17 RegulatingCondEq(Abstract). 274
7.8.18 RotatingMachine(Abstract) . 274
7.8.19 (Description) StaticVarCompensator . 275
7.8.20 (Description) Switch . 275
7.8.21 (Description) SynchronousMachine . 275
7.8.22 (Description) TapChangerControl . 276
7.8.23 (Description) LinearShuntCompensator . 276
7.8.24 (Description) NonlinearShuntCompensator . 277
7.8.25 (Description) RegulatingControl . 277

7.8.26 ShuntCompensator(Abstract) . 278
7.8.27 TapChanger(Abstract) . 278
7.8.28 Enumerations . 279
7.9 LoadModel . 279
7.9.1 (Description) ConformLoad . 279
7.9.2 (Description) NonConformLoad . 280
7.9.3 (Operation,Description) StationSupply . 280
7.10 Global Used Datatypes . 281
7.10.1 Datatypes . 281
7.10.2 Enumerations . 284
7.10.3 Primitives . 286
8 TopologyProfile . 287
8.1 General . 287
8.2 (Entsoe) TopologyVersion(Abstract) . 288

8.3 Core . 289

8.3.1 General . 289

8.3.2 ACDCTerminal(Abstract) . 290

8.3.3 BaseVoltage(Abstract) . 290

8.3.4 (Operation,Description) ConnectivityNode .
...

Questions, Comments and Discussion

Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.

Loading comments...