ASTM E3372-23
(Guide)Standard Guide for Schedule Performance Index, Schedule Beta (βs)
Standard Guide for Schedule Performance Index, Schedule Beta (β<inf>s</inf >)
SIGNIFICANCE AND USE
5.1 The schedule beta (βs) approach produces informational elements: Overall (or composite) schedule beta (βs), schedule beta upside (βs+), and schedule beta downside (βs–)—representing the quantitative components, and the qualitative insight (“early warning”) into the propensity for directional schedule performance for individual schedule participants.
5.1.1 The quantitative component of schedule beta (βs) (inclusive of the upside and downside subvariants) is an index value that depicts schedule participant’s magnitude and direction of movement as compared to the overall project at an assigned value of 1.0, for example, a βs = +2.5 connotes performance of a schedule participant that moves in the same direction as the collection of completed projects at a rate of 2.5 units (schedule days) for each single unit (schedule day) experienced at the overall project level.
5.1.2 The qualitative component of schedule beta (βs) (inclusive of the upside and downside subvariants) provides insight as a cautionary and predictive signal depicting the ability for an individual schedule participant to perform in-keeping with the initially-established as-planned schedule duration(s).
5.2 Schedule beta (βs) also depicts the overall status or health (performing well or not) of a market sector, location and/or trade. Consistent larger schedule beta (βs) values are indicative of external elements (risks) impacting all participants sharing common attribute(s) (that is, trade, location, market sector, etc.).
5.3 Schedule beta (βs) measures current schedule participant performance. As a rolling value (for example, calculated for projects completed during the two most recently completed full calendar years), it depicts the schedule performance ability of the schedule participant. See Note 1.
Note 1: Schedule Data Source and Usage—Schedule beta (βs) (inclusive of the upside and downside subvariants) utilizes schedule data from any schedule calculation method that depicts individ...
SCOPE
1.1 This guide covers schedule beta (βs), which measures construction project participant schedule performance versus that of the overall completed project and is based on beta (β) from financial portfolio theory for measuring the correlation between individual stock performance and that of the overall stock market.2 By correlating the delta of actual activity performance (“as-built”) minus that originally scheduled (“as-planned”) to the delta of as-built minus as-planned for the overall completed project for a participant’s collection of projects over a specified period of time, a schedule performance index is established in a similar manner as the aforementioned beta (β) of an individual stock.
1.2 Schedule beta (βs) measures, as a unitless index value, schedule participant (“subcontractor’s”) performance—ahead or behind—as-planned duration as correlated to its respective overall project’s schedule performance.
1.3 Schedule beta (βs) is measured with input from at least two (2) independent (mutually exclusive) projects that have reached completion, within the defined period of observation.
1.4 Schedule beta (βs) is measured across a standard predetermined period of time, in similar fashion to that of the insurance industry’s experience modification rate’s (EMR) most recent two (2) complete calendar years within the past thirty-six (36) months.
1.5 Schedule beta (βs) evaluates schedule participant’s (“subcontractor’s”) most recent performance, not its complete history, such that is it indicative of current performance and contemporary influences—market, geographic, industry trade, etc.
1.6 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to establish appropriate safety, health, and environmental practices and determine the applicability of regulatory limitations prior to use.
1.7 This internation...
General Information
Relations
Standards Content (Sample)
This international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for the
Development of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.
Designation: E3372 − 23
Standard Guide for
1
Schedule Performance Index, Schedule Beta (β )
s
This standard is issued under the fixed designation E3372; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
INTRODUCTION
The schedule performance index, schedule beta (β ), correlates the performance of network
s
schedule participants (critical path method (CPM)) at the activity level to the overall project
performance on an ongoing basis. The value of the index is representative of the collection of
completed activities within their respective projects over a defined period of time. It identifies the
propensity of schedule participants to fulfill their initial schedule durations (“as-planned”) by
delivering their work on-time, which may be used as an indicator of future performance. Schedule beta
(β ) enables contractors, project managers, supervisors, and schedulers to include indicative
s
performance when assembling construction project teams, evaluate potential participant appropriate-
ness considering schedule time constraints, and improve schedule accuracy and performance.
1. Scope 1.4 Schedule beta (β ) is measured across a standard prede-
s
termined period of time, in similar fashion to that of the
1.1 This guide covers schedule beta (β ), which measures
s
insurance industry’s experience modification rate’s (EMR)
construction project participant schedule performance versus
most recent two (2) complete calendar years within the past
that of the overall completed project and is based on beta (β)
thirty-six (36) months.
from financial portfolio theory for measuring the correlation
between individual stock performance and that of the overall 1.5 Schedule beta (β ) evaluates schedule participant’s
s
2
stock market. By correlating the delta of actual activity (“subcontractor’s”) most recent performance, not its complete
performance (“as-built”) minus that originally scheduled (“as- history, such that is it indicative of current performance and
planned”) to the delta of as-built minus as-planned for the contemporary influences—market, geographic, industry trade,
overall completed project for a participant’s collection of etc.
projects over a specified period of time, a schedule perfor-
1.6 This standard does not purport to address all of the
mance index is established in a similar manner as the afore-
safety concerns, if any, associated with its use. It is the
mentioned beta (β) of an individual stock.
responsibility of the user of this standard to establish appro-
priate safety, health, and environmental practices and deter-
1.2 Schedule beta (β ) measures, as a unitless index value,
s
mine the applicability of regulatory limitations prior to use.
schedule participant (“subcontractor’s”) performance—ahead
1.7 This international standard was developed in accor-
or behind—as-planned duration as correlated to its respective
dance with internationally recognized principles on standard-
overall project’s schedule performance.
ization established in the Decision on Principles for the
1.3 Schedule beta (β ) is measured with input from at least
s
Development of International Standards, Guides and Recom-
two (2) independent (mutually exclusive) projects that have
mendations issued by the World Trade Organization Technical
reached completion, within the defined period of observation.
Barriers to Trade (TBT) Committee.
1 2. Referenced Documents
This guide is under the jurisdiction of ASTM Committee E06 on Performance
of Buildings and is the direct responsibility of Subcommittee E06.81 on Building 3
2.1 ASTM Standards:
Economics.
E631 Terminology of Building Constructions
Current edition approved Feb. 1, 2023. Published June 2023. DOI: 10.1520/
E3372-23. E833 Terminology of Building Economics
2
The schedule performance index, schedule Beta (β ), is based on the Beta (β)
s
factor as found in the Capital Asset Pricing Model (CAPM) of financial portfolio
theory, as formalized by Black, Jensen, and Scholes in Jensen, M. C., Black, F.,
3
Scholes, M. S., “The Capital Asset Pricing Model: Some Empirical Tests.” In For referenced ASTM standards, visit the ASTM website, www.astm.org, or
Studies in the Theory of Capital Markets, ed. M. C. Jensen, Praeger Publishers, Inc., contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM
New York, NY, 1972, which received the 1990 Alfred Nobel Memorial Prize in Standards volume information, refer to the standard’s Document
...
Questions, Comments and Discussion
Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.