ASTM C1758/C1758M-13
(Practice)Standard Practice for Fabricating Test Specimens with Self-Consolidating Concrete
Standard Practice for Fabricating Test Specimens with Self-Consolidating Concrete
SIGNIFICANCE AND USE
4.1 Existing practices and test methods for fabricating fresh concrete test specimens are not suited to SCC. This practice provides requirements and procedures for fabricating test specimens with SCC having a slump flow of 500 mm [20 in.] or greater.
SCOPE
1.1 This practice covers procedures for fabricating test specimens in the laboratory or field using a representative sample of fresh self-consolidating concrete (SCC). This practice is applicable to SCC with a nominal maximum aggregate size up to 25 mm [1 in.] and a slump flow of 500 mm [20 in.] or greater. If the slump flow is less than 500 mm [20 in.] follow the fabrication procedures described in the standard for which the test specimen is required.
1.2 The values stated in either SI units or inch-pound units are to be regarded separately as standard. The values stated in each system may not be exact equivalents; therefore, each system shall be used independently of the other. Combining values from the two systems may result in non-conformance with the standard.
1.3 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility of the user of this standard to establish appropriate safety and health practices and determine the applicability of regulatory limitations prior to use. (Warning—Fresh hydraulic cementitious mixtures are caustic and may cause chemical burns to exposed skin and tissue upon prolonged exposure.2)
1.4 The text of this standard references notes and footnotes which provide explanatory material. These notes and footnotes (excluding those in tables and figures) shall not be considered as requirements of the standard.
General Information
Relations
Buy Standard
Standards Content (Sample)
NOTICE: This standard has either been superseded and replaced by a new version or withdrawn.
Contact ASTM International (www.astm.org) for the latest information
Designation: C1758/C1758M − 13
StandardPractice for
Fabricating Test Specimens with Self-Consolidating
1
Concrete
This standard is issued under the fixed designation C1758/C1758M; the number immediately following the designation indicates the
year of original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last
reapproval. A superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
1. Scope* C125 Terminology Relating to Concrete and Concrete Ag-
gregates
1.1 This practice covers procedures for fabricating test
C172 Practice for Sampling Freshly Mixed Concrete
specimens in the laboratory or field using a representative
C192/C192M Practice for Making and Curing Concrete Test
sample of fresh self-consolidating concrete (SCC). This prac-
Specimens in the Laboratory
tice is applicable to SCC with a nominal maximum aggregate
C1611/C1611M Test Method for Slump Flow of Self-
size up to 25 mm [1 in.] and a slump flow of 500 mm [20 in.]
Consolidating Concrete
or greater. If the slump flow is less than 500 mm [20 in.] follow
the fabrication procedures described in the standard for which
3. Terminology
the test specimen is required.
3.1 Definitions:
1.2 The values stated in either SI units or inch-pound units
3.1.1 For definitions of terms used in this practice, refer to
are to be regarded separately as standard. The values stated in
Terminology C125.
each system may not be exact equivalents; therefore, each
3.2 Definitions of Terms Specific to This Standard:
system shall be used independently of the other. Combining
values from the two systems may result in non-conformance 3.2.1 test specimen, n—self-consolidating concrete placed
in a mold, measure, measuring bowl, or other container
with the standard.
following this standard with the top surface struck off and
1.3 This standard does not purport to address all of the
finished following the standard for which the test specimen is
safety concerns, if any, associated with its use. It is the
required.
responsibility of the user of this standard to establish appro-
priate safety and health practices and determine the applica-
4. Significance and Use
bility of regulatory limitations prior to use. (Warning—Fresh
4.1 Existing practices and test methods for fabricating fresh
hydraulic cementitious mixtures are caustic and may cause
concrete test specimens are not suited to SCC. This practice
chemical burns to exposed skin and tissue upon prolonged
2
provides requirements and procedures for fabricating test
exposure. )
specimens with SCC having a slump flow of 500 mm [20 in.]
1.4 The text of this standard references notes and footnotes
or greater.
which provide explanatory material. These notes and footnotes
(excluding those in tables and figures) shall not be considered
5. Apparatus
as requirements of the standard.
5.1 Specimen Container—Molds, measures, measuring
2. Referenced Documents
bowls, and containers used for fabricating test specimens
3
according to this practice shall conform to the requirements
2.1 ASTM Standards:
described in the standard for which the test specimen is
required.
1
This practice is under the jurisdiction of ASTM Committee C09 on Concrete
5.2 Sample Receptacle—A pan or wheelbarrow that is
andConcreteAggregatesandisthedirectresponsibilityofSubcommitteeC09.47on
water-tight, has a nonabsorbent surface, and is large enough to
Self-Consolidating Concrete.
retain a volume of concrete sufficient to fill all necessary
CurrenteditionapprovedJune1,2013.PublishedJuly2013.Originallyapproved
in 2011. Last previous edition approved in 2011 as C1758/C1758M-11. DOI:
specimen containers.
10.1520/C1758_C1758M-13.
2
5.3 Pouring Vessel for SCC—Awater-tight container having
See section on Safety Precautions, Manual of Aggregate and Concrete Testing,
Annual Book of ASTM Standards, Vol. 04.02.
a size large enough so each amount of concrete obtained from
3
For referenced ASTM standards, visit the ASTM website, www.astm.org, or
the sampling receptacle is representative and small enough so
contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM
concrete is not spilled during placement in the specimen
Standards volume information, refer to the standard’s Document Summary page on
the ASTM website. container.
*A Summary of Changes section appears at the end of this standard
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
1
---------------------- Page: 1 ----------------------
C1758/C1758M − 13
NOTE 1—A pouring vessel with a pouring lip is useful in reducing the
7.3 Fill the pouring vessel with a representative portion of
probability of concrete spilling while filling the specimen container.
SCC from the sample receptacle, either by passing the po
...
This document is not an ASTM standard and is intended only to provide the user of an ASTM standard an indication of what changes have been made to the previous version. Because
it may not be technically possible to adequately depict all changes accurately, ASTM recommends that users consult prior editions as appropriate. In all cases only the current version
of the standard as published by ASTM is to be considered the official document.
Designation: C1758/C1758M − 11 C1758/C1758M − 13
Standard Practice for
Fabricating Test Specimens with Self-Consolidating
1
Concrete
This standard is issued under the fixed designation C1758/C1758M; the number immediately following the designation indicates the
year of original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last
reapproval. A superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
1. Scope Scope*
1.1 This practice covers procedures for fabricating test specimens in the laboratory or field using a representative sample of
fresh self-consolidating concrete (SCC). This practice is applicable to SCC with a nominal maximum aggregate size up to 25 mm
[1 in.] and a slump flow of 500 mm [20 in.] or greater. If the slump flow is less than 500 mm [20 in.] follow the fabrication
procedures described in the standard for which the test specimen is required.
NOTE 1—If the slump flow is less then 500 mm [20 in.] follow the fabrication procedures described in the standard for which the test specimen is
required.
1.2 The values stated in either SI units or inch-pound units are to be regarded separately as standard. The values stated in each
system may not be exact equivalents; therefore, each system shall be used independently of the other. Combining values from the
two systems may result in non-conformance with the standard.
1.3 This standard does not purport to address all of the safety concerns, if any, associated with its use. It is the responsibility
of the user of this standard to establish appropriate safety and health practices and determine the applicability of regulatory
limitations prior to use. (Warning—Fresh hydraulic cementitious mixtures are caustic and may cause chemical burns to exposed
2
skin and tissue upon prolonged exposure. )
1.4 The text of this standard references notes and footnotes which provide explanatory material. These notes and footnotes
(excluding those in tables and figures) shall not be considered as requirements of the standard.
2. Referenced Documents
3
2.1 ASTM Standards:
C125 Terminology Relating to Concrete and Concrete Aggregates
C172 Practice for Sampling Freshly Mixed Concrete
C192/C192M Practice for Making and Curing Concrete Test Specimens in the Laboratory
C1611/C1611M Test Method for Slump Flow of Self-Consolidating Concrete
3. Terminology
3.1 Definitions:
3.1.1 For definitions of terms used in this practice, refer to Terminology C125.
3.2 Definitions of Terms Specific to This Standard:
3.2.1 test specimen, n—self-consolidating concrete placed in a mold, measure, measuring bowl, or other container following this
standard with the top surface struck off and finished following the standard for which the test specimen is required.
4. Significance and Use
4.1 Existing practices and test methods for fabricating fresh concrete test specimens are not suited to SCC. This practice
provides requirements and procedures for fabricating test specimens with SCC having a slump flow of 500 mm [20 in.] or greater.
1
This practice is under the jurisdiction of ASTM Committee C09 on Concrete and Concrete Aggregates and is the direct responsibility of Subcommittee C09.47 on
Self-Consolidating Concrete.
Current edition approved Nov. 1, 2011June 1, 2013. Published January 2012July 2013. Originally approved in 2011. Last previous edition approved in 2011 as
C1758/C1758M-11. DOI: 10.1520/C1758_C1758M-11.
2
See section on Safety Precautions, Manual of Aggregate and Concrete Testing,Annual Book of ASTM Standards, Vol. 04.02.
3
For referenced ASTM standards, visit the ASTM website, www.astm.org, or contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM Standards
volume information, refer to the standard’s Document Summary page on the ASTM website.
*A Summary of Changes section appears at the end of this standard
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
1
---------------------- Page: 1 ----------------------
C1758/C1758M − 13
5. Apparatus
5.1 Specimen Container—Molds, measures, measuring bowls, and containers used for fabricating test specimens according to
this practice shall conform to the requirements described in the standard for which the test specimen is required.
5.2 Sample Receptacle—A pan or wheelbarrow that is water-tight, has a nonabsorbent surface, and is large enough to retain a
volume of concrete sufficient to fill all necessary specimen containers.
5.3 Pouring
...