EN IEC 63223-2:2026
(Main)Management of network assets in power systems - Part 2: Risk-informed decision-making process
- Abstract
This document specifies requirements, recommendations, and examples for implementing a risk-informed decision-making (RIDM) process for managing existing network assets in power systems. The intended audience concerns power network organizations' stakeholders and decision makers, such as asset managers, risk managers, regulators, asset owners, and service providers. The RIDM process details the steps to ensure transparency, consistency, and traceability of the decision by:
– specifying the risk decision-making context depending on asset management objectives, available knowledge, and risk stakeholders' concerns;
– identifying the appropriate risk management strategies and the knowledge supporting the analyses;
– detailing the essential steps for conducting a risk analysis and justifying investments, regardless of the calculation methods used;
– providing essential information and warnings to decision makers;
– implementing performance evaluation and continuous improvement.
The document is based on the asset management principles from ISO 55000:2024 [1] and is aligned with ISO 55001:2024 [2]. Compliance with the requirements of this document is independent of compliance with ISO 55001:2024 [2].
- Status
- Published
- Publication Date
- 10-Sep-2026
- Technical Committee
- CLC/SR 123 - Management of network assets in power systems
- Drafting Committee
- TC 123 - Management of network assets in power systems
- Current Stage
- 6060 - Document made available - Publishing
- Start Date
- 11-Sep-2026
- Due Date
- 05-Sep-2025
- Completion Date
- 05-Sep-2025
EN IEC 63223-2:2026 is a CENELEC European Standard that adopts IEC 63223-2:2026 without modification. It specifies a risk-informed decision-making (RIDM) process for managing existing network assets in power systems. The document is written for people who decide, assess, maintain, regulate, own, or supply those assets and need a structured way to justify actions, compare options, and keep decisions traceable.
What does EN IEC 63223-2:2026 specify?
EN IEC 63223-2:2026 specifies an RIDM process for existing network assets in power systems, with an emphasis on transparency, consistency, traceability, and continual improvement. It sets out how to frame the decision, assess risk, choose among risk control options, review judgments, and monitor results in an asset management context.
The document is organized into:
- Clause 1, Scope
- Clause 2, Normative references
- Clause 3, Terms, definitions and abbreviated terms
- Clause 4, Risk-informed decision-making process and principles
- Clause 5, Risk decision-making context
- Clause 6, Risk management strategies
- Clause 7, Managerial review and judgement
- Clause 8, Performance evaluation and improvement
- Bibliography
- Annex ZA on normative references to international publications
| Annex | What it covers |
|---|---|
| Annex ZA | Normative references to international publications and their corresponding European publications |
In practice, this structure matters because the standard does not jump straight to calculations. It first asks the organization to define the asset group, the context, and the decision criteria, then to select the right strategy for the kind of uncertainty involved.
What are the key requirements of EN IEC 63223-2:2026?
Set the asset-management frame before making risk decisions
Clause 4.2 requires the organization to define the asset portfolio covered by the RIDM process, the decision-making criteria, the asset management objectives, and the asset management plan(s). These elements must be kept as documented information and updated.
For a power network organization, this means the decision process starts with a clear boundary: which lines, substations, protection devices, communications assets, or other assets are in scope, what objectives they serve, and what criteria will be used to compare options. Without that frame, risk comparisons are not consistent.
Run RIDM as an iterative and documented process
Clause 4.3 requires the organization to establish documented information for the RIDM process itself and for each iteration. It also assigns roles for analysts, decision makers, and evaluators, and says the organization should update the process when the context changes.
This matters because the standard treats RIDM as a repeatable cycle, not a one-time study. New alternatives, changed operating conditions, climate effects, or changed stakeholder expectations can trigger a new iteration.
Identify the risk context before quantifying anything
Clause 5 requires risk identification, knowledge characterization, and documentation of stakeholders’ concerns. The organization must define the asset group, identify events and their causes and consequences, record existing and previously considered controls, and capture the sources of information and any lack of consensus.
In practice, this step separates “what can go wrong, for whom, and why” from later calculations. It is also where the organization records whether the issue is mainly about variability, weak knowledge, or conflicting values.
Use the risk management strategy that matches the uncertainty
Clause 6 distinguishes three strategies:
- risk analysis
- the cautionary principle
- the discursive strategy
Risk analysis in 6.1 is for comparing risk mitigation options when knowledge is sufficient for a quantitative approach. The organization must define probability models, value the consequences, evaluate option performance against decision criteria, and state the strength of knowledge behind assumptions, data, and models.
The cautionary principle in 6.2 applies when uncertainty is significant and consequences may be severe. The organization then focuses on improving knowledge and choosing temporary or precautionary controls that reduce risk without creating new problems for stakeholders.
The discursive strategy in 6.3 applies when stakeholders do not agree on values, priorities, or objectives. The organization must share the risk representation and knowledge, seek alignment on objectives and controls, and document unresolved conflicts if consensus is not reached.
Make managerial review explicit
Clause 7 requires review of the analysis quality, the performance of chosen controls, and portfolio-level effects. The organization must check analyst competence and independence, confirm that the required steps were completed, and note any lack of consensus among analysts.
This matters because the standard expects decision makers to see not only the preferred option, but also the strength of the evidence, the operational impact, the resources needed, and any constraints or conflicts with other projects in the asset portfolio.
Monitor results and feed lessons back into the next cycle
Clause 8 requires the organization to monitor implementation, review deviations, and improve the process. Indicators should cover the deployment of controls, their costs, and residual risks.
In practice, this means comparing planned and actual outcomes, asking whether assumptions or models were valid, and deciding what knowledge, data, or control changes are needed for the next RIDM iteration.
What terms does EN IEC 63223-2:2026 define?
- RIDM - Risk-informed decision-making, the iterative process used in this standard to support decisions about network assets.
- Risk - The effect of uncertainty on objectives, including both threats and opportunities.
- Uncertainty - A state of incomplete information or knowledge that can affect understanding and decision-making.
- Consequence - The outcome of an event that affects objectives, positively or negatively.
- Asset portfolio - The set of assets within the scope of the asset management system.
- Asset management plan - Documented information that specifies activities, resources, and timescales needed to achieve asset management objectives.
- Stakeholder - An organization that can affect, be affected by, or perceive itself to be affected by a decision or activity.
- Risk control - A measure that maintains and/or modifies risk.
Who uses EN IEC 63223-2:2026?
EN IEC 63223-2:2026 is intended for stakeholders and decision makers in power network organizations. The introduction names asset managers, risk managers, regulators, asset owners, and service providers as key users.
It is most relevant where people must decide on renewal, inspection, monitoring, preventive replacement, temporary controls, or portfolio-level trade-offs for transmission and distribution assets. Quality and planning teams can use it to document why a decision was made, what evidence supported it, and how the outcome will be checked later.
Which standards are used with EN IEC 63223-2:2026?
IEC 60050-693 is the normative vocabulary base for the document. It supplies the terminology for management of network assets in power systems.
IEC 63223-1:2026 is the companion part for the series. It provides the overview, principles, and terminology that frame this part.
ISO 55000:2024 and ISO 55001:2024 provide the asset management principles and asset management system requirements that this document aligns with. EN IEC 63223-2:2026 says its RIDM process is independent of, but aligned with, ISO 55001.
IEC 31010:2019 supports the selection of risk assessment techniques. ISO 31000:2018 and ISO 31073:2022 provide the broader risk management guideline and vocabulary basis used in the document. IEC TS 63224:2025 is also cited for asset management aspects of power system network organizations.
What does the EN IEC 63223-2:2026 document contain?
EN IEC 63223-2:2026 contains a conceptual model of RIDM, a step-by-step process, and examples that help organizations apply the process to network assets. Figure 1 explains the three main risk management strategies and how they relate to aleatory uncertainty, epistemic uncertainty, and normative ambiguity.
Figure 2 presents the overall RIDM flow for managing power system network assets, from risk context through review and improvement. Table 1 gives an example of how some preventive risk mitigation options can be compared using parameters to optimize, implementation costs, and residual risks.
The document also includes examples of probability models, consequence valuation, and cautionary measures. Those examples are meant to support design, analysis, and decision review, not to prescribe one fixed calculation method.
Get Certified
Connect with accredited certification bodies for this standard

BSI Group
BSI (British Standards Institution) is the business standards company that helps organizations make excellence a habit.

Bureau Veritas
Bureau Veritas is a world leader in laboratory testing, inspection and certification services.

DNV
DNV is an independent assurance and risk management provider.
Sponsored listings
Frequently Asked Questions
EN IEC 63223-2:2026 is a standard published by CLC. Its full title is "Management of network assets in power systems - Part 2: Risk-informed decision-making process". This standard covers: This document specifies requirements, recommendations, and examples for implementing a risk-informed decision-making (RIDM) process for managing existing network assets in power systems. The intended audience concerns power network organizations' stakeholders and decision makers, such as asset managers, risk managers, regulators, asset owners, and service providers. The RIDM process details the steps to ensure transparency, consistency, and traceability of the decision by: – specifying the risk decision-making context depending on asset management objectives, available knowledge, and risk stakeholders' concerns; – identifying the appropriate risk management strategies and the knowledge supporting the analyses; – detailing the essential steps for conducting a risk analysis and justifying investments, regardless of the calculation methods used; – providing essential information and warnings to decision makers; – implementing performance evaluation and continuous improvement. The document is based on the asset management principles from ISO 55000:2024 [1] and is aligned with ISO 55001:2024 [2]. Compliance with the requirements of this document is independent of compliance with ISO 55001:2024 [2].
This document specifies requirements, recommendations, and examples for implementing a risk-informed decision-making (RIDM) process for managing existing network assets in power systems. The intended audience concerns power network organizations' stakeholders and decision makers, such as asset managers, risk managers, regulators, asset owners, and service providers. The RIDM process details the steps to ensure transparency, consistency, and traceability of the decision by: – specifying the risk decision-making context depending on asset management objectives, available knowledge, and risk stakeholders' concerns; – identifying the appropriate risk management strategies and the knowledge supporting the analyses; – detailing the essential steps for conducting a risk analysis and justifying investments, regardless of the calculation methods used; – providing essential information and warnings to decision makers; – implementing performance evaluation and continuous improvement. The document is based on the asset management principles from ISO 55000:2024 [1] and is aligned with ISO 55001:2024 [2]. Compliance with the requirements of this document is independent of compliance with ISO 55001:2024 [2].
EN IEC 63223-2:2026 is classified under the following ICS (International Classification for Standards) categories: 03.100.01 - Company organization and management in general; 29.240.01 - Power transmission and distribution networks in general. The ICS classification helps identify the subject area and facilitates finding related standards.
EN IEC 63223-2:2026 is available in PDF format for immediate download after purchase. The document can be added to your cart and obtained through the secure checkout process. Digital delivery ensures instant access to the complete standard document.
Standards Content (Sample)
Contents
- 0.1 General
- 0.2 Benefits of the risk-informed decision-making process
- 0.3 Relationship to asset management system
- 1 Scope
- 2 Normative references
- 3 Terms, definitions and abbreviated terms
- 3.1 Terms and definitions
- 3.1.1 risk
- 3.1.2 objective
- 3.1.3 uncertainty
- 3.1.4 consequence
- 3.1.5 event
- 3.1.6 organization
- 3.1.7 stakeholder
- 3.1.8 risk control
- 3.1.9 documented information
- 3.1.10 asset
- 3.1.11 asset portfolio
- 3.1.12 asset management
- 3.1.13 asset management plan
- 3.2 Abbreviated terms
- 4 Risk-informed decision-making process and principles
- 4.1 Core concepts of risk science
- 4.2 Asset management requirements
- 4.3 Risk-informed decision-making process implementation
- 5 Risk decision-making context
- 5.1 Risk identification
- 5.2 Knowledge characterization
- 5.3 Stakeholders' concerns
- 6 Risk management strategies
- 6.1 Risk analysis
- 6.2 Cautionary principle
- 6.3 Discursive strategy
- 7 Managerial review and judgement
- 7.1 Quality of the analyses
- 7.2 Risk control option analysis
- 7.3 Portfolio analysis
- 8 Performance evaluation and improvement
- 8.1 Monitoring the decision
- 8.2 Reviewing
- 8.3 Improving
- Bibliography
INTRODUCTION
0.1 General
This document specifies requirements, recommendations, and examples for implementing a risk-informed decision-making (RIDM) process for managing existing network assets on power systems. The main intended audience includes power network organizations’ stakeholders and decision makers, such as asset managers, risk managers, regulators, asset owners, and service providers.
ISO 55000:2024 [1] and ISO 55001:2024 [2] provide asset management principles and asset management system requirements for any organization. IEC TS 63224:2025 [3] gives recommendations for asset management aspects of power system network organizations. The IEC 63223 series [4] aims to establish International Standards specific to asset management for power system networks. While IEC 63223-1:2026 [5] provides an overview of the scope, principles, and terminology, this document focuses on a process for making risk-informed decisions regarding existing assets. These decisions are driven by the creation of asset related value through mitigation of the risks. Quantitative assessments such as cost-benefit analyses are generally the most advisable approach to justify renewal investments and risk mitigation measures such as inspections and monitoring. However, risk analysis relies on calculation and expert judgment, which depend on assumptions, models, and data that are not always validated. As a result, the outcomes can mislead decision makers if they do not adequately account for all uncertainties and risk controls derived from other risk management strategies such as the cautionary principle and the discursive strategy.
This document intends to support and inform asset managers, decision makers, and stakeholders affected by the risk in establishing the appropriate risk management approach consistent with the asset management objectives, decision-making criteria, and the risk decision-making context. It details the necessary steps for controlling risks in an asset management framework by specifying:
- the risk decision-making context with regard to asset management objectives, available knowledge, and internal and external stakeholders' concerns;
- the relevant risk management strategies consistent with the risk decision-making context (risk analysis, cautionary principle, and discursive strategy);
- essential criteria to support decision-making;
- evaluation criteria and actions to ensure continual improvement. The RIDM process aims to support decision-making without mandating a specific method or providing detailed calculations for particular risk assessment techniques. It encourages the use of appropriate methods in each step, referencing other standards or scientific sources, such as the risk assessment techniques outlined in IEC 31010:2019 [6]. It also enhances the process described in IEC 31010:2019 [6] and ISO 31000:2018 [7] by integrating the asset management principles and providing guidelines to handle all manifestations of uncertainty.
0.2 Benefits of the risk-informed decision-making process
The RIDM process provides a structured approach for managing the risks of network assets in power systems. It contributes to achieving the organizational objectives by ensuring transparency, consistency, and traceability of risk-informed decisions, and detailing the steps that support asset management stakeholders in their analyses by:
- providing guidance on the appropriate category of risk assessment techniques at each step of the process (risk identification, risk analysis, comparing risk mitigation options);
- providing essential information and warnings when performing a risk analysis by:
Numbers in square brackets refer to the Bibliography.
SIST EN IEC 63223-2:2026
- specifying the essential information for the risk analysis (probability model, consequences, performance criteria);
- specifying the strength of knowledge supporting assumptions, models and parameters;
- guiding toward other complementary risk management strategies when necessary, deliberating on risk analysis output and detecting constraints and conflicts by:
- comparing options based on their performance;
- considering the background knowledge supporting the risk analysis;
- identifying the impacts of the decisions on the asset portfolio and for stakeholders;
- implementing performance evaluation and continuous improvement, including:
- enhancing knowledge through information gathering, data collection, or experimentation;
- identifying deviations from assumptions or expected performance;
- ensuring that lessons learned are incorporated into future iterations of the process.
0.3 Relationship to asset management system
This document is based on the principles of asset management outlined in ISO 55000:2024 [1]. The focus is on implementing an RIDM process to mitigate network asset risks in power systems. Subclause 4.2 introduces essential elements of asset management and associated requirements. The requirements are independent but aligned with those of ISO 55001:2024 [2]. In the case of an asset management system conforming to ISO 55001:2024 [2], the RIDM process is part of the asset management decision-making framework described in 4.5 of ISO 55001:2024 [2], which is included in the strategic asset management plan according to 6.2 of the same standard. In addition, the RIDM process helps contribute to satisfying several subclauses of ISO 55001:2024 [2], including:
- subclause 4.5 Asset management decision-making;
- subclause 6.1 Actions to address risks and opportunities;
- subclause 7.6 Data and information;
- subclause 7.7 Knowledge;
- subclause 9.1 Monitoring, measurement, analysis, and evaluation.
SIST EN IEC 63223-2:2026
1 Scope
This document specifies requirements, recommendations, and examples for implementing a risk-informed decision-making (RIDM) process for managing existing network assets in power systems. The intended audience concerns power network organizations' stakeholders and decision makers, such as asset managers, risk managers, regulators, asset owners, and service providers. The RIDM process details the steps to ensure transparency, consistency, and traceability of the decision by:
- specifying the risk decision-making context depending on asset management objectives, available knowledge, and risk stakeholders' concerns;
- identifying the appropriate risk management strategies and the knowledge supporting the analyses;
- detailing the essential steps for conducting a risk analysis and justifying investments, regardless of the calculation methods used;
- providing essential information and warnings to decision makers;
- implementing performance evaluation and continuous improvement. The document is based on the asset management principles from ISO 55000:2024 [1] and is aligned with ISO 55001:2024 [2]. Compliance with the requirements of this document is independent of compliance with ISO 55001:2024 [2].
2 Normative references
The following documents are referred to in the text in such a way that some or all of their content constitutes requirements of this document. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies.
IEC 60050-693:—, International Electrotechnical Vocabulary (IEV) - Part 693: Management of network assets in power systems
3 Terms, definitions and abbreviated terms
3.1 Terms and definitions
For the purposes of this document, the terms and definitions given in IEC 60050-693:— as well as the following apply.
ISO and IEC maintain terminology databases for use in standardization at the following addresses:
- IEC Electropedia: available at https://www.electropedia.org/
- ISO Online browsing platform: available at https://www.iso.org/obp
3.1.1 risk
effect of uncertainty (3.1.3) on objectives (3.1.2) Note 1 to entry: An effect is a deviation from the expected. It can be positive, negative or both, and can address, create or result in opportunities and threats.
Note 2 to entry: objectives (3.1.2) can have different aspects and categories, and can be applied at different levels.
Under preparation. Stage at the time of publication: IEC FDIS 60050-693:2025
SIST EN IEC 63223-2:2026
Note 3 to entry: Risk is usually expressed in terms of risk sources, potential events, their consequences and their likelihood.
[SOURCE: ISO 31073:2022 [8], 3.1.1]
3.1.2 objective
result to be achieved Note 1 to entry: An objective can be strategic, tactical or operational. Note 2 to entry: Objectives can relate to different disciplines (such as finance, health and safety, and environmental). They can be, for example, organization-wide or specific to a project, service, product or process (IEV 693-01-19).
Note 3 to entry: An objective can be expressed in other ways, e.g. as an intended result, as a purpose, as an operational criterion, as an asset management objective or by the use of other words with similar meaning (e.g. aim, goal, or target).
Note 4 to entry: In the context of asset management systems (IEV 693-01-39), asset management objectives are set by the organization (3.1.6), consistent with the asset management policy (IEV 693-01-18), to achieve specific results.
[SOURCE: IEC 60050-693:— [9], 693-01-12]
3.1.3 uncertainty
state, even partial, of deficiency of information related to understanding or knowledge Note 1 to entry: In some cases, uncertainty can be related to the organization's (3.1.6) context as well as to its objective (3.1.2).
Note 2 to entry: Uncertainty is the root source of risk (3.1.1), namely any kind of "deficiency of information" that matters in relation to objectives (3.1.2) (and objectives, in turn, relate to all relevant interested parties’ needs and expectations).
[SOURCE: ISO 31073:2022 [8], 3.1.3]
3.1.4 consequence
outcome of an event (3.1.5) affecting objectives (3.1.2) Note 1 to entry: A consequence can have positive or negative, direct or indirect, effects on objectives. Note 2 to entry: Consequences can be expressed qualitatively or quantitatively. Note 3 to entry: Any consequence can escalate through cascading and cumulative effects. [SOURCE: IEC 60050-693:— [9], 693-03-14]
3.1.5 event
occurrence or change of a particular set of circumstances Note 1 to entry: An event can have one or more occurrences, and can have several causes and several consequences (3.1.4).
Note 2 to entry: An event can also be something that is expected which does not happen, or something that is not expected which does happen.
Note 3 to entry: An event can be a a risk source.
[SOURCE: IEC 60050-693:— [9], 693-03-09]
SIST EN IEC 63223-2:2026
3.1.6 organization
person or group of people that has its own functions with responsibilities, authorities and relationships to achieve its objectives (3.1.2) Note 1 to entry: The concept of organization includes, but is not limited to, sole-trader, company, corporation, firm, enterprise, authority, partnership, charity or institution, or part or combination thereof, whether incorporated or not, public or private.
Note 2 to entry: If the organization is part of a larger entity, the term "organization" refers only to the part of the larger entity that is within the scope of the asset management system (IEV 693-01-38). [SOURCE: IEC 60050-693:— [9], 693-01-13]
3.1.7 stakeholder
organization (3.1.6) that can affect, be affected by, or perceive itself to be affected by a decision or activity [SOURCE: IEC 60050-693:— [9], 693-01-23]
3.1.8 risk control
measure that maintains and/or modifies risk (3.1.1) Note 1 to entry: Risk controls include, but are not limited to, any process, policy, device, practice, or other conditions and/or actions which maintain and/or modify risk.
Note 2 to entry: Risk controls do not always exert the intended or assumed modifying effect. [SOURCE: ISO 31073:2022 [8], 3.3.33]
3.1.9 documented information
information required to be controlled and maintained by an organization (3.1.6) and the medium on which it is contained Note 1 to entry: Documented information can be in any format and media and from any source. Note 2 to entry: Documented information can refer to:
- the management system (IEV 693-01-38), including related processes;
- information created in order for the organization to operate (documentation);
- evidence of results achieved (e.g. records).
[SOURCE: IEC 60050-693:— [9], 693-01-06]
3.1.10 asset
item, thing or entity that has potential or actual value to an organization (3.1.6) Note 1 to entry: Assets can be physical or non-physical.
Note 2 to entry: A grouping of assets referred to as an asset system (IEV 693-01-28) can also be considered as an asset.
[SOURCE: IEC 60050-693:— [9], 693-01-25]
SIST EN IEC 63223-2:2026
3.1.11 asset portfolio
set of assets (3.1.10) that are within the scope of the asset management system (IEV 693-01-39) Note 1 to entry: A portfolio is typically established and assigned for managerial control purposes. [SOURCE: IEC 60050-693:— [9], 693-01-27]
3.1.12 asset management
coordinated activity of an organization (3.1.6) to realize value from assets (3.1.10) Note 1 to entry: Realization of value will normally involve a balancing of costs, risks (3.1.1), opportunities and performance (IEV 693-01-17) benefits.
Note 2 to entry: Activity can also refer to the application of the elements of the asset management system (IEV 693-01-39).
Note 3 to entry: The term "activity" has a broad meaning and can include, for example, the approach, the planning, the plans and their implementation.
[SOURCE: IEC 60050-693:— [9], 693-01-31]
3.1.13 asset management plan
documented information (3.1.9) that specifies the activities, resources and timescales required for an individual asset (3.1.10), or a grouping of assets, to achieve the organization's (3.1.6) asset management (3.1.12) objective (3.1.2) Note 1 to entry: The grouping of assets can be by asset type (IEV 693-01-29), asset class, asset system (IEV 693- 517 01-28) or asset portfolio (3.1.11).
Note 2 to entry: An asset management plan is derived from the strategic asset management plan (IEV 693-01-32). Note 3 to entry: An asset management plan can be contained in, or can be a subsidiary plan of, the strategic asset management plan.
[SOURCE: IEC 60050-693:— [9], 693-01-33]
3.2 Abbreviated terms
RIDM Risk-informed decision-making
4 Risk-informed decision-making process and principles
4.1 Core concepts of risk science
4.1.1 General
The management of power network assets is significantly influenced by risk, particularly due to asset failures. Effectively managing risk requires a sound understanding of the essential concepts of risk science, as appropriate risk controls depend heavily on the nature of the uncertainties involved. Risk science establishes the foundational concepts and principles necessary for understanding, characterizing, evaluating, and managing risks. The formal definitions applicable to this document are those established in 3.1, while 4.1.2, 4.1.3, 4.1.4 and 4.1.5 provide additional references, explanations, and comments to facilitate understanding and to support the development in 4.1.6 of the three main risk management strategies central to the process.
SIST EN IEC 63223-2:2026
4.1.2 Uncertainty
Uncertainty reflects incomplete information or knowledge related to assumptions, quantities, events, and their occurrence [10]. It is generally categorized into the following types (see IEC 31010:2019 [6], [11] and [12]):
- Aleatory uncertainty refers to the inherent variability in a phenomenon or within a population, such as time to failure, deterioration increment, or failure occurrence within a specific time interval following a monitoring alert for an asset fleet. Aleatory uncertainty is mainly represented by a probability model, such as the probability distribution of the time-to-failure within an asset fleet or a stochastic process describing the deterioration of an asset over time.
- Epistemic uncertainty arises from incomplete information or knowledge, affecting understanding of the problem under consideration and the ability to model it. In quantitative assessment, epistemic uncertainty refers to the lack of justification or validation of assumptions, models, and parameter values, reflecting issues with scientific knowledge of the problem, data, or accuracy. It can result from complexity (the difficulties in predicting a system's behaviour despite knowledge of its components) and interpretative ambiguity due to differing interpretations of an assessment's results.
- Normative ambiguity involves differing implicit values, priorities, or objectives among stakeholders. This can manifest as constraints on the resources required to implement decisions, conflicts between decisions and operational rules, or issues of responsibility arising after an undesired event (involving decision makers, affected stakeholders, and legally accountable parties).
Recognizing and addressing these dimensions of uncertainty is crucial in risk management, as they guide the selection of appropriate strategies for risk mitigation and decision-making.
4.1.3 Risk
In this document, risk is considered as the combination of consequences related to an event or activity and the associated uncertainties, as introduced in 4.1.2 (see IEC 31010:2019 [6] and [10]). This document mainly addresses undesired consequences relating to network assets on power systems and the organization's objectives.
4.1.4 Risk representation
The three dimensions of uncertainty indicate that the same risk is not necessarily perceived in the same way by different stakeholders. This perception varies depending on their knowledge, the consequences that affect them directly, and their objectives or priorities. To distinguish the concept of risk from its representation, which can vary among stakeholders, this representation can be described as the combination of:
- the choice of undesired consequences;
- the choice of probability models, particularly those reflecting aleatory uncertainty;
- the supporting knowledge that justifies the description.
This approach highlights the central role of knowledge, as well as its limitations, in the perception of risk. Normative ambiguity arises when there is no alignment among stakeholders regarding this representation. Differences can concern:
- the choice of undesired consequences (range, magnitude, or value);
- the choice of probability models (event occurrence, or distribution of consequence magnitude);
- the supporting knowledge (lack of consensus, or indicators challenging the validity of assumptions, models, or parameter values).
SIST EN IEC 63223-2:2026
4.1.5 Risk control
Risk control is a measure intended to modify risk . It includes any actions having an impact on the consequences or the associated uncertainties by:
- improving knowledge when there are significant epistemic uncertainties;
- clearing up ambiguities from assessment results, differing values or priorities among risk stakeholders;
- reducing or preventing the occurrence of an undesirable event through preventive measures;
- minimizing the consequences of an undesirable event through preventive or protective measures;
- limiting the extent of the consequences of an undesirable event through reactive actions. In this document, the expressions risk mitigation option and cautionary measures are also employed to refer to types of risk controls in specific contexts:
- risk mitigation option refers to a risk control whose performance is compared with other options during risk analysis in 6.1;
- cautionary measures refers to risk controls applied under the cautionary principle in 6.2 when there is significant uncertainty.
...