Electrical and instrumentation loop check

describes the steps recommended to complete a loop check, which comprises the activities between the completion of the loop construction (including installation and point-to-point checks) and the start-up of cold commissioning. Is applicable for the construction of new plants and for expansion/retrofits (i.e. revamping) of E&I installations in existing plants (including PLC, BAS, DCS, panel-mounted and field instrumentation). It does not include a detailed checkout of power distribution systems, except as they relate to the loops being checked (i.e. a motor starter or a power supply to a four-wire transmitter).

General Information

Status
Published
Publication Date
14-Nov-2006
Current Stage
DELPUB - Deleted Publication
Completion Date
08-Nov-2012
Ref Project

Relations

Buy Standard

Standard
iec62382{ed1.0}en - IEC 62382:2006 - Electrical and instrumentation loop check Released:11/15/2006 Isbn:2831888891
English language
18 pages
sale 15% off
Preview
sale 15% off
Preview

Standards Content (Sample)


INTERNATIONAL IEC
STANDARD 62382
First edition
2006-11
Electrical and instrumentation loop check

Reference number
Publication numbering
As from 1 January 1997 all IEC publications are issued with a designation in the
60000 series. For example, IEC 34-1 is now referred to as IEC 60034-1.
Consolidated editions
The IEC is now publishing consolidated versions of its publications. For example,
edition numbers 1.0, 1.1 and 1.2 refer, respectively, to the base publication, the
base publication incorporating amendment 1 and the base publication incorporating
amendments 1 and 2.
Further information on IEC publications
The technical content of IEC publications is kept under constant review by the IEC,
thus ensuring that the content reflects current technology. Information relating to
this publication, including its validity, is available in the IEC Catalogue of
publications (see below) in addition to new editions, amendments and corrigenda.
Information on the subjects under consideration and work in progress undertaken
by the technical committee which has prepared this publication, as well as the list
of publications issued, is also available from the following:
• IEC Web Site (www.iec.ch)
• Catalogue of IEC publications
The on-line catalogue on the IEC web site (www.iec.ch/searchpub) enables you to
search by a variety of criteria including text searches, technical committees
and date of publication. On-line information is also available on recently issued
publications, withdrawn and replaced publications, as well as corrigenda.
• IEC Just Published
This summary of recently issued publications (www.iec.ch/online_news/ justpub)
is also available by email. Please contact the Customer Service Centre (see
below) for further information.
• Customer Service Centre
If you have any questions regarding this publication or need further assistance,
please contact the Customer Service Centre:

Email: custserv@iec.ch
Tel: +41 22 919 02 11
Fax: +41 22 919 03 00
INTERNATIONAL IEC
STANDARD 62382
First edition
2006-11
Electrical and instrumentation loop check
© IEC 2006 ⎯ Copyright - all rights reserved
No part of this publication may be reproduced or utilized in any form or by any means, electronic or
mechanical, including photocopying and microfilm, without permission in writing from the publisher.
International Electrotechnical Commission, 3, rue de Varembé, PO Box 131, CH-1211 Geneva 20, Switzerland
Telephone: +41 22 919 02 11 Telefax: +41 22 919 03 00 E-mail: inmail@iec.ch Web: www.iec.ch
PRICE CODE
Commission Electrotechnique Internationale R
International Electrotechnical Commission
МеждународнаяЭлектротехническаяКомиссия
For price, see current catalogue

– 2 – 62382 © IEC:2006(E)
CONTENTS
FOREWORD.3
INTRODUCTION.5

1 Scope.6
2 Terms and definitions.6
3 Abbreviations .7
4 The order of loop check and cold commissioning in the project schedule.7
5 Loop-check content .8
5.1 Included activities.8
5.2 Excluded activities.10
6 Loop check procedure .10
6.1 Documentation check .10
6.2 Visual inspection .10
6.3 Function check .11
6.4 Checkout of E&I infrastructure and E&I concepts.11
6.5 Additional tests – Quality and safety relevant loops.12
7 Documents and test sheets .12
7.1 Input documents.12
7.2 Test sheets .12
7.3 Documents generated upon completion of loop check .13
7.4 Loop-check results .13
8 Quality assurance.13
9 Safety aspects.13

Annexe A (informative) Test report for analogue input loop.14
Annexe B (informative) Test report for binary input loop.15
Annexe C (informative) Test report for analogue output loop.16
Annexe D (informative) Test report for binary output loop .17
Annexe E (informative) Test report for motors and variable frequency drives .18

62382 © IEC:2006(E) – 3 –
INTERNATIONAL ELECTROTECHNICAL COMMISSION
____________
ELECTRICAL AND INSTRUMENTATION LOOP CHECK

FOREWORD
1) The International Electrotechnical Commission (IEC) is a worldwide organization for standardization comprising
all national electrotechnical committees (IEC National Committees). The object of IEC is to promote
international co-operation on all questions concerning standardization in the electrical and electronic fields. To
this end and in addition to other activities, IEC publishes International Standards, Technical Specifications,
Technical Reports, Publicly Available Specifications (PAS) and Guides (hereafter referred to as “IEC
Publication(s)”). Their preparation is entrusted to technical committees; any IEC National Committee interested
in the subject dealt with may participate in this preparatory work. International, governmental and non-
governmental organizations liaising with the IEC also participate in this preparation. IEC collaborates closely
with the International Organization for Standardization (ISO) in accordance with conditions determined by
agreement between the two organizations.
2) The formal decisions or agreements of IEC on technical matters express, as nearly as possible, an international
consensus of opinion on the relevant subjects since each technical committee has representation from all
interested IEC National Committees.
3) IEC Publications have the form of recommendations for international use and are accepted by IEC National
Committees in that sense. While all reasonable efforts are made to ensure that the technical content of IEC
Publications is accurate, IEC cannot be held responsible for the way in which they are used or for any
misinterpretation by any end user.
4) In order to promote international uniformity, IEC National Committees undertake to apply IEC Publications
transparently to the maximum extent possible in their national and regional publications. Any divergence
between any IEC Publication and the corresponding national or regional publication shall be clearly indicated in
the latter.
5) IEC provides no marking procedure to indicate its approval and cannot be rendered responsible for any
equipment declared to be in conformity with an IEC Publication.
6) All users should ensure that they have the latest edition of this publication.
7) No liability shall attach to IEC or its directors, employees, servants or agents including individual experts and
members of its technical committees and IEC National Committees for any personal injury, property damage or
other damage of any nature whatsoever, whether direct or indirect, or for costs (including legal fees) and
expenses arising out of the publication, use of, or reliance upon, this IEC Publication or any other IEC
Publications.
8) Attention is drawn to the Normative references cited in this publication. Use of the referenced publications is
indispensable for the correct application of this publication.
9) Attention is drawn to the possibility that some of the elements of this IEC Publication may be the subject of
patent rights. IEC shall not be held responsible for identifying any or all such patent rights.
International Standard IEC 62382 has been prepared by IEC technical committee 65:
Industrial-process measurement and control.
This standard cancels and replaces IEC/PAS 62382 published in 2004. This first edition
constitutes a technical revision.
The text of this standard is based on the following documents:
FDIS Report on voting
65/386/FDIS 65/395/RVD
Full information on the voting for the approval of this standard can be found in the report on
voting indicated in the above table.
This publication has been drafted in accordance with the ISO/IEC Directives, Part 2.

– 4 – 62382 © IEC:2006(E)
The committee has decided that the contents of this publication will remain unchanged until
the maintenance result date indicated on the IEC web site under "http://webstore.iec.ch" in
the data related to the specific publication. At this date, the publication will be
• reconfirmed,
• withdrawn,
• replaced by a revised edition, or
• amended.
A bilingual version of this publication may be issued at a later date.

62382 © IEC:2006(E) – 5 –
INTRODUCTION
The inspection and verification of the individual measurements and controls in conjunction
with the control systems used to monitor these devices (DCS, PLC, etc.) is referred to as loop
check. In industry, numerous methods and philosophies are used to check the instrumentation
and controls after mechanical installation within projects for modified or new facilities.
This standard was created to provide a better understanding of what loop check consists of
and also to provide a standard methodology for executing loop check.
The annexes of this standard contain forms which may be used in the check procedures.
Buyers of this publication may copy these forms for their own purposes only in the required
amount.
For application in the pharmaceutical or other highly specialized industries, additional
guidelines (for example, Good Automated Manufacturing Practice (GAMP)), definitions and
stipulations should apply in accordance with existing standards, for example, for GMP
Compliance 21 CFR (FDA) and the Standard Operating Procedure of the European Medicines
Agency (SOP/INSP/2003).
– 6 – 62382 © IEC:2006(E)
ELECTRICAL AND INSTRUMENTATION LOOP CHECK

1 Scope
This International Standard describes the steps recommended to complete a loop check,
which comprises the activities between the completion of the loop construction (including
installation and point-to-point checks) and the start-up of cold commissioning. This standard
is applicable for the construction of new plants and for expansion/retrofits (i.e. revamping) of
E&I installations in existing plants (including PLC, BAS, DCS, panel-mounted and field
instrumentation). It does not include a detailed checkout of power distribution systems, except
as they relate to the loops being checked (i.e. a motor starter or a power supply to a four-wire
transmitter).
2 Terms and definitions
For the purposes of this document, the following terms and definitions apply.
2.1
precommissioning
phase, during which the activities of non-operating adjustments, cold alignment checks,
cleaning, and testing of machinery take place.
NOTE Please refer to the enclosed annexes as an example.
2.2
mechanical completion
milestone, which is achieved when the plant, or any part thereof, has been erected and
tested in accordance with drawings, specifications, instructions, and applicable codes and
regulations to the extent necessary to permit cold commissioning
NOTE This includes completion of all necessary electrical and instrumentation work. This is a milestone marking
the end of the precommissioning activities.
2.3
cold commissioning
phase, during which the activities associated with the testing and operation of equipment or
facilities using test media such as water or inert substances prior to introducing any chemical
in the system take place
2.4
start-up
milestone marking the end of cold commissioning.
NOTE At this stage, the operating range of every instrument loop is already adjusted to reflect the actual working
condition.
2.5
hot commissioning
phase, during which the activities associated with the testing and operation of equipment or
facilities using the actual chemical process prior to making an actual production run take
place
2.6
start of production
milestone marking the end of hot commissioning.
NOTE At this stage, the plant is ready for full and continuous operation.

62382 © IEC:2006(E) – 7 –
2.7
performance test
milestone at which time the production plant runs to its design capacity
NOTE This test, carried out by the owner’s personnel with the help and supervision of the contractor, should
demonstrate the contractor’s process performance and consumption guarantees as specified in the contract.
2.8
acceptance of plant
milestone at which the formal turn over of the plant from the contractor to the owner is carried
out
2.9
basic software
software which, at a minimum, contains the graphic faceplates, base-level alarms and switch
points, basic interlocking and analogue control. In the case of safety loops, any safety switch
point should be included i
...

Questions, Comments and Discussion

Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.