Standard Classification for Cost Estimate Classification System

SIGNIFICANCE AND USE
4.1 Use of this classification will improve communication among all the stakeholders involved with preparing, evaluating, and using cost estimates.  
4.2 The various parties that use cost estimates often misinterpret the quality and value of the information available to prepare cost estimates, the various methods employed during the estimating process, the accuracy level expected from estimates, and the level of risk associated with estimates.  
4.3 This classification applies the degree of project definition as the primary characteristic for determining an estimate’s classification.  
4.4 Using this classification will help those involved with project estimates to avoid misinterpretation of the various classes of cost estimates and to avoid their misapplication and misrepresentation. Improving communications about estimate classifications reduces business costs and project cycle times by avoiding inappropriate business and financial decisions, actions, delays, or disputes caused by misunderstandings of cost estimates and what they are expected to represent.  
4.5 This classification is intended to be generic and so provide a system for the classification of cost estimates in any industry. There are also references to specific industries, for cost estimate classification as applied in: AACE International, Process Industry 18R-97, and AACE International, Building/General Construction Industry 56R-08.  
4.6 Estimate classifications provide valuable additional reporting information when used as an adjunct to Practice E1804.
SCOPE
1.1 This classification provides a generic classification system for cost estimates and provides guidelines for applying the classification to cost estimates.  
1.2 This classification maps the phases and stages of cost estimating to a generic maturity and quality matrix, keyed to a degree of project definition, that can be applied across a wide variety of industries.  
1.3 The Cost Estimate Classification System has been developed in a way that:  
1.3.1 provides a common understanding of the concepts involved with classifying cost estimates;  
1.3.2 defines and correlates the major characteristics used in classifying cost estimates, and;  
1.3.3 uses the degree of project definition as the primary characteristic used to categorize estimate classes.  
1.4 This international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for the Development of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.

General Information

Status
Published
Publication Date
30-Sep-2019
Technical Committee
E06 - Performance of Buildings
Drafting Committee
E06.81 - Building Economics

Relations

Effective Date
01-Oct-2019
Effective Date
01-Mar-2015
Effective Date
01-Nov-2014
Effective Date
01-Nov-2013
Effective Date
15-Oct-2013
Effective Date
01-Oct-2013
Effective Date
01-May-2012
Effective Date
01-Apr-2012
Effective Date
01-Nov-2009
Effective Date
01-May-2009
Effective Date
01-Nov-2008
Effective Date
01-Apr-2007
Effective Date
15-Sep-2006
Effective Date
01-Jun-2006
Effective Date
01-Oct-2004

Overview

ASTM E2516-11(2019): Standard Classification for Cost Estimate Classification System is a globally recognized ASTM standard that establishes a generic framework for classifying cost estimates. Developed according to internationally approved standardization principles, this classification system is intended for use across all industries, enhancing consistency and mutual understanding among stakeholders involved in preparing, evaluating, and utilizing cost estimates. The standard aims to improve communication, reduce misinterpretation, and minimize risks associated with misapplied or misunderstood cost estimate information during a project’s lifecycle.

Key Topics

  • Degree of Project Definition: The primary basis for cost estimate classification, reflecting the level of completeness and maturity of project documentation.
  • Cost Estimate Classes: Five distinct estimate classes (Class 1 to Class 5) are outlined, each linked to the degree of project definition, ranging from minimal (Class 5) to full definition (Class 1).
  • Secondary Characteristics: These include end usage, estimating methodology, expected accuracy range, and level of effort required to prepare the estimate.
  • Classification Matrix: The standard provides a generic matrix mapping estimate classes against primary and secondary characteristics, supporting consistent application in any industry.
  • Improved Communication & Decision Making: By clarifying estimate types and their appropriate uses, stakeholders avoid inappropriate financial decisions, delays, or disputes stemming from misinterpreted cost data.
  • Industry Applicability: While designed as a generic system, the standard references industry-specific applications in the process and construction sectors and can be adapted to sector-specific needs.

Applications

The ASTM E2516 Cost Estimate Classification System has broad practical value in project management, budgeting, and risk assessment. Typical applications include:

  • Project Planning and Funding: Supports clear delineation between estimate types used in feasibility studies, budget authorizations, and control or bidding processes.
  • Risk Management: Enables identification of accuracy ranges and risk levels according to the maturity of project information, ensuring more reliable project cost forecasts.
  • Stakeholder Alignment: Enhances communication among owners, contractors, cost estimators, and auditors by standardizing estimate terminology and expectations.
  • Cost Control and Monitoring: Assists in tracking progress and financial performance throughout the project lifecycle by correlating estimate class with project milestones.
  • Cross-industry Adaptation: Applicable in sectors such as building construction, process industries, and other fields requiring rigorous cost estimation frameworks.
  • Adjunct Use with Other Standards: Provides valuable supplementary information when used alongside standards such as ASTM E1804 (Performing and Reporting Cost Analysis during Design Phase).

Related Standards

  • ASTM E1804: Practice for Performing and Reporting Cost Analysis During the Design Phase of a Project.
  • ASTM E833 / E631: Terminology related to building economics and construction.
  • AACE International Recommended Practices: Includes 17R-97 (Cost Estimate Classification), 18R-97 (Process Industry), and 56R-08 (Building and General Construction).
  • ANSI Z94.2-1989: Industrial Engineering Terminology related to cost engineering.

Practical Value

By providing a common language and framework for cost estimate classification, ASTM E2516-11(2019) reduces ambiguity, supports informed decision-making, and streamlines project cost management across diverse sectors. Its adoption helps ensure project cost estimates are appropriately classified, understood, and applied, ultimately reducing project cycle times and minimizing business risks.

Keywords: ASTM E2516, cost estimate classification, estimate class, project definition, cost estimating methodology, project cost management, risk assessment, industry standards, budget authorization, bid/tender estimate, project planning, accuracy range, estimating effort.

Buy Documents

Standard

ASTM E2516-11(2019) - Standard Classification for Cost Estimate Classification System

English language (7 pages)
sale 15% off
sale 15% off

Get Certified

Connect with accredited certification bodies for this standard

BSI Group

BSI (British Standards Institution) is the business standards company that helps organizations make excellence a habit.

UKAS United Kingdom Verified

Bureau Veritas

Bureau Veritas is a world leader in laboratory testing, inspection and certification services.

COFRAC France Verified

DNV

DNV is an independent assurance and risk management provider.

NA Norway Verified

Sponsored listings

Frequently Asked Questions

ASTM E2516-11(2019) is a standard published by ASTM International. Its full title is "Standard Classification for Cost Estimate Classification System". This standard covers: SIGNIFICANCE AND USE 4.1 Use of this classification will improve communication among all the stakeholders involved with preparing, evaluating, and using cost estimates. 4.2 The various parties that use cost estimates often misinterpret the quality and value of the information available to prepare cost estimates, the various methods employed during the estimating process, the accuracy level expected from estimates, and the level of risk associated with estimates. 4.3 This classification applies the degree of project definition as the primary characteristic for determining an estimate’s classification. 4.4 Using this classification will help those involved with project estimates to avoid misinterpretation of the various classes of cost estimates and to avoid their misapplication and misrepresentation. Improving communications about estimate classifications reduces business costs and project cycle times by avoiding inappropriate business and financial decisions, actions, delays, or disputes caused by misunderstandings of cost estimates and what they are expected to represent. 4.5 This classification is intended to be generic and so provide a system for the classification of cost estimates in any industry. There are also references to specific industries, for cost estimate classification as applied in: AACE International, Process Industry 18R-97, and AACE International, Building/General Construction Industry 56R-08. 4.6 Estimate classifications provide valuable additional reporting information when used as an adjunct to Practice E1804. SCOPE 1.1 This classification provides a generic classification system for cost estimates and provides guidelines for applying the classification to cost estimates. 1.2 This classification maps the phases and stages of cost estimating to a generic maturity and quality matrix, keyed to a degree of project definition, that can be applied across a wide variety of industries. 1.3 The Cost Estimate Classification System has been developed in a way that: 1.3.1 provides a common understanding of the concepts involved with classifying cost estimates; 1.3.2 defines and correlates the major characteristics used in classifying cost estimates, and; 1.3.3 uses the degree of project definition as the primary characteristic used to categorize estimate classes. 1.4 This international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for the Development of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.

SIGNIFICANCE AND USE 4.1 Use of this classification will improve communication among all the stakeholders involved with preparing, evaluating, and using cost estimates. 4.2 The various parties that use cost estimates often misinterpret the quality and value of the information available to prepare cost estimates, the various methods employed during the estimating process, the accuracy level expected from estimates, and the level of risk associated with estimates. 4.3 This classification applies the degree of project definition as the primary characteristic for determining an estimate’s classification. 4.4 Using this classification will help those involved with project estimates to avoid misinterpretation of the various classes of cost estimates and to avoid their misapplication and misrepresentation. Improving communications about estimate classifications reduces business costs and project cycle times by avoiding inappropriate business and financial decisions, actions, delays, or disputes caused by misunderstandings of cost estimates and what they are expected to represent. 4.5 This classification is intended to be generic and so provide a system for the classification of cost estimates in any industry. There are also references to specific industries, for cost estimate classification as applied in: AACE International, Process Industry 18R-97, and AACE International, Building/General Construction Industry 56R-08. 4.6 Estimate classifications provide valuable additional reporting information when used as an adjunct to Practice E1804. SCOPE 1.1 This classification provides a generic classification system for cost estimates and provides guidelines for applying the classification to cost estimates. 1.2 This classification maps the phases and stages of cost estimating to a generic maturity and quality matrix, keyed to a degree of project definition, that can be applied across a wide variety of industries. 1.3 The Cost Estimate Classification System has been developed in a way that: 1.3.1 provides a common understanding of the concepts involved with classifying cost estimates; 1.3.2 defines and correlates the major characteristics used in classifying cost estimates, and; 1.3.3 uses the degree of project definition as the primary characteristic used to categorize estimate classes. 1.4 This international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for the Development of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.

ASTM E2516-11(2019) is classified under the following ICS (International Classification for Standards) categories: 03.100.60 - Accountancy. The ICS classification helps identify the subject area and facilitates finding related standards.

ASTM E2516-11(2019) has the following relationships with other standards: It is inter standard links to ASTM E2516-11, ASTM E631-15, ASTM E631-14, ASTM E833-13b, ASTM E833-13a, ASTM E833-13, ASTM E833-12, ASTM E1804-12, ASTM E833-09a, ASTM E833-09, ASTM E833-08, ASTM E1804-07, ASTM E833-06, ASTM E631-06, ASTM E833-04. Understanding these relationships helps ensure you are using the most current and applicable version of the standard.

ASTM E2516-11(2019) is available in PDF format for immediate download after purchase. The document can be added to your cart and obtained through the secure checkout process. Digital delivery ensures instant access to the complete standard document.

Standards Content (Sample)


This international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for the
Development of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.
Designation: E2516 −11 (Reapproved 2019)
Standard Classification for
1,2
Cost Estimate Classification System
This standard is issued under the fixed designation E2516; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (´) indicates an editorial change since the last revision or reapproval.
1. Scope 2.2 Other Standards:
ANSI Z94.2-1989 Industrial EngineeringTerminology: Cost
1.1 This classification provides a generic classification sys-
Engineering
tem for cost estimates and provides guidelines for applying the
AACE International Recommended Practice No 17R-97:
classification to cost estimates.
Cost Estimate Classification System
AACE International Recommended Practice No 18R-97:
1.2 This classification maps the phases and stages of cost
Cost Estimate Classification System: As Applied in
estimating to a generic maturity and quality matrix, keyed to a
Engineering, Procurement, and Construction for the Pro-
degree of project definition, that can be applied across a wide
cess Industries
variety of industries.
AACE International Recommended Practice No 56R-08:
1.3 The Cost Estimate Classification System has been
Cost Estimate Classification System – As Applied in
developed in a way that: 5
Building and General Construction Industries
1.3.1 provides a common understanding of the concepts
involved with classifying cost estimates; 3. Terminology
1.3.2 defines and correlates the major characteristics used in
3.1 Definitions—For definitions of terms used in this
classifying cost estimates, and;
practice, refer to Terminology E833 and Terminology E631.
1.3.3 uses the degree of project definition as the primary
4. Significance and Use
characteristic used to categorize estimate classes.
4.1 Use of this classification will improve communication
1.4 This international standard was developed in accor-
among all the stakeholders involved with preparing,
dance with internationally recognized principles on standard-
evaluating, and using cost estimates.
ization established in the Decision on Principles for the
Development of International Standards, Guides and Recom- 4.2 The various parties that use cost estimates often misin-
mendations issued by the World Trade Organization Technical terpret the quality and value of the information available to
Barriers to Trade (TBT) Committee. prepare cost estimates, the various methods employed during
the estimating process, the accuracy level expected from
estimates, and the level of risk associated with estimates.
2. Referenced Documents
4.3 This classification applies the degree of project defini-
2.1 ASTM Standards:
tion as the primary characteristic for determining an estimate’s
E631 Terminology of Building Constructions
classification.
E833 Terminology of Building Economics
E1804 Practice for Performing and Reporting CostAnalysis
4.4 Using this classification will help those involved with
During the Design Phase of a Project project estimates to avoid misinterpretation of the various
classes of cost estimates and to avoid their misapplication and
misrepresentation. Improving communications about estimate
classifications reduces business costs and project cycle times
This specification is under the jurisdiction of ASTM Committee E06 on
by avoiding inappropriate business and financial decisions,
Performance of Buildings and is the direct responsibility of Subcommittee E06.81
on Building Economics.
actions, delays, or disputes caused by misunderstandings of
Current edition approved Oct. 1, 2019. Published October 2019. Originally
cost estimates and what they are expected to represent.
approved in 2006. Last previous edition approved in 2011 as E2516–11. DOI:
10.1520/E2516–11R19.
This classification is based on theAACE International Recommended Practices
17R–97, 18R-97, and 56R-09 pertaining to Cost Estimate Classification System. Available fromAmerican National Standards Institute (ANSI), 25 W. 43rd St.,
For referenced ASTM standards, visit the ASTM website, www.astm.org, or 4th Floor, New York, NY 10036, http://www.ansi.org.
contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM Available from the Association for the Advancement of Cost Engineering
Standards volume information, refer to the standard’s Document Summary page on (AACE International), 1265 Suncrest Towne Centre Dr., Morgantown, WV 26505-
the ASTM website. 1876, http://www.aacei.org.
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
E2516 − 11 (2019)
4.5 This classification is intended to be generic and so understand that it is only the degree of project definition that
provide a system for the classification of cost estimates in any determinestheestimateclass.Theotherfourcharacteristicsare
industry. There are also references to specific industries, for secondary characteristics that are generally correlated with the
cost estimate classification as applied in: AACE International, degree of project definition.
Process Industry 18R-97, and AACE International, Building/
5.6 This generic matrix and guideline provides a high-level
General Construction Industry 56R-08.
estimate classification system that is non-industry specific.The
4.6 Estimate classifications provide valuable additional re- accuracy ranges identified in Table 1 are indicated as index
portinginformationwhenusedasanadjuncttoPracticeE1804. valuessothattheymaybeappliedgenericallytojustaboutany
particular industry.Amore detailed explanation of these index
5. Basis of Classification
values, including two examples of their possible ranges, can be
found in Appendix X1.
5.1 There are numerous characteristics that can be used to
categorizecostestimatetypes.Themostsignificantoftheseare
6. Determination of the Cost Estimate Class
degree of project definition, end usage of the estimate, estimat-
ing methodology, and the effort and time needed to prepare the 6.1 The cost estimator makes the determination of the
estimate class based upon the degree of project definition
estimate. The primary characteristic used in this guideline to
define the classification category is the degree of project (design % complete). While the determination of the estimate
class is somewhat subjective, the design input data, complete-
definition. The other characteristics are secondary.
ness and quality of the design deliverables serve to make the
5.2 The discrete degrees of project definition used for
determination more objective.
classifyingestimatescorrespondtothetypicalphasesandgates
of evaluation, authorization, and execution often used by
7. Estimate Characteristics
project stakeholders during a project life cycle.
7.1 The following are brief discussions of the various
5.3 Five cost estimate classes have been established. While
estimate characteristics used in the estimate classification
the degree of project definition is a continuous spectrum, it has
matrix, Table 1. For the secondary characteristics, the overall
been determined from benchmarking industry practices that
trend of how each characteristic varies with the degree of
three to five discrete categories are commonly used. Five
project definition (the primary characteristic) is provided.
categories are established in this standard classification as it is
7.2 Degree of Project Definition (Primary Characteristic):
easier to simplify by combining categories than it is to
7.2.1 This characteristic is based upon the level of comple-
arbitrarily split a standard.
tion of project definition (roughly corresponding to the per-
5.4 In Table 1 these estimate class designations are labeled
centage completion of architectural/engineering detail and
Class 1, 2, 3, 4, and 5. A Class 5 estimate is based upon the
design). The degree of project definition defines maturity, or
lowest degree of project definition, and a Class 1 estimate is
the extent and types, of input information available to the
closest to full project definition and maturity. This countdown
estimating process. Such inputs include project scope
approach considers that estimating is an iterative process
definition, requirements documents, specifications, project
whereby successive estimates are prepared until a final esti-
plans, drawings, calculations, knowledge and experience
mate closes the process.
gained from past projects, reconnaissance data, and other
5.5 The five estimate classes are presented in Table 1 in information that must be used, and developed, to define the
relationship to the identified characteristics. It is important to project. Each industry will have a typical set of deliverables
TABLE 1 Generic Cost Estimate Classification Matrix
Primary Characteristic Secondary Characteristic
DEGREE OF EXPECTED
ESTIMATED PREPARATION
PROJECTION END USAGE METHODOLOGY ACCURACY
CLASS EFFORT
DEFINITION RANGE
Typical ± range
Typical degree of effort
Expressed as % of Typical purpose relative to index of 1
Typical estimating method relative to least cost
complete definition of estimate (that is, Class 1
B
index of 1
A
estimate)
Class 5 0 % to 2 % Screening or feasibility Stochastic (factors or models, or both) 4to20 1
or judgment
Class 4 1 % to 15 % Concept study or feasibility Primarily stochastic 3 to 12 2 to 4
Class 3 10 % to 40 % Budget authorization Mixed but primarily stochastic 2 to 6 3 to 10
or control
Class 2 30 % to 70 % Control or bid/tender Primarily deterministic 1 to 3 5 to 20
Class 1 70 % to 100 % Check estimate or bid/tender Deterministic 1 10 to 100
A
If the expected accuracy range index value of “1” represents +10/–5 %, then an index value of “10” represents +100/–50 %.
B
If the preparation effort index value of “1” represents 0.005 % of project costs, then an index value of “100” represents 0.5 %.
E2516 − 11 (2019)
that are used to support the type of estimates used in that 7.6.1 The level of effort needed to prepare a given estimate
industry. The set of deliverables becomes more definitive and is an indication of the cost, time, and resources required. The
complete as the degree of project definition (such as architec-
cost measure of that effort is typically expressed as a percent-
ture and engineering) progresses. age of the total project costs for a given project size. As the
degree of project definition increases, the amount of effort to
7.3 End Usage (Secondary Characteristic):
prepare an estimate increases, as does its cost relative to the
7.3.1 The various classes (or phases) of cost estimates
total project cost.The effort to develop the project deliverables
prepared for a project typically have different end uses or
is not included in these effort metrics; they only cover the cost
purposes.As the degree of project definition increases, the end
to prepare the cost estimate itself.
usage of an estimate typically progresses from strategic evalu-
ation and feasibility studies to funding authorization and
8. Relationships and Variations of Estimate
budgeting, to project control.
Characteristics: Discussion
7.4 Estimating Methodology (Secondary Characteristic):
8.1 Thereareamyriadofcomplexrelationshipsthatmaybe
7.4.1 Estimating methodologies fall into two broad catego-
exhibited among the estimate characteristics within the esti-
ries: stochastic and deterministic. In stochastic methods, the
mate classifications. The overall trend of how the secondary
independent variable(s) used in the cost estimating algorithms
characteristics vary with the degree of project definition was
aregenerallysomethingotherthanadirectmeasureoftheunits
provided above. This section explores those trends in more
of the item being estimated. The cost estimating relationships
detail. Typically, there are commonalties in the secondary
used in stochastic methods are often based on factors, metrics,
models, etc. With deterministic methods, the independent characteristics between one estimate and the next, but in any
given situation there may be wide variations in usage,
variable(s) are more or less a definitive measure of the item
being estimated (can include, detailed takeoff, quotes, bids, methodology, accuracy, and effort.
etc.).Adeterministic methodology reduces the level of conjec-
8.1.1 Thelevelofprojectdefinitionisthedriveroftheother
ture inherent in an estimate.As the degree of project definition
characteristics. Typically, all of the secondary characteristics
increases, the estimating methodology tends to progress from
have the level of project definition as a primary determinant.
stochastic to deterministic methods.
While the other characteristics are important to categorization,
they lack complete consensus. For example, one estimator’s
7.5 Expected Accuracy Range (Secondary Characteristic):
bid might be another’s budget. Characteristics such as meth-
7.5.1 Estimate accuracy range is an indication of the degree
odology and accuracy can vary markedly from one industry to
to which the final cost outcome for a given project could vary
another and even from estimator to estimator within a given
from the estimated cost.Accuracy is traditionally expressed as
industry.
a 6 percentage range around the point estimate, after applica-
tion of contingency, with a stated level of confidence that the
8.2 Degree of Project Definition:
actual cost outcome would fall within this range (6 measures
8.2.1 Each project (or industry grouping) will have a typical
are a useful simplification, given that actual cost outcomes
set of deliverables that are used to support a given class of
have different frequency distributions for di
...

Questions, Comments and Discussion