Pump system energy assessment

This document sets the requirements for conducting and reporting the results of a pumping system energy assessment (hereafter referenced as "assessment") that considers the entire pumping system, from energy inputs to the work performed as the result of these inputs. The objective of a pumping system energy assessment is to determine the current energy consumption of an existing system and identify ways to improve system efficiency. These requirements consist of — organizing and conducting an assessment, — analysing the data from the assessment, and — reporting and documenting assessment findings. This document is designed to be applied, to open and closed loop pumping systems typically used at industrial, institutional, commercial, and municipal facilities, when requested. This document is focused on assessing electrically-driven pumping systems, which are dominant in most facilities, but is also applicable with other types of drivers, such as steam turbines and engines. The document does not a) specify how to design a pumping system, b) give detailed qualifications and expertise required of the person using the International Standard although provides a list of body of knowledge in Annex C, c) address the training or certification of persons, d) specify how to implement the recommendations developed during the assessment, but does include requirements for an action plan, e) specify how to measure and validate the energy savings that result from implementing assessment recommendations, f) specify how to make measurements and how to calibrate test equipment used during the assessment, g) specify how to estimate the implementation cost or conduct financial analysis for recommendations developed during the assessment, h) specify specific steps required for safe operation of equipment during the assessment. The facility personnel in charge of normal operation of the equipment are responsible for ensuring that it is operated safely during the data collection phase of the assessment, i) address issues of intellectual property, security, confidentiality, and safety.

Évaluation énergétique des systèmes de pompage

Le présent document pose les exigences de réalisation et de compte-rendu d'une évaluation énergétique de systčme de pompage (désignée par la suite «évaluation») qui prend en compte l'ensemble de l'installation de pompage, depuis les points d'introduction de l'énergie dans l'installation jusqu'au travail fourni par l'installation ŕ l'aide de cette énergie. L'objectif d'une évaluation énergétique d'un systčme de pompage est de déterminer la consommation d'énergie actuelle d'un systčme existant et d'identifier les maničres d'augmenter l'efficacité du systčme. Ces exigences concernent — l'organisation et le pilotage d'une évaluation, — l'analyse des données de l'évaluation, — la rédaction du compte-rendu de fin d'évaluation et étayer les conclusions de l'évaluation.. Le présent document est conçu pour ętre appliqué, selon la demande, aux systčmes de pompage en boucle ouverte et en boucle fermée, utilisés dans des installations industrielles, institutionnelles, commerciales et municipales. Le présent document met la priorité sur l'évaluation des systčmes de pompage entraînés par des moteurs électriques, qui sont majoritaires dans les installations. Elle est toutefois applicable ŕ d'autres types d'entraînements, par exemple turbines ŕ vapeur et moteurs thermiques. Le présent document a) ne spécifie pas la maničre de concevoir un systčme de pompage, b) ne fournit pas de détails sur les qualifications et l'expertise exigées de la personne utilisant la présente Norme internationale, bien qu'elle fournisse une liste d'un ensemble de connaissances en Annexe C, c) ne traite pas de la formation et de la certification des personnes, d) ne spécifie pas la maničre de mettre en place les recommandations élaborées au cours de l'évaluation, elle inclut néanmoins des exigences relatives ŕ un plan d'action, e) ne spécifie pas la maničre de mesurer de valider les économies d'énergie résultant de la mise en œuvre des recommandations de l'évaluation, f) ne spécifie pas la maničre d'effectuer des campagnes de mesurages et la maničre d'étalonner les équipements d'essai utilisés lors de l'évaluation, g) ne spécifie pas la maničre d'estimer les coűts de mise en œuvre et de conduire l'analyse financičre concernant les recommandations élaborées au cours de l'évaluation, h) ne spécifie pas les étapes spécifiques exigées pour un fonctionnement sűr des équipements au cours de l'évaluation. Le personnel du site en charge du fonctionnement courant des équipements est chargé de veiller ŕ ce qu'ils fonctionnent en toute sécurité durant la phase de collecte de données de l'évaluation, i) ne traite pas des questions de propriété intellectuelle, de sűreté, de confidentialité et de sécurité.

General Information

Status
Published
Publication Date
29-Jan-2019
Technical Committee
Drafting Committee
Current Stage
6060 - International Standard published
Start Date
27-Nov-2018
Completion Date
30-Jan-2019
Ref Project

RELATIONS

Buy Standard

Standard
ISO/ASME 14414:2019 - Pump system energy assessment
English language
56 pages
sale 15% off
Preview
sale 15% off
Preview
Standard
ISO/ASME 14414:2019 - Évaluation énergétique des systemes de pompage
French language
58 pages
sale 15% off
Preview
sale 15% off
Preview

Standards Content (sample)

INTERNATIONAL ISO/ASME
STANDARD 14414
Second edition
2019-01
Pump system energy assessment
Évaluation énergétique des systèmes de pompage
Reference number
ISO/ASME 14414:2019(E)
ISO/ASME 2019
---------------------- Page: 1 ----------------------
ISO/ASME 14414:2019(E)
COPYRIGHT PROTECTED DOCUMENT
© ISO/ASME 2019

All rights reserved. Unless otherwise specified, or required in the context of its implementation, no part of this publication may

be reproduced or utilized otherwise in any form or by any means, electronic or mechanical, including photocopying, or posting

on the internet or an intranet, without prior written permission. Permission can be requested from either ISO at the address

below or ISO’s member body in the country of the requester.
ISO copyright office ASME
CP 401 • Ch. de Blandonnet 8 Two Park Avenue • New York, NY 10016-5990 • USA
CH-1214 Vernier, Geneva
Phone: +41 22 749 01 11 Phone: 800-843-2763
Fax: +41 22 749 09 47 Fax: 973-882-1717
Email: copyright@iso.org Email: CustomerCare@asme.org
Website: www.iso.org Website: www.asme.org
Published in Switzerland
ii © ISO/ASME 2019 – All rights reserved
---------------------- Page: 2 ----------------------
ISO/ASME 14414:2019(E)
Contents Page

Foreword ..........................................................................................................................................................................................................................................v

Introduction ..............................................................................................................................................................................................................................vii

1 Scope ................................................................................................................................................................................................................................. 1

2 Normative references ...................................................................................................................................................................................... 1

3 Terms and definitions ..................................................................................................................................................................................... 2

4 Identification of the assessment team, authority and functions ........................................................................2

4.1 Identification of assessment team functions ................................................................................................................ 2

4.2 Assessment team structure, leadership and competency ................................................................................. 3

4.3 Facility management support .................................................................................................................................................... 3

4.4 Communications .................................................................................................................................................................................... 3

4.5 Access to facilities, personnel and information .......................................................................................................... 4

4.6 Assessment objectives, scope and boundaries ............................................................................................................ 4

4.7 Action plan .................................................................................................................................................................................................. 4

4.7.1 General...................................................................................................................................................................................... 4

4.7.2 Assessment scheduling .............................................................................................................................................. 5

4.8 Initial data collection and evaluation .................................................................................................................................. 5

4.8.1 General...................................................................................................................................................................................... 5

4.8.2 Initial facility specialist interviews .................................................................................................................. 5

4.8.3 Energy project history ................................................................................................................................................ 6

4.8.4 Energy cost ........................................................................................................................................................................... 6

4.8.5 Initial system data .......................................................................................................................................................... 6

4.9 Objective check ....................................................................................................................................................................................... 6

5 Conducting the assessment ....................................................................................................................................................................... 6

5.1 Assessment levels ................................................................................................................................................................................. 6

5.1.1 General...................................................................................................................................................................................... 6

5.1.2 Level 1 assessments ...................................................................................................................................................... 7

5.1.3 Level 2 assessments ...................................................................................................................................................... 8

5.1.4 Level 3 assessments ...................................................................................................................................................... 8

5.2 Walk through ............................................................................................................................................................................................ 9

5.3 Understanding system functional requirements ....................................................................................................10

5.4 Determining system boundaries and system energy demand ...................................................................10

5.5 Information needed to assess the efficiency of a pumping system ........................................................10

5.5.1 General...................................................................................................................................................................................10

5.5.2 Electrical motor/drive information ..............................................................................................................10

5.5.3 Pump information .................. .................................................... ..................................................................................11

5.5.4 Liquid properties information ..........................................................................................................................12

5.5.5 Detailed system data .................................................................................................................................................12

5.5.6 Measured data .................................................................................................................................................................13

5.6 Data collection ......................................................................................................................................................................................14

5.6.1 System information ....................................................................................................................................................14

5.6.2 Measurement of pump and motor operating data ..........................................................................14

5.6.3 Pressure ................................................................................................................................................................................14

5.6.4 Flow ........................................................................................................................................... ...............................................14

5.6.5 Input power .......................................................................................................................................................................15

5.7 Cross validation ...................................................................................................................................................................................15

5.8 Wrap-up meeting and presentation of initial findings and recommendations ............................15

6 Reporting and documentation ............................................................................................................................................................16

6.1 Final assessment report ...............................................................................................................................................................16

6.2 Data for third party review........................................................................................................................................................16

6.3 Review of final report by assessment team members .......................................................................................16

Annex A (normative) Report contents .............................................................................................................................................................17

© ISO/ASME 2019 – All rights reserved iii
---------------------- Page: 3 ----------------------
ISO/ASME 14414:2019(E)
Annex B (informative) Recommendations on efficient system operation and energy

reduction — Examples ................................................................................................................................................................................21

Annex C (informative) Expertise, experience and competencies ........................................................................................39

Annex D (informative) Recommended guidelines for analysis software ....................................................................42

Annex E (informative) Example of pre-screening worksheet ..................................................................................................44

Annex F (informative) Specific energy consumption .......................................................................................................................46

Annex G (informative) Pumping system parasitic power ............................................................................................................50

Annex H (informative) Example of pumping system efficiency indicator ..................................................................53

Bibliography .............................................................................................................................................................................................................................56

iv © ISO/ASME 2019 – All rights reserved
---------------------- Page: 4 ----------------------
ISO/ASME 14414:2019(E)
Foreword

ISO (the International Organization for Standardization) is a worldwide federation of national standards

bodies (ISO member bodies). The work of preparing International Standards is normally carried out

through ISO technical committees. Each member body interested in a subject for which a technical

committee has been established has the right to be represented on that committee. International

organizations, governmental and non-governmental, in liaison with ISO, also take part in the work.

ISO collaborates closely with the International Electrotechnical Commission (IEC) on all matters of

electrotechnical standardization.

The procedures used to develop this document and those intended for its further maintenance are

described in the ISO/IEC Directives, Part 1. In particular, the different approval criteria needed for the

different types of ISO documents should be noted. This document was drafted in accordance with the

editorial rules of the ISO/IEC Directives, Part 2 (see www .iso .org/directives).

Attention is drawn to the possibility that some of the elements of this document may be the subject of

patent rights. ISO shall not be held responsible for identifying any or all such patent rights. Details of

any patent rights identified during the development of the document will be in the Introduction and/or

on the ISO list of patent declarations received (see www .iso .org/patents).

Any trade name used in this document is information given for the convenience of users and does not

constitute an endorsement.

For an explanation of the voluntary nature of standards, the meaning of ISO specific terms and

expressions related to conformity assessment, as well as information about ISO's adherence to the

World Trade Organization (WTO) principles in the Technical Barriers to Trade (TBT) see www .iso

.org/iso/foreword .html.

This document was prepared by Technical Committee ISO/TC 115, Pumps, in collaboration with ASME

EA Standards Committee — Industrial System Energy Assessment.

Any feedback or questions on this document should be directed to the user’s national standards body. A

complete listing of these bodies can be found at www .iso .org/members .html.

This second edition cancels and replaces the first edition (ISO 14414:2015), which has been technically

revised. It also incorporates the Amendment ISO 14414:2015/Amd.1:2016. The main changes compared

to the previous edition are as follows:
— 4.2 has been slightly modified;

— Table 2 has been modified to add descriptions of “histogram” and “duration” diagrams;

— 5.6.4 has been redrafted;
— the term “specific energy” has been replaced by “specific energy consumption”;
— Formulae G.1, G.2 and G.4 have been corrected to align with ISO 17769-1;
— the bibliography has been modified;
— the document has been editorially revised.

ASME is the registered trademark of The American Society of Mechanical Engineers.

This standard was developed under procedures accredited as meeting the criteria for American National

Standards. The Standards Committee that approved the standard was balanced to ensure that individuals

from competent and concerned interests have had an opportunity to participate. The proposed code or

standard was made available for public review and comment that provides an opportunity for additional

public input from industry, academia, regulatory agencies, and the public-at-large.

© ISO/ASME 2019 – All rights reserved v
---------------------- Page: 5 ----------------------
ISO/ASME 14414:2019(E)

ASME does not “approve”, “rate”, or “endorse” any item, construction, proprietary device, or activity.

ASME does not take any position with respect to the validity of any patent rights asserted in connection

with any items mentioned in this document, and does not undertake to ensure anyone utilizing a

standard against liability for infringement of any applicable letters patent, nor assumes any such

liability. Users of a standard are expressly advised that determination of the validity of any such patent

rights, and the risk of infringement of such rights, is entirely their own responsibility.

Participation by federal agency representative(s) or person(s) affiliated with industry is not to be

interpreted as government or industry endorsement of this standard.

ASME accepts responsibility for only those interpretations of designated documents issued in

accordance with the established ASME procedures and policies, which precludes the issuance of

interpretations by individuals. ASME will not issue written interpretations of this edition of this

standard.

ISO/ASME 14414 was approved as an American National Standard by the American National Standards

Institute on 2015-02-06.
vi © ISO/ASME 2019 – All rights reserved
---------------------- Page: 6 ----------------------
ISO/ASME 14414:2019(E)
Introduction

Pumping systems account for a significant portion of a facility’s energy consumption in many industries.

In the majority of pumping systems, the energy added to the working liquid by the pump is much greater

than is required by the process. The excess energy added to the system (e.g. due to throttled control

valve) increases heat, noise and vibration but also increases the system’s maintenance costs. Oversized

pumps will cause excessive energy within a system. Increasing the size of the components within the

system such as pipes, valves and heat exchangers can, however, result in lower energy consumption.

This document provides a method to assess pump systems, to identify and quantify pump system energy

consumption reduction opportunities and reliability improvement opportunities. It gives a common

definition for what constitutes an assessment for both users and providers of assessment services. Its

objective is to provide clarity for these types of services which have been variously described as energy

assessments, energy audits, energy surveys and energy studies.

In all cases, systems (energy-using logical groups of equipment organized to perform a specific

function) are analysed through various techniques such as measurement, resulting in identification,

documentation and prioritization of energy performance improvement opportunities.

When contracting for assessment services, facility personnel can use this document to define and

communicate their desired scope of assessment activity to third party contractors or consultants.

This document is expected to contribute to decreased energy consumption and consequently to

decreased carbon footprint.

This document includes the required assessment report content in Annex A. It gives examples of

efficient system operation and energy reduction opportunities in Annex B, information on competencies

and experiences welcomed to perform audit in Annex C, guidelines for analysis software in Annex D, a

typical example of pre-screening worksheet in Annex E, information on specific energy consumption

in Annex F, information on the concept of parasitic power in Annex G and examples of pumping system

efficiency indicator in Annex H.

This document is developed within the framework of ISO 50001, ISO 50002 and ISO 50003.

© ISO/ASME 2019 – All rights reserved vii
---------------------- Page: 7 ----------------------
INTERNATIONAL STANDARD ISO/ASME 14414:2019(E)
Pump system energy assessment
1 Scope

This document sets the requirements for conducting and reporting the results of a pumping system

energy assessment (hereafter referenced as “assessment”) that considers the entire pumping system,

from energy inputs to the work performed as the result of these inputs.

The objective of a pumping system energy assessment is to determine the current energy consumption

of an existing system and identify ways to improve system efficiency.
These requirements consist of
— organizing and conducting an assessment,
— analysing the data from the assessment, and
— reporting and documenting assessment findings.

This document is designed to be applied, to open and closed loop pumping systems typically used at

industrial, institutional, commercial, and municipal facilities, when requested.

This document is focused on assessing electrically-driven pumping systems, which are dominant in

most facilities, but is also applicable with other types of drivers, such as steam turbines and engines.

The document does not
a) specify how to design a pumping system,

b) give detailed qualifications and expertise required of the person using the International Standard

although provides a list of body of knowledge in Annex C,
c) address the training or certification of persons,

d) specify how to implement the recommendations developed during the assessment, but does include

requirements for an action plan,

e) specify how to measure and validate the energy savings that result from implementing assessment

recommendations,

f) specify how to make measurements and how to calibrate test equipment used during the

assessment,

g) specify how to estimate the implementation cost or conduct financial analysis for recommendations

developed during the assessment,

h) specify specific steps required for safe operation of equipment during the assessment. The facility

personnel in charge of normal operation of the equipment are responsible for ensuring that it is

operated safely during the data collection phase of the assessment,

i) address issues of intellectual property, security, confidentiality, and safety.

2 Normative references

The following documents are referred to in the text in such a way that some or all of their content

constitutes requirements of this document. For dated references, only the edition cited applies. For

undated references, the latest edition of the referenced document (including any amendments) applies.

© ISO/ASME 2019 – All rights reserved 1
---------------------- Page: 8 ----------------------
ISO/ASME 14414:2019(E)

ISO 17769-1, Liquid pumps and installation — General terms, definitions, quantities, letter symbols and

units — Part 1: Liquid pumps

ISO 17769-2, Liquid pumps and installation — General terms, definitions, quantities, letter symbols and

units — Part 2: Pumping system
3 Terms and definitions

For the purposes of this document, the terms and definitions given in ISO 17769-1, ISO 17769-2 and the

following apply.

ISO and IEC maintain terminological databases for use in standardization at the following addresses:

— ISO Online browsing platform: available at https: //www .iso .org/obp
— IEC Electropedia: available at http: //www .electropedia .org/
3.1
system energy demand
minimum amount of energy which a pumping system in a specified process requires
3.2
components
individual items of equipment within a system
EXAMPLE Pump, motor, drive, valve, heat exchanger.
3.3
hydraulic power
pump power output
power imparted to the liquid by the pump
3.4
electrical power input
power required to support the pumping system operation
3.5
specific energy consumption
energy consumed to move a certain volume of liquid through the system
3.6
parasitic power

power imparted to the shaft of a pump and not used to move the fluid through the system

4 Identification of the assessment team, authority and functions
4.1 Identification of assessment team functions

The assessment team composed of knowledgeable personnel shall have members that are assigned

responsibility and authority to carry out the following functions.
— Resource allocation, in order to:
— allocate funding and resources necessary to plan and execute the assessment;
— exercise final decision making authority on resources;
2 © ISO/ASME 2019 – All rights reserved
---------------------- Page: 9 ----------------------
ISO/ASME 14414:2019(E)

— oversee the eventual participation of non-facility personnel including contracts, scheduling,

confidentiality agreements, and statement of work.
— Coordination, logistics and communications, in order to:

— obtain necessary support from facility personnel and other individuals and organizations

during the assessment;

— participate in organizing the assessment team and coordinate access to relevant personnel,

systems, and equipment;
— organize, schedule activities and manage the assessment.
4.2 Assessment team structure, leadership and competency

The assessment team should comprise of personnel from cross functional backgrounds.

It shall include:

— an assessor who has the pump system analysis competencies as described in Annex C;

— the host organization representative who has overall responsibility and ownership for the

assessment.
The assessment team should also include:
— experts on the processes and the function of the system;
— experts on the maintenance practices of the pumping system;
— experts who can provide the team with cost data.

The assessment team may be from the host organization or enhanced by using outsourced specialists

particularly considering the competence of the assessor.

The host organization shall appoint the assessment team leader. This person may be a host facility

employee or an external assessor. In small organizations, the team leader may be the competent

assessor.
4.3 Facility management support
Facility management shall understand and support the purpose of the assessment.

Facility management shall allow assessment team members from the facility to participate in the

assessment to the extent necessary.

The assessment team shall gain written support of facility management prior to conducting the

assessment, as follows:

— commit the necessary funding, personnel, and resources to support the assessment;

— communicate to facility personnel the assessment's importance to the organization.

4.4 Communications
Lines of communication required for the assessment shall be established.

The assessment team shall provide clear guidance to facilitate communications among members of the

assessment team so all necessary information and data can be communicated in a timely manner. This

shall include administrative data, logistics information, as well as operational and maintenance data.

© ISO/ASME 2019 – All rights reserved 3
---------------------- Page: 10 ----------------------
ISO/ASME 14414:2019(E)
4.5 Access to facilities, personnel and information
The assessment team shall have access to:
— facility areas and pump systems required to conduct the assessment;

— facility personnel (engineering, operations, maintenance, …), their equipment vendors, contractors

and others, to collect information pertinent and useful to the assessment activities and analysis of

data used for preparation of the report,

— other information sources such as drawings, manuals, data sheet, maintenance records, test reports,

historical utility bill information, computer monitoring and control data, electrical equipment

panels, and calibration records.

All data initially identified as essential to the assessment shall be obtained in discussions with

knowledgeable facility staff.
4.6 Assessment objectives, scope and boundaries

The overall objectives and scope of the assessment including portion(s) of the facility and boundaries

of the system(s) that are to be assessed shall be discussed and agreed upon at an early stage by the

assessment team.

The assessment team shall develop a list of site specific objectives for each pumping system, such as

performance improvement targets.
4.7 Action plan
4.7.1 General

An initial action plan for the assessment shall be developed and agreed upon by the assessment team

and system owners in order to facilitate the assessment and to make it clear to all assessment team

members how the assessment shall be conducted.

The action plan shall be flexible enough in order to accommodate various outcomes depending on

findings during the assessment, among others:
a) establish assessment objectives, in particular:
— determine system boundaries (see 5.4);
— review information that has been collected before the start of the assessment;

— identify how much is known about the systems and what general information has to be obtained;

— start with a level 1 assessment (see 5.1.2);
b) identify informational objectives for the assessment (see 5.1):
— determine how extensive the assessment is;
— identify the systems that are included in the assessment;

— identify what specific information is available and what is necessary to collect;

— identify information that is available on paper records (such as logs) or in the facility computer

systems and what system parameters are necessary to measure;

— identify who is going to be involved and responsible for the collection of necessary data;

4 © ISO/ASME 2019 – All rights reserved
---------------------- Page: 11 ----------------------
ISO/ASME 14414:2019(E)
c) establish measurement requirements (see 5.6) in particular:

— identify whether a snapshot of the conditions is sufficient (level 2 according to Table 1) or if

it is necessary to collect information during an extended period of time (level 3 according to

Table 2);

— identify if permanently installed measurement equipment is available and trustworthy;

d) identify additional informational objectives and, in particular, true process demands (see 5.4);

e) identify the methods required to meet assessment informational objectives:

— identify how the data are going to be analysed, taking into account the recommendations from

Annex B;
— identify tools/software programs that are going to be used;
f) identify content of the report and responsibilities.
4.7.2 Assessment scheduling

The dates of the assessment, and dates and times of key meetings shall be designated in advance of

beginning the assessment.
The assessment meetings shall include:
— kick-off meeting. It shall occur just prior to the commence
...

NORME ISO/ASME
INTERNATIONALE 14414
Deuxième édition
2019-01
Évaluation énergétique des systèmes
de pompage
Pump system energy assessment
Numéro de référence
ISO/ASME 14414:2019(F)
ISO/ASME 2019
---------------------- Page: 1 ----------------------
ISO/ASME 14414:2019(F)
DOCUMENT PROTÉGÉ PAR COPYRIGHT
© ISO 2019

Tous droits réservés. Sauf prescription différente ou nécessité dans le contexte de sa mise en œuvre, aucune partie de cette

publication ne peut être reproduite ni utilisée sous quelque forme que ce soit et par aucun procédé, électronique ou mécanique,

y compris la photocopie, ou la diffusion sur l’internet ou sur un intranet, sans autorisation écrite préalable. Une autorisation peut

être demandée à l’ISO à l’adresse ci-après ou au comité membre de l’ISO dans le pays du demandeur.

ISO copyright office ASME

Case postale 401 • Ch. de Blandonnet 8 Two Park Avenue • New York, NY 10016-5990 • USA

CH-1214 Vernier, Genève
Tél.: +41 22 749 01 11 Tél.: 800-843-2763
Fax: +41 22 749 09 47 Fax: 973-882-1717
E-mail: copyright@iso.org E-mail: CustomerCare@asme.org
Web: www.iso.org Web: www.asme.org
Publié en Suisse
ii © ISO/ASME 2019 – Tous droits réservés
---------------------- Page: 2 ----------------------
ISO/ASME 14414:2019(F)
Sommaire Page

Avant-propos ................................................................................................................................................................................................................................v

Introduction ..............................................................................................................................................................................................................................vii

1 Domaine d'application ................................................................................................................................................................................... 1

2 Références normatives ................................................................................................................................................................................... 2

3 Termes et définitions ....................................................................................................................................................................................... 2

4 Identification de l’autorité et des fonctions de l’équipe d’évaluation ..........................................................3

4.1 Identification des fonctions de l’équipe d’évaluation ............................................................................................ 3

4.2 Structure, encadrement et compétences de l’équipe d’évaluation ............................................................ 3

4.3 Soutien de la direction de l’installation ............................................................................................................................. 3

4.4 Communications .................................................................................................................................................................................... 4

4.5 Accès aux installations, au personnel et aux informations ............................................................................... 4

4.6 Objectifs, étendue de l’évaluation et limites .................................................................................................................. 4

4.7 Plan d’action .............................................................................................................................................................................................. 4

4.7.1 Généralités ............................................................................................................................................................................ 4

4.7.2 Planning de l’évaluation ............................................................................................................................................ 5

4.8 Collecte initiale des données et évaluation .................................................................................................................... 6

4.8.1 Généralités ............................................................................................................................................................................ 6

4.8.2 Entretiens initiaux avec les spécialistes du site .................................................................................... 6

4.8.3 Historique des projets relatifs à l’énergie .................................................................................................. 6

4.8.4 Coût de l’énergie............................................................................................................................................................... 6

4.8.5 Données initiales du système ............................................................................................................................... 6

4.9 Vérification des objectifs ................................................................................................................................................................ 7

5 Conduite de l’évaluation ............................................................................................................................................................................... 7

5.1 Niveaux d’évaluation .......................................................................................................................................................................... 7

5.1.1 Généralités ............................................................................................................................................................................ 7

5.1.2 Évaluations de niveau 1 ............................................................................................................................................. 7

5.1.3 Évaluations de niveau 2 ............................................................................................................................................. 8

5.1.4 Évaluations de niveau 3 ............................................................................................................................................. 8

5.2 État des lieux ............................................................................................................................................................................................. 9

5.3 Compréhension des exigences de fonctionnement du système ................................................................10

5.4 Détermination des limites du système et de la demande énergétique du système .................11

5.5 Informations nécessaires pour évaluer le rendement d’un système de pompage ....................11

5.5.1 Généralités .........................................................................................................................................................................11

5.5.2 Informations sur les moteurs électriques d’entraînement ......................................................11

5.5.3 Informations sur les pompes .............................................................................................................................12

5.5.4 Informations sur les propriétés des liquides .......................................................................................13

5.5.5 Données détaillées du système ........................................................................................................................13

5.5.6 Données mesurées ......................................................................................................................................................14

5.6 Collecte des données .......................................................................................................................................................................14

5.6.1 Informations sur le système ...............................................................................................................................14

5.6.2 Campagnes de mesurages des données opérationnelles de la pompe et du

moteur ...................................................................................................................................................................................15

5.6.3 Pression ................................................................................................................................................................................15

5.6.4 Débit ........................................................................................................................................................................................15

5.6.5 Puissance absorbée ....................................................................................................................................................15

5.7 Validation croisée ..............................................................................................................................................................................16

5.8 Réunion de synthèse, et présentation des constatations et recommandations initiales .....16

6 Rapports et documentation ...................................................................................................................................................................17

6.1 Rapport d’évaluation final ..........................................................................................................................................................17

6.2 Données pour examen par un tiers ....................................................................................................................................17

6.3 Examen du rapport final par les membres de l’équipe d’évaluation .....................................................17

Annexe A (normative) Contenu du rapport ................................................................................................................................................18

© ISO/ASME 2019 – Tous droits réservés iii
---------------------- Page: 3 ----------------------
ISO/ASME 14414:2019(F)

Annexe B (informative) Recommandations de fonctionnement efficace de systèmes et de

possibilités de réduction de la consommation d’énergie – Exemples .......................................................22

Annexe C (informative) Expertise, expérience et compétences ............................................................................................42

Annexe D (informative) Lignes directrices recommandées pour le logiciel d’analyse .................................45

Annexe E (informative) Exemple de feuille de travail de pré-analyse ............................................................................47

Annexe F (informative) Énergie spécifique ................................................................................................................................................49

Annexe G (informative) Énergie parasite du système de pompage ...................................................................................53

Annexe H (informative) Exemple d’indice de rendement du système de pompage .........................................56

Bibliographie ...........................................................................................................................................................................................................................58

iv © ISO/ASME 2019 – Tous droits réservés
---------------------- Page: 4 ----------------------
ISO/ASME 14414:2019(F)
Avant-propos

L'ISO (Organisation internationale de normalisation) est une fédération mondiale d'organismes

nationaux de normalisation (comités membres de l'ISO). L'élaboration des Normes internationales est

en général confiée aux comités techniques de l'ISO. Chaque comité membre intéressé par une étude

a le droit de faire partie du comité technique créé à cet effet. Les organisations internationales,

gouvernementales et non gouvernementales, en liaison avec l'ISO participent également aux travaux.

L'ISO collabore étroitement avec la Commission électrotechnique internationale (IEC) en ce qui

concerne la normalisation électrotechnique.

Les procédures utilisées pour élaborer le présent document et celles destinées à sa mise à jour sont

décrites dans les Directives ISO/IEC, Partie 1. Il convient, en particulier de prendre note des différents

critères d'approbation requis pour les différents types de documents ISO. Le présent document a été

rédigé conformément aux règles de rédaction données dans les Directives ISO/IEC, Partie 2 (voir www

.iso .org/directives).

L'attention est attirée sur le fait que certains des éléments du présent document peuvent faire l'objet de

droits de propriété intellectuelle ou de droits analogues. L'ISO ne saurait être tenue pour responsable

de ne pas avoir identifié de tels droits de propriété et averti de leur existence. Les détails concernant

les références aux droits de propriété intellectuelle ou autres droits analogues identifiés lors de

l'élaboration du document sont indiqués dans l'Introduction et/ou dans la liste des déclarations de

brevets reçues par l'ISO (voir www .iso .org/brevets).

Les appellations commerciales éventuellement mentionnées dans le présent document sont données

pour information, par souci de commodité, à l’intention des utilisateurs et ne sauraient constituer un

engagement.

Pour une explication de la nature volontaire des normes, la signification des termes et expressions

spécifiques de l'ISO liés à l'évaluation de la conformité, ou pour toute information au sujet de l'adhésion

de l'ISO aux principes de l’Organisation mondiale du commerce (OMC) concernant les obstacles

techniques au commerce (OTC), voir le lien suivant: www .iso .org/iso/fr/avant -propos .html.

Le présent document a été élaboré par le comité technique ISO/TC 115, Pompes, en collaboration avec le

comité des Normes ASME EA — Évaluation énergétique de système industriel.

Il convient que l’utilisateur adresse tout retour d’information ou toute question concernant le présent

document à l’organisme national de normalisation de son pays. Une liste exhaustive desdits organismes

se trouve à l’adresse www .iso .org/fr/members .html.

Cette deuxième édition annule et remplace la première édition (ISO 14414:2015), qui a fait l’objet d’une

révision technique. Il incorpore également l'amendement ISO 14414:2015/Amd.1:2016. Les principales

modifications par rapport à l’édition précédente sont les suivantes:
— 4.2 a été légèrement modifié;

— le Tableau 2 a été modifié pour ajouter les descriptions des diagrammes «histogramme» et «durée»;

— le paragraphe 5.6.4 a été reformulée;

— le terme «énergie spécifique» a été remplacé par «consommation d'énergie spécifique»;

— les Formules G.1, G.2 et G.4 ont été corrigées pour être alignées sur l’ISO 17769-1;

— la bibliographie a été modifiée;
— le document a été révisé sur le plan rédactionnel.
L’ASME est une marque déposée de l’American Society of Mechanical Engineers.

Cette norme a été développée selon les procédures reconnues satisfaisant aux normes nationales

américaines. Le comité technique a été créé pour assurer une représentation équilibrée. Il était

© ISO/ASME 2019 – Tous droits réservés v
---------------------- Page: 5 ----------------------
ISO/ASME 14414:2019(F)

composé de personnes possédant les compétences et les intérêts requis. Le code ou la norme proposé a

été soumis à l’examen public pour commentaires, de façon à obtenir des observations complémentaires

du secteur de l’industrie, du milieu de l’enseignement, des organismes de réglementation et du public en

général.

L’ASME «n’approuve», «n’évalue» ni «n’entérine» aucun article, produit, dispositif breveté ou activité.

L’ASME ne prend pas position en ce qui a trait à la validité des droits de propriété intellectuelle ayant trait

à tout article mentionné dans le présent document et ne s’engage pas à dégager de ses responsabilités

quiconque utilise une norme en violation de toute lettre patente applicable, ni à assumer de telles

responsabilités. Les utilisateurs d’une norme sont expressément informés de la responsabilité qui leur

incombe pleinement en ce qui concerne la détermination de la validité de tous droits sur des brevets et

le risque de d’atteinte à tels droits.

La participation de représentant(s) d’organismes fédéraux ou de personne(s) affiliée(s) au secteur de

l’industrie n’est pas à interpréter comme étant un endossement de cette norme par le gouvernement ou

l’industrie.

L’ASME accepte d’assumer des responsabilités uniquement pour les interprétations émises

conformément aux procédures et politiques de l’ASME qui la régissent et empêchent les interprétations

de tiers. L’ASME n’émettra pas d’interprétation écrite de la présente édition de la présente norme.

L’ISO/ASME 14414 a été approuvée en tant que norme nationale américaine par l’Institut de

normalisation nationale américain le 2015-02-06.
vi © ISO/ASME 2019 – Tous droits réservés
---------------------- Page: 6 ----------------------
ISO/ASME 14414:2019(F)
Introduction

Dans beaucoup d’industries, les systèmes de pompage représentent une part significative de la

consommation d’énergie d’un site. Dans la majorité des systèmes de pompage, l’énergie ajoutée

au fluide travaillé par la pompe est beaucoup plus importante que ce qui est nécessaire au procédé.

L’énergie ajoutée en excès dans le système (par exemple, provoqué par une vanne de régulation avec

organe d’étranglement) augmente la chaleur, le bruit et les vibrations, mais augmente aussi les coûts

de maintenance du système. Les pompes surdimensionnées entraînent une surcharge énergétique

du système. Cependant, l'augmentation de la dimension des composants dans le système tels que les

tuyauteries, les appareils de robinetterie et les échangeurs thermiques peut engendrer une diminution

de la consommation énergétique.

Le présent document entend fournir une méthode d’évaluation des systèmes de pompage permettant

d’identifier et de quantifier les possibilités de réduction de la consommation d’énergie de ces

systèmes et les possibilités d’amélioration de leur fiabilité. Elle donne une définition commune pour

les utilisateurs et pour les prestataires de services de ce qui constitue une évaluation. Son objectif est

d’apporter des éclaircissements sur ces types de services qui ont fait l’objet de désignations diverses

telles qu’évaluations énergétiques, audits énergétiques, enquêtes énergétiques et études énergétiques.

Dans tous les cas, les systèmes (groupes logiques d’équipements consommateurs d’énergie, organisés

pour assurer une fonction spécifique) sont analysés au moyen de techniques diverses telles que des

campagnes de mesurages aboutissant à l’identification, à la documentation et au classement par priorité

des possibilités d’amélioration des performances énergétiques.

Lors de la passation de contrats de prestations de services d’évaluation, le personnel du site peut utiliser

le présent document pour définir et communiquer le périmètre souhaité de l’activité d’évaluation à des

tiers prestataires ou consultants.

Le présent document devrait contribuer à réduire la consommation d’énergie et, en conséquence,

l’empreinte carbone.

Le présent document comporte le contenu exigé du rapport d’évaluation en Annexe A. Elle comporte des

exemples de fonctionnement efficace de systèmes et de possibilités de réduction de la consommation

d’énergie en Annexe B, des informations sur les compétences et expériences souhaitables pour effectuer

des audits en Annexe C, des lignes directrices pour le logiciel d’analyse en Annexe D, un exemple type de

feuille de travail de pré-analyse en Annexe E, des informations sur l'énergie spécifique en Annexe F, des

informations sur le concept d’énergie parasite en Annexe G et des exemples d’indicateur de rendement

d’un système de pompage en Annexe H.

Le présent document est élaboré dans le cadre des normes ISO 50001, ISO 50002 et ISO 50003.

© ISO/ASME 2019 – Tous droits réservés vii
---------------------- Page: 7 ----------------------
NORME INTERNATIONALE ISO/ASME 14414:2019(F)
Évaluation énergétique des systèmes de pompage
1 Domaine d'application

Le présent document pose les exigences de réalisation et de compte-rendu d’une évaluation énergétique

de système de pompage (désignée par la suite «évaluation») qui prend en compte l’ensemble de

l’installation de pompage, depuis les points d’introduction de l’énergie dans l’installation jusqu’au

travail fourni par l’installation à l’aide de cette énergie.

L’objectif d’une évaluation énergétique d’un système de pompage est de déterminer la consommation

d’énergie actuelle d’un système existant et d’identifier les manières d’augmenter l’efficacité du système.

Ces exigences concernent
— l’organisation et le pilotage d’une évaluation,
— l’analyse des données de l’évaluation,

— la rédaction du compte-rendu de fin d’évaluation et étayer les conclusions de l'évaluation..

Le présent document est conçu pour être appliqué, selon la demande, aux systèmes de pompage en

boucle ouverte et en boucle fermée, utilisés dans des installations industrielles, institutionnelles,

commerciales et municipales.

Le présent document met la priorité sur l’évaluation des systèmes de pompage entraînés par des

moteurs électriques, qui sont majoritaires dans les installations. Elle est toutefois applicable à d’autres

types d’entraînements, par exemple turbines à vapeur et moteurs thermiques. Le présent document

a) ne spécifie pas la manière de concevoir un système de pompage,

b) ne fournit pas de détails sur les qualifications et l’expertise exigées de la personne utilisant la

présente Norme internationale, bien qu’elle fournisse une liste d’un ensemble de connaissances en

Annexe C,
c) ne traite pas de la formation et de la certification des personnes,

d) ne spécifie pas la manière de mettre en place les recommandations élaborées au cours de

l’évaluation, elle inclut néanmoins des exigences relatives à un plan d’action,

e) ne spécifie pas la manière de mesurer de valider les économies d’énergie résultant de la mise en

œuvre des recommandations de l’évaluation,

f) ne spécifie pas la manière d’effectuer des campagnes de mesurages et la manière d’étalonner les

équipements d’essai utilisés lors de l’évaluation,

g) ne spécifie pas la manière d’estimer les coûts de mise en œuvre et de conduire l’analyse financière

concernant les recommandations élaborées au cours de l’évaluation,

h) ne spécifie pas les étapes spécifiques exigées pour un fonctionnement sûr des équipements au

cours de l’évaluation. Le personnel du site en charge du fonctionnement courant des équipements

est chargé de veiller à ce qu’ils fonctionnent en toute sécurité durant la phase de collecte de données

de l’évaluation,

i) ne traite pas des questions de propriété intellectuelle, de sûreté, de confidentialité et de sécurité.

© ISO/ASME 2019 – Tous droits réservés 1
---------------------- Page: 8 ----------------------
ISO/ASME 14414:2019(F)
2 Références normatives

Les documents suivants sont mentionnés dans le texte de sorte que tout ou partie de leur contenu

constitue des exigences du présent document. Pour les références datées, seule l'édition citée s'applique.

Pour les références non datées, la dernière édition du document de référence s'applique (y compris les

éventuels amendements).

ISO 17769-1, Pompes pour liquides et installations — Termes généraux, définitions, grandeurs, symboles

littéraux et unités — Partie 1: Pompes pour liquides

ISO 17769-2, Pompes pour liquides et installations — Termes généraux, définitions, grandeurs, symboles

littéraux et unités — Partie 2: Systèmes de pompage
3 Termes et définitions

Pour les besoins du présent document, les termes et définitions donnés dans l’ISO 17769-1 et

l’ISO 17769-2, ainsi que les suivants s’appliquent.

L'ISO et l’IEC tiennent à jour des bases de données terminologiques à utiliser pour la normalisation aux

adresses suivantes:

— ISO Online browsing platform: disponible à l'adresse https: //www .iso .org/obp

— IEC Electropedi: disponible à l’adresse http: //www .electropedia .org/
3.1
demande énergétique du système

quantité minimale d’énergie exigée par un système de pompage dans un procédé spécifié

3.2
composants
équipements élémentaires dans un système
EXEMPLE Pompe, moteur, entraînement, vanne, échangeur de chaleur.
3.3
puissance hydraulique
cheval vapeur hydraulique
puissance transmise au liquide par la pompe
3.4
puissance électrique absorbée
puissance nécessaire pour faire fonctionner le système de pompage
3.5
énergie spécifique
énergie consommée pour déplacer un volume donné de liquide à travers le système
3.6
puissance parasite

puissance transmise à l’arbre d’entraînement d’une pompe et non utilisée pour déplacer le fluide à

travers le système
2 © ISO/ASME 2019 – Tous droits réservés
---------------------- Page: 9 ----------------------
ISO/ASME 14414:2019(F)
4 Identification de l’autorité et des fonctions de l’équipe d’évaluation
4.1 Identification des fonctions de l’équipe d’évaluation

L’équipe d’évaluation composée de personnel compétent doit être formée de membres ayant reçu la

responsabilité et l’autorité nécessaires pour assurer les fonctions suivantes.
— Allocation des ressources pour:

— affecter les moyens financiers et les ressources nécessaires à la planification et à l’exécution de

l’évaluation,
— exercer le pouvoir décisionnel ultime sur les ressources,

— superviser la participation éventuelle de personnel extérieur au site, y compris les contrats,

plannings, accords de confidentialité et liste de prestations.
— Coordination, logistique et communication pour:

— obtenir le soutien nécessaire de la part du personnel des sites et d’autres personnes et

organisations au cours de l’évaluation,

— participer à l’organisation de l’équipe d’évaluation et coordonner l’accès au personnel, aux

systèmes et aux équipements concernés,
— organiser, planifier les activités et gérer l’évaluation.
4.2 Structure, encadrement et compétences de l’équipe d’évaluation

Il convient que l’équipe d’évaluation se compose de personnes ayant des origines diverses. Elle doit

comprendre:

— un évaluateur possédant les compétences d’analyse du système de pompage décrites en Annexe C,

— le représentant de la structure cliente qui assume la responsabilité générale et la prise en charge de

l’évaluation,
L'équipe d'évaluation peut aussi comprendre:
— des experts sur les procédés et le fonctionnement du système,
— des experts sur les pratiques de maintenance du système de pompage,
— des experts pouvant fournir à l’équipe des données relatives aux coûts.

L’équipe d’évaluation peut être issue de la structure cliente ou être renforcée avec des spécialistes

extérieurs, notamment au regard des compétences de l’évaluateur.

La structure cliente doit désigner le responsable de l’équipe d’évaluation. Cette personne peut être un

employé de la structure cliente ou un évaluateur externe. Dans les petites organisations, le responsable

de l’équipe peut être l’évaluateur compétent.
4.3 Soutien de la direction de l’installation

La direction de l’installation doit comprendre et soutenir le but de l’évaluation.

La direction de l’installation doit permettre aux membres de l’équipe d’évaluation du site de participer

à l’évaluation dans la mesure des besoins.
© ISO/ASME 2019 – Tous droits réservés 3
---------------------- Page: 10 ----------------------
ISO/ASME 14414:2019(F)

L’équipe d’évaluation doit obtenir la confirmation écrite du soutien de la direction de l’installation,

portant sur les points suivants, avant de commencer l’évaluation:

— affectation des moyens financiers, du personnel et des ressources nécessaires pour soutenir

l’évaluation,

— communication au personnel du site de l’importance de l’évaluation pour l’organisation.

4.4 Communications
Les moyens de communication nécessaires à l’évaluation doivent être définis.

L’équipe d’évaluation doit fournir des consignes claires pour faciliter la communication parmi les

membres de l’équipe d'évaluation, de sorte que toutes les informations et données nécessaires puissent

être communiquées en temps utile. Ces informations doivent comprendre aussi bien les données

administratives, que les informations logistiques et que les données opérationnelles et de maintenance.

4.5 Accès aux installations, au personnel et aux informations
L’équipe d’évaluation doit avoir accès:

— aux installations et aux systèmes de pompage nécessaires pour conduire l’évaluation,

— au personnel du site (ingénierie, exploitation, maintenance, etc.), aux fournisseurs des équipements,

aux prestataires et autres, afin de collecter des informations pertinentes et utiles aux activités

d’évaluation et à l’analyse des données utilisées pour l’élaboration du rapport,

— aux autres sources d’information telles que plans, manuels, fiches techniques, historiques des

opérations de maintenance, rapports d’essai, informations sur l’historique des factures d’électricité,

données de surveillance et de régulation informatisées, tableaux électriques des équipements et

enregistrements d’étalonnage.

Toutes les données initialement identifiées comme essentielles à l’évaluation doivent être obtenues lors

de discussions avec le personnel du site disposant des qualifications requises.
4.6 Objectifs, étendue de l’évaluation et limites

Les objectifs généraux et l’étendue de l’évaluation, y compris la (ou les) portion(s) du site et les limites

du (ou des) système(s) appelé(s) à faire l’objet de l’évaluation, doivent être examinés et convenus au plus

tôt au sein de l’équipe d’év
...

Questions, Comments and Discussion

Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.