Railway applications - Track - Switches and crossings for Vignole rails - Part 1: Definitions

This European Standard provides an accepted "terminology" for switch and crossing work. With the assistance of diagrams, the various components are given definitions, and these specific names are regarded as obligatory.
The definitions cover the constituent parts and design geometry of switch and crossing work, and include the movement of switches. Additional terminology of a more specific nature will be defined in the relevant part of the series.
The present definitions set out the terms most generally used for the geometrical form and the construction of switches and crossings, omitting those of too special a nature.

Bahnanwendungen - Oberbau - Weichen und Kreuzungen für Vignolschienen - Teil 1: Definitionen

Applications ferroviaires - Voie - Appareils de voie - Partie 1: Définitions

Le présent document établit la terminologie couramment utilisée pour les appareils de voie. Les différents éléments sont définis à l'aide de figures et leurs dénominations spécifiques doivent être respectées.
Les définitions couvrent les constituants, ainsi que la géométrie conceptuelle des appareils de voie. Chaque partie de la série de normes fournit des termes et définitions supplémentaires plus spécifiques.
Les définitions fournies ci-après concernent les termes les plus couramment utilisés pour la forme géométrique et la construction des appareils de voie ; elles ne couvrent pas les cas plus spécifiques.

Železniške naprave - Zgornji ustroj proge - Kretnice in križišča za Vignolove tirnice - 1. del: Definicije

General Information

Status
Not Published
Public Enquiry End Date
31-Mar-2020
Technical Committee
Current Stage
4020 - Public enquire (PE) (Adopted Project)
Start Date
31-Jan-2020
Due Date
19-Jun-2020
Completion Date
01-Apr-2020

RELATIONS

Buy Standard

Draft
oSIST prEN 13232-1:2020
English language
22 pages
sale 10% off
Preview
sale 10% off
Preview

e-Library read for
1 day

Standards Content (sample)

SLOVENSKI STANDARD
oSIST prEN 13232-1:2020
01-marec-2020

Železniške naprave - Zgornji ustroj proge - Kretnice in križišča za Vignolove tirnice

- 1. del: Definicije

Railway applications - Track - Switches and crossings for Vignole rails - Part 1:

Definitions
Bahnanwendungen - Oberbau - Weichen und Kreuzungen für Vignolschienen - Teil 1:
Definitionen
Applications ferroviaires - Voie - Appareils de voie - Partie 1: Définitions
Ta slovenski standard je istoveten z: prEN 13232-1
ICS:
01.040.45 Železniška tehnika (Slovarji) Railway engineering
(Vocabularies)
45.080 Tračnice in železniški deli Rails and railway
components
oSIST prEN 13232-1:2020 en,fr,de

2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.

---------------------- Page: 1 ----------------------
oSIST prEN 13232-1:2020
---------------------- Page: 2 ----------------------
oSIST prEN 13232-1:2020
DRAFT
EUROPEAN STANDARD
prEN 13232-1
NORME EUROPÉENNE
EUROPÄISCHE NORM
January 2020
ICS 01.040.93; 93.100 Will supersede EN 13232-1:2003
English Version
Railway applications - Track - Switches and crossings for
Vignole rails - Part 1: Definitions

Applications ferroviaires - Voie - Appareils de voie - Bahnanwendungen - Oberbau - Weichen und

Partie 1: Définitions Kreuzungen für Vignolschienen - Teil 1: Definitionen

This draft European Standard is submitted to CEN members for enquiry. It has been drawn up by the Technical Committee

CEN/TC 256.

If this draft becomes a European Standard, CEN members are bound to comply with the CEN/CENELEC Internal Regulations

which stipulate the conditions for giving this European Standard the status of a national standard without any alteration.

This draft European Standard was established by CEN in three official versions (English, French, German). A version in any other

language made by translation under the responsibility of a CEN member into its own language and notified to the CEN-CENELEC

Management Centre has the same status as the official versions.

CEN members are the national standards bodies of Austria, Belgium, Bulgaria, Croatia, Cyprus, Czech Republic, Denmark, Estonia,

Finland, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta, Netherlands, Norway,

Poland, Portugal, Republic of North Macedonia, Romania, Serbia, Slovakia, Slovenia, Spain, Sweden, Switzerland, Turkey and

United Kingdom.

Recipients of this draft are invited to submit, with their comments, notification of any relevant patent rights of which they are

aware and to provide supporting documentation.

Warning : This document is not a European Standard. It is distributed for review and comments. It is subject to change without

notice and shall not be referred to as a European Standard.
EUROPEAN COMMITTEE FOR STANDARDIZATION
COMITÉ EUROPÉEN DE NORMALISATION
EUROPÄISCHES KOMITEE FÜR NORMUNG
CEN-CENELEC Management Centre: Rue de la Science 23, B-1040 Brussels

© 2020 CEN All rights of exploitation in any form and by any means reserved Ref. No. prEN 13232-1:2020 E

worldwide for CEN national Members.
---------------------- Page: 3 ----------------------
oSIST prEN 13232-1:2020
prEN 13232-1:2020 (E)
Contents

European foreword ....................................................................................................................................................... 3

1 Scope .................................................................................................................................................................... 4

2 Normative references .................................................................................................................................... 4

3 Terms and definitions ................................................................................................................................... 4

3.1 General definitions ......................................................................................................................................... 4

3.2 Definitions of special trackwork ............................................................................................................... 9

3.3 Definitions of terms in turnouts and diamonds ................................................................................ 11

3.4 Definitions of terms in layouts ................................................................................................................ 19

3.5 Definitions of constituent parts of switch and crossing work ..................................................... 21

3.6 Documents ...................................................................................................................................................... 22

---------------------- Page: 4 ----------------------
oSIST prEN 13232-1:2020
prEN 13232-1:2020 (E)
European foreword

This document (prEN 13232-1:2020) has been prepared by Technical Committee CEN/TC 256 “Railway

applications”, the secretariat of which is held by DIN.
This document is currently submitted to the CEN Enquiry.
This document will supersede EN 13232-1:2003.

This series of standards “Railway applications – Track – Switches and crossings for Vignole rails” covers

the design and quality of switches and crossings in flat bottomed rail. The list of Parts is as follows:

— Part 1: Definitions
— Part 2: Requirements for geometric design
— Part 3: Requirements for wheel/rail interaction
— Part 4: Actuation, locking and detection
— Part 5: Switches
— Part 6: Fixed common and obtuse crossings
— Part 7: Crossings with moveable parts
— Part 8: Expansion devices
— Part 9: Layouts

Part 1 contains terminology used throughout all parts of this series. Parts 2 to 4 contain basic design

guides and are applicable to all switch and crossing assemblies. Parts 5 to 8 deal with particular types of

equipment including their tolerances. These use Parts 1 to 4 as a basis. Part 9 defines the functional and

geometric dimensions and tolerances for layout assembly.
---------------------- Page: 5 ----------------------
oSIST prEN 13232-1:2020
prEN 13232-1:2020 (E)
1 Scope

This document provides an accepted “terminology” for switch and crossing work. With the assistance of

diagrams, the various components are given definitions, and these specific names are regarded as

obligatory.

The definitions cover the constituent parts and design geometry of switch and crossing work.

Additional terminology of a more specific nature will be defined in the relevant part of the series.

The present definitions set out the terms most generally used for the geometrical form and the

construction of switches and crossings, omitting those of too special a nature.
2 Normative references
There are no normative references in this document.
3 Terms and definitions

For the purposes of this document, the following terms and definitions apply. ISO and IEC maintain

terminological databases for use in standardization at the following addresses:
• ISO Online browsing platform: available at https://www.iso.org/obp
• IEC Electropedia: available at http://www.electropedia.org/
3.1 General definitions
3.1.1
customer

term used to define one party involved in using the EN as the technical basis for a transaction: the

Operator or User of the equipment, or the Purchaser of the equipment on the User's behalf

3.1.2
supplier

term used to define one party involved in using the EN as the technical basis for a transaction: the Body

responsible for the use of the EN in response to the Customer's requirements
3.1.3
contact area

those parts of the rail ensuring the support and/or guidance, inside or outside, of a wheel (see Figure 4)

3.1.4
running table
upper surface of the head of a rail. See Figures 1 and 4
---------------------- Page: 6 ----------------------
oSIST prEN 13232-1:2020
prEN 13232-1:2020 (E)
Key
1 running table
Figure 1
3.1.5
running surface

curved surface defined by the longitudinal displacement of a straight line perpendicular to the centre-

line of the track and tangential to both running tables (see Figure 2)
Figure 2
3.1.6
running plane

flat plane tangential to the running surface at the considered point (see Figure 4)

3.1.7
rail inclination

angle measured as a tangent (e.g. 1 in 20) between the normal to the running surface and the y-y axis of

the rail. See Figure 3. Rail head inclination may be achieved by inclining the rail as shown in figure3 or

by inclining the head profile only, for example by machining
---------------------- Page: 7 ----------------------
oSIST prEN 13232-1:2020
prEN 13232-1:2020 (E)
Key
1 y-y-axis
2 rail inclination
Figure 3
3.1.8
inclined track

where the axes of the two running rails are inclined inwards towards each other (see Figure 4)

3.1.9
vertical track

where the axes of the two running rails are parallel, that is, have a rail inclination of zero (see Figure 4)

3.1.10
rail twist
change in inclination of the rail (e.g. from 1 in 20 to vertical) (see Figure 4)
Key
1 contact area 6 vertical rail
2 running table 7 gauge reference plane
3 running plane 8 running edge
4 inclined rail 9 design track gauge
5 rail twist
Figure 4
---------------------- Page: 8 ----------------------
oSIST prEN 13232-1:2020
prEN 13232-1:2020 (E)
3.1.11
gauge reference plane

plane parallel to and below the running surface at a dimension “z”. This dimension “z” is 14mm for

interoperable railways with 1435, 1524, 1600 and 1668 mm track gauge or 13 mm for 1520 mm track

gauge. This plane is used for all design work, machining, and measurements (see Figures 4 and 5)

a) b)
Key
z depth of gauge reference plane below running table
Figure 5
3.1.12
running edge

intersection of the gauge reference plane with the inside of the rail head (see Figure 4)

3.1.13
design track gauge
distance between the corresponding running edges of the two rails (see Figure 4)
3.1.14
centre-line of track

line midway between the running edges on straight track, and half design track gauge inside the

running edge of the larger radius rail in curved track (see Figures 4 and 6)
3.1.15
high-side rail

on curved track, the rail with the larger radius, i.e. centre-line radius plus half of design track gauge

3.1.16
low-side rail
on curved track, the rail with the smaller radius
3.1.17
gauge widening

intended increase in design track gauge. The radius of the low-side rail is decreased, and the distance

between the centre-line of track and the low-side rail is increased, by the amount of gauge widening

(see Figure 6)
---------------------- Page: 9 ----------------------
oSIST prEN 13232-1:2020
prEN 13232-1:2020 (E)
Key
1 gauge widening on sharp curves
2 A + gauge widening
3 A + gauge widening
A design track gauge / 2
Figure 6
3.1.18
sleeper or bearer spacing

distance along the rails between the centre-lines of adjacent sleepers or bearers

3.1.19
cant (superelevation)
amount by which one running rail is raised above the other (see Figure 7)
Key
1 horizontal
2 cant (superelevation)
Figure 7
---------------------- Page: 10 ----------------------
oSIST prEN 13232-1:2020
prEN 13232-1:2020 (E)
3.1.20
equilibrium cant

cant at a particular speed at which the vehicle will have a resultant force perpendicular to the running

plane
3.1.21
cant deficiency
difference between the applied cant on the track and a higher equilibrium cant
3.2 Definitions of special trackwork
3.2.1
switch and crossing work

trackwork ensuring the support and guidance of a vehicle along any given route among various

diverging or intersecting tracks. The term (switch and crossing work) is amplified to include certain

items having other functions (for example, expansion devices)

Note 1 to entry: Switches are in some circumstances described as points - either word is considered acceptable.

...

Questions, Comments and Discussion