SIST EN IEC 60953-4:2027
(Main)Rules for steam turbine thermal acceptance tests - Part 4: Routine testing (IEC 60953-4:2026)
- Abstract
This part of IEC 60953 establishes a Supplementary Standard for routine testing of steam turbines.
The rules given in this document follow the guidance given in IEC 60953-0, but contain amendments and supplements regarding the analysis and supervision of relative performance by routine testing of steam turbine.
General principles for the preparation, performance evaluation, trends of performance parameters and the determination of the measurement uncertainty of periodic routine tests are given in this document.
This document is applicable to routine testing covering a wide range of accuracy on steam turbines of every type, rating and application, operating with superheated or saturated steam.
This document is not intended for application in acceptance tests of new units or retrofits and its application for such is strongly not recommended.
- Status
- Published
- Public Enquiry End Date
- 31-Oct-2025
- Publication Date
- 17-Nov-2026
- Technical Committee
- I10 - Imaginarni 10 za neaktivna TDT na elektro področju
- Current Stage
- 6060 - National Implementation/Publication (Adopted Project)
- Start Date
- 10-Nov-2026
- Due Date
- 15-Jan-2027
- Completion Date
- 18-Nov-2026
SIST EN IEC 60953-4:2027 is the Slovenian standard for routine testing of steam turbines, published by SIST and identical to prEN IEC 60953-4:2025. It gives supplementary rules for analyzing and supervising relative performance in existing power plants, with an emphasis on repeatable trend monitoring rather than full acceptance-test accuracy.
What does SIST EN IEC 60953-4:2027 specify?
SIST EN IEC 60953-4:2027 specifies routine thermal acceptance testing for steam turbines and turbine cycles. It is intended for existing units and for long-term performance monitoring, diagnosis, and comparison against a chosen reference condition.
The document is written as a supplement to IEC 60953-0. It keeps the same overall structure as IEC 60953-0, but adds routine-test-specific guidance and annexes for planning, measurement, evaluation, correction, uncertainty, and examples.
It is applicable to steam turbines of every type, rating, and application operating with superheated or saturated steam. The introduction also states that it is not recommended for acceptance tests on new units or retrofit units.
| Annex | What it covers |
|---|---|
| A | Feedwater heater leakage and condenser leakage tests |
| B | Evaluation of multiple measurements and compatibility |
| C | Mass flow balances |
| D | Short-statistical definition of measuring uncertainty and error propagation |
| E | Temperature variation method |
| F | Guidance on selecting a type of routine test |
| G | Sensitivity factors for component performance on overall cycle performance |
| H | Typical thermodynamic boundary and instrument layout for routine tests |
| I | Calculation and analysis of test results - numerical example |
| J | Numerical example of uncertainty calculation for periodic routine tests |
| K | Typical reasons for deviations of steam turbine performance from reference or design level |
What are the key requirements of SIST EN IEC 60953-4:2027?
SIST EN IEC 60953-4:2027 focuses on getting comparable results over time with a simplified test setup. The practical aim is to detect performance change, locate likely causes, and support maintenance planning with results that can be repeated consistently.
Test planning and responsibility
Clause 4 requires advance agreement on the test type, procedure, measuring points, instruments, valves, and piping arrangements. One person should be assigned responsibility for the routine test, including coordination, decisions during the test, calculations, and reporting. In practice, this avoids changing methods from one test to the next, which is important if the results are to be trended over years.
Clause 4 also recommends routine tests at regular intervals, at least once a year, and before and after overhaul. That matters because the standard is designed to track change, so tests are most useful when they are repeated under similar conditions.
Plant condition and cycle isolation
Before testing, the steam turbine, driven machine, condenser, and feedheaters should be in suitable condition, and leaks should be eliminated as far as possible. Clause 4 also requires the cycle to be isolated so that the reference test and later tests are comparable.
The document pays particular attention to unaccounted leakage. If the difference from the reference test exceeds 0.2% of full-load main steam flow, it should be investigated and corrected or otherwise accounted for. In practice, this helps distinguish real turbine deterioration from leakage or cycle-side effects.
Instrument selection and calibration
Clause 5 gives a flexible approach to instruments, with emphasis on repeatability and cost-effective routine monitoring. Permanently installed plant instruments may be used, especially for preliminary assessment and some primary measurements, but they need known calibration status or field verification before the test.
The standard distinguishes primary parameters from secondary parameters. Primary parameters are those that significantly affect the result and therefore need known calibration status; secondary parameters have a smaller effect. This matters because routine tests often rely on a mix of plant instruments and portable instruments, and the standard expects the team to choose the arrangement that gives stable comparison results.
Measurement methods for flow, pressure, temperature, and steam condition
Clause 5 sets out how to measure power, primary flow, secondary flows, pressure, temperature, steam quality, time, and speed. For primary flow, the preferred basis is water flow measurement, while steam flow between the steam generator outlet and the turbine throttle can be used in special cases when repeatability is good.
The pressure rules require measurements close to the turbine stop valve and at key turbine, feed, and pump locations. Temperature measurements are also placed at feed train points, heater inlets and outlets, and bled steam lines where needed for heat balance. These placements matter because the standard uses the measured boundary conditions to correct results back to the chosen reference condition.
Evaluation, correction, and trending
Clause 6 covers averaging, data checking, mass flow balances, and leakage treatment. Clause 7 then explains correction of test results and comparison with the reference condition. The document explicitly treats routine-test comparison as a relative-performance exercise, so the same correction method should be used for the reference test and the later comparative tests.
Clause 7 also requires performance trending. Heat rate, power output, HP turbine efficiency, IP turbine efficiency, first-stage pressure, and extraction pressure are all used as chronological indicators of condition change. In practice, this gives engineers a way to see deterioration before it becomes an outage problem.
Measuring uncertainty
Clause 8 addresses uncertainty, but with a routine-test emphasis on uncertainty of performance differences rather than absolute acceptance-test uncertainty. The document points to the method in IEC 60953-3 for determining uncertainty of performance differences and includes a numerical example in Annex J.
That distinction matters because routine testing is meant to be economical and repeatable, not to reproduce a full acceptance test. The uncertainty framework supports decisions about whether a change in performance is real enough to act on.
What terms does SIST EN IEC 60953-4:2027 define?
Reference condition - The external test-boundary values to which the measured results are corrected.
Reference test - A test carried out under the reference condition, used as the baseline for later comparisons.
Comparative test - A current test or series of tests used to show relative performance change against the reference test.
Repeatability - The ability of the measurement system to give the same output/input relationship over time, which is central to routine monitoring.
Primary parameters - Measured variables with a major influence on the result, so they need known calibration status.
Secondary parameters - Measured variables with a smaller influence on the result, often handled with less demanding instrumentation.
Thermal efficiency - A routine performance result used to describe how effectively the turbine cycle converts heat into useful output.
Heat rate - A routine performance result used alongside thermal efficiency to track cycle performance over time.
Who uses SIST EN IEC 60953-4:2027?
SIST EN IEC 60953-4:2027 is used by performance engineers, plant operators, maintenance teams, and technical managers responsible for steam turbine plants. It is relevant to fossil plants, nuclear applications, combined-cycle units, and co-generating units where routine performance monitoring is needed.
The document is especially useful when the objective is to schedule maintenance based on performance, diagnose changes in a turbine or cycle, and compare current operation with a baseline. Buyers and owners can also use it to agree the basis for a specific routine-testing procedure.
What changed in SIST EN IEC 60953-4:2027 from the previous edition?
SIST EN IEC 60953-4:2027 is presented as a supplementary standard to IEC 60953-0 and adds routine-test-specific material. The introduction states that it adds guidance for planning, timing, test leadership, settings, cycle isolation, allowable conditions, instrument consistency, leakage treatment, correction comparison, performance trending, heat rate diagnosis, and routine-test uncertainty.
It also adds new annexes F to K, including guidance on test selection, sensitivity factors, thermodynamic boundary layouts, worked numerical examples, uncertainty examples, and typical reasons for performance deviation.
Which standards are used with SIST EN IEC 60953-4:2027?
SIST EN IEC 60953-4:2027 is built to be read with IEC 60953-0:2022 and IEC 60953-3:2023.
- IEC 60953-0:2022 provides the base rules for steam turbine thermal acceptance tests and supplies the clauses reused throughout this part.
- IEC 60953-3:2023 supplies the method used for determining uncertainty of performance differences in routine testing.
What does the SIST EN IEC 60953-4:2027 document contain?
The document contains clause-by-clause guidance for routine testing, including definitions, planning rules, measuring techniques, evaluation methods, correction methods, and uncertainty treatment. It also contains figures showing cylinder efficiency, typical instrument layouts, and a sample measuring-points layout.
The annexes add practical material for test selection, component sensitivity, thermodynamic boundaries, uncertainty calculation, and worked examples. Annex I gives a numerical example of calculation and analysis of test results, while Annex J gives a numerical uncertainty example for periodic routine tests.
Several tables support interpretation of results, including leakage apportionment, component sensitivity tables, and example calculation tables. In practice, these parts are used for routine performance monitoring, testing, diagnosis, and report preparation.
Relations
- Effective Date
- 20-Oct-2026
- Effective Date
- 10-Nov-2026
Get Certified
Connect with accredited certification bodies for this standard

DNV
DNV is an independent assurance and risk management provider.

Lloyd's Register
Lloyd's Register is a global professional services organisation specialising in engineering and technology.

DNV Energy Systems
Energy and renewable energy certification.
Sponsored listings
Frequently Asked Questions
SIST EN IEC 60953-4:2027 is a standard published by the Slovenian Institute for Standardization (SIST). Its full title is "Rules for steam turbine thermal acceptance tests - Part 4: Routine testing (IEC 60953-4:2026)". This standard covers: This part of IEC 60953 establishes a Supplementary Standard for routine testing of steam turbines. The rules given in this document follow the guidance given in IEC 60953-0, but contain amendments and supplements regarding the analysis and supervision of relative performance by routine testing of steam turbine. General principles for the preparation, performance evaluation, trends of performance parameters and the determination of the measurement uncertainty of periodic routine tests are given in this document. This document is applicable to routine testing covering a wide range of accuracy on steam turbines of every type, rating and application, operating with superheated or saturated steam. This document is not intended for application in acceptance tests of new units or retrofits and its application for such is strongly not recommended.
This part of IEC 60953 establishes a Supplementary Standard for routine testing of steam turbines. The rules given in this document follow the guidance given in IEC 60953-0, but contain amendments and supplements regarding the analysis and supervision of relative performance by routine testing of steam turbine. General principles for the preparation, performance evaluation, trends of performance parameters and the determination of the measurement uncertainty of periodic routine tests are given in this document. This document is applicable to routine testing covering a wide range of accuracy on steam turbines of every type, rating and application, operating with superheated or saturated steam. This document is not intended for application in acceptance tests of new units or retrofits and its application for such is strongly not recommended.
SIST EN IEC 60953-4:2027 is classified under the following ICS (International Classification for Standards) categories: 27.040 - Gas and steam turbines. Steam engines. The ICS classification helps identify the subject area and facilitates finding related standards.
SIST EN IEC 60953-4:2027 has the following relationships with other standards: It is inter standard links to SIST EN IEC 60953-0:2022, SIST EN IEC 60045-1:2020. Understanding these relationships helps ensure you are using the most current and applicable version of the standard.
SIST EN IEC 60953-4:2027 is available in PDF format for immediate download after purchase. The document can be added to your cart and obtained through the secure checkout process. Digital delivery ensures instant access to the complete standard document.
Standards Content (Sample)
SLOVENSKI STANDARD
01-januar-2027
Pravila za preskuse toplotne sprejemljivosti parne turbine - 4. del: Rutinsko
preskušanje (IEC 60953-4:2026)
Rules for steam turbine thermal acceptance tests - Part 4: Routine testing (IEC 60953-
4:2026)
Regeln für thermische Abnahmeprüfungen von Dampfturbinen – Teil 4: Routine Tests
(IEC 60953-4:2026)
Règles pour les essais thermiques de réception des turbines à vapeur - Partie 4: Essais
individuels de série (IEC 60953-4:2026)
Ta slovenski standard je istoveten z: EN IEC 60953-4:2026
ICS:
27.040 Plinske in parne turbine. Gas and steam turbines.
Parni stroji Steam engines
2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.
EUROPEAN STANDARD EN IEC 60953-4
NORME EUROPÉENNE
EUROPÄISCHE NORM November 2026
ICS 27.040
English Version
Rules for steam turbine thermal acceptance tests - Part 4:
Routine testing
(IEC 60953-4:2026)
Règles pour les essais thermiques de réception des Regeln für thermische Abnahmeprüfungen von
turbines à vapeur - Partie 4: Essais individuels de série Dampfturbinen - Teil 4: Routine Tests
(IEC 60953-4:2026) (IEC 60953-4:2026)
This European Standard was approved by CENELEC on 2026-10-27. CENELEC members are bound to comply with the CEN/CENELEC
Internal Regulations which stipulate the conditions for giving this European Standard the status of a national standard without any alteration.
Up-to-date lists and bibliographical references concerning such national standards may be obtained on application to the CEN-CENELEC
Management Centre or to any CENELEC member.
This European Standard exists in three official versions (English, French, German). A version in any other language made by translation
under the responsibility of a CENELEC member into its own language and notified to the CEN-CENELEC Management Centre has the
same status as the official versions.
CENELEC members are the national electrotechnical committees of Austria, Belgium, Bulgaria, Croatia, Cyprus, the Czech Republic,
Denmark, Estonia, Finland, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta, the
Netherlands, Norway, Poland, Portugal, Republic of North Macedonia, Romania, Serbia, Slovakia, Slovenia, Spain, Sweden, Switzerland,
Türkiye and the United Kingdom.
European Committee for Electrotechnical Standardization
Comité Européen de Normalisation Electrotechnique
Europäisches Komitee für Elektrotechnische Normung
CEN-CENELEC Management Centre: Rue de la Science 23, B-1040 Brussels
© 2026 CENELEC All rights of exploitation in any form and by any means reserved worldwide for CENELEC Members.
Ref. No. EN IEC 60953-4:2026 E
European foreword
The text of document 5/298/FDIS, future edition 1 of IEC 60953-4, prepared by TC 5 "Steam turbines"
was submitted to the IEC-CENELEC parallel vote and approved by CENELEC as EN IEC 60953-
4:2026.
The following dates are fixed:
• latest date by which the document has to be implemented at national (dop) 2027-11-30
level by publication of an identical national standard or by endorsement
• latest date by which the national standards conflicting with the (dow) 2029-11-30
document have to be withdrawn
Attention is drawn to the possibility that some of the elements of this document may be the subject of
patent rights. CENELEC shall not be held responsible for identifying any or all such patent rights.
This document is read in conjunction with EN IEC 60953-0.
Any feedback and questions on this document should be directed to the users’ national committee. A
complete listing of these bodies can be found on the CENELEC website.
Endorsement notice
The text of the International Standard IEC 60953-4:2026 was approved by CENELEC as a European
Standard without any modification.
Annex ZA
(normative)
Normative references to international publications
with their corresponding European publications
The following documents are referred to in the text in such a way that some or all of their content
constitutes requirements of this document. For dated references, only the edition cited applies. For
undated references, the latest edition of the referenced document (including any amendments)
applies.
NOTE 1 Where an International Publication has been modified by common modifications, indicated by (mod),
the relevant EN/HD applies.
NOTE 2 Up-to-date information on the latest versions of the European Standards listed in this annex is available
here: www.cencenelec.eu.
Annex ZA of EN IEC 60953-0:2022, applies, except as follows:
Addition:
Publication Year Title EN/HD Year
IEC 60953-0 2022 Rules for steam turbine thermal EN IEC 60953-0 2022
acceptance tests - Part 0: Wide range of
accuracy for various types and sizes of
turbines
IEC 60953-4 ®
Edition 1.0 2026-09
INTERNATIONAL
STANDARD
Rules for steam turbine thermal acceptance tests -
Part 4: Routine testing
ICS 27.040 ISBN 978-2-8327-1491-1
IEC 60953-4:2026-09(en)
IEC 60953-4:2026 © IEC 2026
CONTENTS
FOREWORD. 7
INTRODUCTION . 9
1 Scope . 11
1.1 General . 11
1.2 Object . 11
1.3 Matter to be considered in the contract . 12
2 Normative references . 12
3 Units, symbols, terms and definitions . 12
3.1 General . 12
3.2 Symbols, units . 12
3.3 Subscripts, superscripts and definitions . 12
3.4 Definition of guarantee values and test results . 13
3.4.1 Guidance on guarantee parameters . 13
3.4.2 Thermal efficiency . 13
3.4.3 Heat rate . 13
3.4.4 Thermodynamic efficiency . 13
3.4.5 Steam rate . 13
3.4.6 Main steam flow capacity . 14
3.4.7 Power output . 14
3.4.8 Guarantee values for extraction and mixed-pressure turbines . 14
3.4.9 Thermal Load Capacity (for nuclear applications) . 14
3.5 Additional definitions of routine test results . 14
3.5.1 Turbine efficiency – Expansion in superheated region . 14
3.5.2 Turbine efficiency – Expansion in wet region . 15
3.5.3 Flow passing capacity . 15
3.5.4 Corrected turbine stage pressures . 16
3.5.5 Heat rate and power output characteristic . 17
3.5.6 Heat input and power output characteristic . 17
3.5.7 Component performance . 17
4 Guiding principles . 19
4.1 Advance planning for test . 19
4.2 Preparatory agreements and arrangements for tests . 20
4.3 Planning of the test . 20
4.3.1 Time for acceptance tests . 20
4.3.2 Direction of acceptance tests . 20
4.4 Preparation of the tests . 20
4.4.1 Condition of the plant . 20
4.4.2 Condition of the steam turbine . 21
4.4.3 Condition of the condenser . 21
4.4.4 Isolation of the cycle . 21
4.4.5 Checks for leakage of condenser and feed water heaters . 21
4.4.6 Cleanliness of the steam strainers . 21
4.4.7 Checking of the test measuring equipment . 22
4.5 Comparison measurements . 22
4.6 Settings for tests . 22
4.6.1 Load settings . 22
4.6.2 Special settings . 22
IEC 60953-4:2026 © IEC 2026
4.7 Preliminary tests . 22
4.8 Acceptance tests . 22
4.8.1 Constancy of test conditions . 22
4.8.2 Maximum deviation and fluctuation in test conditions . 22
4.8.3 Duration of test runs and frequency of reading . 22
4.8.4 Reading of integrating measuring instruments . 22
4.8.5 Alternative methods . 22
4.8.6 Recording of tests . 22
4.8.7 Additional measurement . 22
4.8.8 Preliminary calculations . 23
4.8.9 Consistency and number of tests . 23
4.9 Repetition of acceptance tests . 23
5 Measuring techniques and measuring instruments . 23
5.1 Overview . 23
5.1.1 Instrument accuracy requirements . 23
5.1.2 Measuring instruments . 23
5.1.3 Measuring uncertainty . 23
5.1.4 Calibration of instruments . 23
5.1.5 Alternative instrumentation . 23
5.1.6 Consistency of comparative test instruments . 23
5.1.7 Special considerations of permanently installed instrument . 24
5.2 Measurement of power . 24
5.2.1 Determination of mechanical turbine output . 24
5.2.2 Measurement of boiler feed pump power . 24
5.2.3 Determination of electrical power of a turbine generator . 24
5.2.4 Measurement of electrical power . 24
5.2.5 Electrical instrument connections . 24
5.2.6 Electrical instruments . 25
5.2.7 Instrument transformers . 25
5.3 Flow measurement . 25
5.3.1 Determination of flows to be measured . 25
5.3.2 Measurement of primary flow . 28
5.3.3 Installation and location of flow measuring devices . 28
5.3.4 Calibration of primary flow devices for water flow . 28
5.3.5 Inspection of flow measuring devices . 29
5.3.6 Differential pressure measurements . 29
5.3.7 Water flow fluctuation . 29
5.3.8 Secondary flow measurements . 29
5.3.9 Occasional secondary flows . 30
5.3.10 Density of water and steam . 30
5.3.11 Determination of cooling water flow of condenser . 30
5.4 Pressure measurement (excluding condensing turbine exhaust pressure) . 30
5.4.1 Pressures to be measured . 30
5.4.2 Instruments . 31
5.4.3 Main pressure measurements . 31
5.4.4 Pressure tapping holes and connecting lines . 31
5.4.5 Shut-off valves . 31
5.4.6 Calibration of pressure measuring devices . 31
5.4.7 Atmospheric pressure . 31
IEC 60953-4:2026 © IEC 2026
5.4.8 Correction of readings . 31
5.5 Condensing turbine exhaust pressure measurement . 32
5.5.1 General . 32
5.5.2 Plane of measurement . 32
5.5.3 Pressure taps . 32
5.5.4 Manifolds . 32
5.5.5 Connecting lines . 32
5.5.6 Instruments . 32
5.5.7 Calibration . 32
5.6 Temperature measurement . 32
5.6.1 Points of temperature measurement . 32
5.6.2 Instruments . 32
5.6.3 Main temperature measurements . 32
5.6.4 Feed train temperature measurements (including bled steam) . 32
5.6.5 Condenser cooling water temperature measurement . 32
5.6.6 Thermometer wells . 32
5.6.7 Precautions to be observed in the measurement of temperature . 33
5.7 Steam quality determination . 33
5.7.1 General . 33
5.7.2 Tracer technique . 33
5.7.3 Condensing method . 33
5.7.4 Constant rate injection method . 33
5.7.5 Extraction enthalpy determined by constant rate injection method . 33
5.7.6 Tracers and their use . 33
5.8 Time measurement . 33
5.9 Speed measurement . 34
6 Evaluation of tests . 34
6.1 Preparation of evaluation. 34
6.2 Computation of results . 34
6.2.1 Calculation of average values of instrument readings . 34
6.2.2 Correction and conversion of averaged readings . 34
6.2.3 Checking of measured data . 34
6.2.4 Thermodynamic properties of steam and water . 35
6.2.5 Calculation of test results . 35
7 Correction of test results and comparison with guarantee . 35
7.1 Guarantee values and guarantee conditions . 35
7.2 Correction of initial steam flow capacity . 35
7.3 Correction of output . 35
7.3.1 Correction of maximum output . 35
7.3.2 Correction of output with specified initial steam flow . 35
7.4 Correction of the thermal performance . 36
7.5 Definition and application of correction values . 36
7.6 Correction methods . 36
7.6.1 General . 36
7.6.2 Correction by heat balance calculation . 36
7.6.3 Correction by use of correction curves prepared by the manufacturer . 36
7.6.4 Tests to determine correction values . 36
7.7 Variables to be considered in the correction of specific turbine cycles . 36
7.7.1 Scope of corrections . 36
IEC 60953-4:2026 © IEC 2026
7.7.2 Turbines with regenerative feed-water heating . 37
7.7.3 Turbines which have no provision for the addition or extraction of steam
after partial expansion . 38
7.7.4 Turbines with steam extraction for purposes other than feed-water
heating (extraction turbines) . 38
7.7.5 Other types of turbine . 38
7.8 Guarantee comparison . 38
7.8.1 Tolerance and weighting . 38
7.8.2 Guarantee comparison with locus curve . 38
7.8.3 Guarantee comparison with guarantee point . 38
7.8.4 Guarantee comparison for turbines with throttle governing . 38
7.8.5 Guarantee comparison for extraction turbines . 38
7.8.6 Additional consideration for routine test results comparison . 39
7.9 Deterioration of turbine performance (ageing) . 40
7.9.1 Timing to minimise deterioration . 40
7.9.2 Correction with comparison tests . 40
7.9.3 Correction without comparison tests . 40
8 Measuring uncertainty. 41
8.1 General . 41
8.2 Determination of measuring uncertainty of steam and water properties . 41
8.2.1 Pressure . 41
8.2.2 Temperature . 41
8.2.3 Enthalpy and enthalpy difference . 41
8.3 Calculation of measuring uncertainty of output . 41
8.3.1 Electrical measurement . 41
8.3.2 Mechanical measurement . 41
8.3.3 Additional uncertainty allowance because of unsteady load conditions . 41
8.4 Determination of measuring uncertainty of mass flow . 41
8.4.1 Measuring uncertainty of mass flow measurements . 41
8.4.2 Measuring uncertainty of multiple measurements of primary flow . 41
8.4.3 Uncertainty allowance for cycle imperfections . 41
8.5 Calculation of measuring uncertainty of results . 41
8.5.1 General . 41
8.5.2 Measuring uncertainty of thermal efficiency . 41
8.5.3 Measuring uncertainty of thermodynamic efficiency . 42
8.5.4 Uncertainty of corrections . 42
8.5.5 Guiding values for the measuring uncertainty of results . 42
8.5.6 Routine testing uncertainty . 42
8.6 Example uncertainty calculation . 42
Annex A (normative) Feedwater heater leakage and condenser leakage tests . 43
A.1 Feedwater heater leakage tests . 43
A.2 Condenser leakage tests . 43
Annex B (normative) Evaluation of multiple measurements, compatibility . 44
Annex C (normative) Mass flow balances . 45
C.1 Multiple mass balances (normative) . 45
C.2 Flows for further evaluations (informative) . 45
Annex D (informative) Short-statistical definition of measuring uncertainty and error
propagation in acceptance test . 46
Annex E (informative) Temperature variation method . 47
IEC 60953-4:2026 © IEC 2026
E.1 Description of the problem . 47
E.2 Possibility to determine the leakage flow. 47
E.3 Applied example . 47
Annex F (normative) Measuring uncertainty of results – routine test application . 48
Annex G (informative) Guidance on selection of type of routine test to be performed . 51
G.1 General . 51
G.2 Routine monitoring . 51
G.2.1 Components performance (cylinder, Heater, deaerator, condenser,
pump and BFP turbine, system leakage) . 51
G.2.2 Output monitoring . 51
G.2.3 Flow capacity monitoring . 51
G.2.4 Turbine stage pressure and temperature profiles . 52
G.3 Periodical performance tests . 52
G.3.1 Maximum power test . 52
G.3.2 Steam rate test . 52
G.3.3 Thermal efficiency test (heat rate) . 52
G.3.4 Turbine efficiency test (enthalpy drop test) . 52
G.3.5 Measurement of heat input to cycle . 53
G.3.6 Measurement of heat rejected from cycle . 53
Annex H (informative) Sensitivity factors for some component performance on overall
cycle performance . 54
H.1 General . 54
H.2 Large reheat fossil cycle . 54
H.3 Small industrial back pressure turbine with extraction . 54
H.4 Combined cycle condensing turbine with injection . 55
Annex I (informative) Typical thermodynamic boundary and instrument layout for
routine tests . 56
I.1 General . 56
I.2 Typical thermodynamic boundary and instrument layouts . 56
Annex J (informative) Calculation and analysis of test results – Numerical example . 59
J.1 Overview . 59
J.2 General . 59
J.3 Instrumentation . 60
J.4 Measuring points layout. 62
J.5 Conduct of the test . 63
J.6 Calculation and Interpretation of test results . 64
J.6.1 Corrections and main test results for turbine . 64
J.6.2 Heat rate diagnosis . 66
J.6.3 Flow capacity and power output . 67
J.6.4 HP/IP turbine efficiency . 67
J.6.5 HP Heaters performance . 68
J.6.6 System leakage status . 69
Annex K (informative) Numerical example of routine testing uncertainty calculation
(fossil) . 70
K.1 General . 70
K.2 Measurement uncertainty . 70
K.3 Uncertainty calculation results . 71
Bibliography . 76
IEC 60953-4:2026 © IEC 2026
Figure 1 – Isentropic efficiency of turbine . 14
Figure 2 – Diagram showing location and type of test instrumentation for a typical
periodical thermal efficiency test (condensate flow as primary flow) . 26
Figure 3 – Diagram showing location and type of test instrumentation for a typical
periodical thermal efficiency test (final feedwater flow as primary flow) . 27
Figure I.1 – Example 1 . 56
Figure I.2 – Example 2 . 57
Figure I.3 – Example 3 . 57
Figure I.4 – Example 4 . 58
Figure J.1 – Measuring points layout . 63
Figure J.2 – Corrected heat rate vs. power output relationship curve . 67
Figure K.1 – Original heat balance diagram . 72
Table 1 – Apportionment of unaccounted leakages . 35
Table H.1 – Sensitivity of component performance on overall cycle performance for a
typical reheat fossil cycle . 54
Table H.2 – Sensitivity of components on overall cycle performance for a typical co-
generating unit. 55
Table H.3 – Sensitivity of components on overall cycle performance for a CCGT
turbine unit . 55
Table J.1 – Turbine technical specifications . 59
Table J.2 – Instrumentation list . 60
Table J.3 – Main test results of 350 MW and VWO condition . 64
Table J.4 – Main test results of partial load conditions . 65
Table J.5 – Heat rate change due to boundary parameters (350 MW, post-outage test) . 66
Table J.6 – Heat rate change due to component performance (350 MW,
post-outage test) . 66
Table J.7 – Heaters performance results . 68
Table K.1 – Assumed total measured variable uncertainty . 70
Table K.2 – The uncertainty result for Heat Rate difference of a fossil fired plant . 73
IEC 60953-4:2026 © IEC 2026
INTERNATIONAL ELECTROTECHNICAL COMMISSION
____________
Rules for steam turbine thermal acceptance tests -
Part 4: Routine testing
FOREWORD
1) The International Electrotechnical Commission (IEC) is a worldwide organization for standardization comprising
all national electrotechnical committees (IEC National Committees). The object of IEC is to promote international
co-operation on all questions concerning standardization in the electrical and electronic fields. To this end and
in addition to other activities, IEC publishes International Standards, Technical Specifications, Technical Reports,
Publicly Available Specifications (PAS) and Guides (hereafter referred to as "IEC Publication(s)"). Their
preparation is entrusted to technical committees; any IEC National Committee interested in the subject dealt with
may participate in this preparatory work. International, governmental and non-governmental organizations liaising
with the IEC also participate in this preparation. IEC collaborates closely with the International Organization for
Standardization (ISO) in accordance with conditions determined by agreement between the two organizations.
2) The formal decisions or agreements of IEC on technical matters express, as nearly as possible, an international
consensus of opinion on the relevant subjects since each technical committee has representation from all
interested IEC National Committees.
3) IEC Publications have the form of recommendations for international use and are accepted by IEC National
Committees in that sense. While all reasonable efforts are made to ensure that the technical content of IEC
Publications is accurate, IEC cannot be held responsible for the way in which they are used or for any
misinterpretation by any end user.
4) In order to promote international uniformity, IEC National Committees undertake to apply IEC Publications
transparently to the maximum extent possible in their national and regional publications. Any divergence between
any IEC Publication and the corresponding national or regional publication shall be clearly indicated in the latter.
5) IEC itself does not provide any attestation of conformity. Independent certification bodies provide conformity
assessment services and, in some areas, access to IEC marks of conformity. IEC is not responsible for any
services carried out by independent certification bodies.
6) All users should ensure that they have the latest edition of this publication.
7) No liability shall attach to IEC or its directors, employees, servants or agents including individual experts and
members of its technical committees and IEC National Committees for any personal injury, property damage or
other damage of any nature whatsoever, whether direct or indirect, or for costs (including legal fees) and
expenses arising out of the publication, use of, or reliance upon, this IEC Publication or any other IEC
Publications.
8) Attention is drawn to the Normative references cited in this publication. Use of the referenced publications is
indispensable for the correct application of this publication.
9) IEC draws attention to the possibility that the implementation of this document may involve the use of (a)
patent(s). IEC takes no position concerning the evidence, validity or applicability of any claimed patent rights in
respect thereof. As of the date of publication of this document, IEC [had/had not] received notice of (a) patent(s),
which may be required to implement this document. However, implementers are cautioned that this may not
represent the latest information, which may be obtained from the patent database available at
https://patents.iec.ch. IEC shall not be held responsible for identifying any or all such patent rights.
IEC 60953-4 has been prepared by IEC technical committee 5: Steam Turbines. It is an
International Standard.
The text of this International Standard is based on the following documents:
Draft Report on voting
5/298/FDIS 5/302/RVD
Full information on the voting for its approval can be found in the report on voting indicated in
the above table.
The language used for the development of this International Standard is English.
IEC 60953-4:2026 © IEC 2026
This document was drafted in accordance with ISO/IEC Directives, Part 2, and developed in
accordance with ISO/IEC Directives, Part 1 and ISO/IEC Directives, IEC Supplement, available
at www.iec.ch/members_experts/refdocs. The main document types developed by IEC are
described in greater detail at www.iec.ch/publications.
This part of IEC 60953 is to be read in conjunction with IEC 60953-0, and the words 'routine
test' are to be read in place of 'acceptance test', the words' reference conditions' are to be read
in place of 'guarantee conditions', and the words 'reference value' are to be read in place of
'guarantee value'. IEC 60953-0 is taken as a reference standard.
A list of all parts in the IEC 60953 series, published under the general title Rules for steam
turbine thermal acceptance tests, can be found on the IEC website.
The committee has decided that the contents of this document will remain unchanged until the
stability date indicated on the IEC website under webstore.iec.ch in the data related to the
specific document. At this date, the document will be
– reconfirmed,
– withdrawn, or
– revised.
IEC 60953-4:2026 © IEC 2026
INTRODUCTION
Routine test in an existing power plant mainly involves an analysis, monitoring and supervision
of steam turbine performance. IEC 60953-0, which defines the rules for steam turbine thermal
acceptance tests in power plants, does not cater for all the requirements specific to routine test.
It was considered necessary to draw up a Supplementary Standard (this document) for guidance
on the routine tests of existing steam turbines.
However, a large number of the provisions and recommendations of IEC 60953-0 are still
applicable to routine tests and, therefore, in order to avoid a repetitive and bulky document,
only the routine-specific addenda will be found in this document.
Although this document is intended to apply to the routine test of large condensing steam
turbines, it can nevertheless be used for other types and sizes of turbines to define the basis
of a specific procedure to be agreed upon by the parties involved.
The purpose of this document is to cover the existing steam turbine components which influence
the efficiency of the power plant. This document helps the parties determine the most
appropriate parameters that characterize the relative performance change and that could be
used as long-term performance monitoring and analysis.
The relative performance rather than absolute value is emphasized in this document. The
repeatability of test results rather than absolute test uncertainty is emphasized. In addition,
depending on the type of test and thermodynamic boundary chosen, the full condition of each
component might not be known. In some cases, as per the result of routine test, full or further
diagnostic test may be needed.
For reference purposes only, a numerical sample calculation and analysis of a fossil steam
turbine unit is presented in Annex J.
The structure and clause numbering of this document follow that of IEC 60953-0. Subclauses
found in this document supersede the whole of the equivalent subclause in IEC 60953-0.
Subclause numbering has been extended whenever new items have been included.
The main differences between this document and IEC 60953-0 are listed below:
– Clause 1: Scope
This document gives additional clauses for routine tests of steam turbines, regarding the
analysis and supervision of relative performance by routine testing.
General principles and the determination of the measurement uncertainty of periodic routine
tests are given.
The purpose of this document is to provide a simple and economic test procedures guide
for long-term and relative performance of turbines a
...