Commissioning of electrical, instrumentation and control systems in the process industry - Specific phases and milestones

IEC 62337:2006 defines specific phases and milestones in the commissioning of electrical, instrumentation and control systems in the process industry. By way of example, it describes activities following the "completion-of-erection" milestone of the project and prior to the "acceptance-of-the-plant" phase by the owner. Such activities need to be adapted for each type of process/plant concerned. This bilingual version (2013-05) corresponds to the monolingual English version, published in 2006-11. It cancels and replaces IEC/PAS 62337 published in 2002. This first edition constitutes a technical revision.

Mise en service des systèmes électriques, de mesure et de commande dans l'industrie de transformation - Phases et jalons spécifiques

La CEI 62337:2006 définit des phases et des jalons spécifiques pour la mise en service des systèmes électriques, de mesure et de commande, utilisés dans l'industrie de transformation. Elle décrit, à titre d'exemple, les activités qui suivent le jalon "achèvement du montage" du projet mais préalables à la phase "de réception de l'ensemble industriel" par le maître d'ouvrage. Il est nécessaire d'adapter ces activités à chaque type de processus/ensemble industriel concerné. La présente norme annule et remplace le CEI/PAS 62337 publié en 2002. Cette première édition constitue une révision technique. La présente version bilingue (2013-05) correspond à la version anglaise monolingue publiée en 2006-11.

General Information

Status
Published
Publication Date
07-Nov-2006
Current Stage
DELPUB - Deleted Publication
Completion Date
22-Feb-2012
Ref Project

Relations

Buy Standard

Standard
IEC 62337:2006 - Commissioning of electrical, instrumentation and control systems in the process industry - Specific phases and milestones Released:11/8/2006 Isbn:2831888808
English language
30 pages
sale 15% off
Preview
sale 15% off
Preview
Standard
IEC 62337:2006 - Commissioning of electrical, instrumentation and control systems in the process industry - Specific phases and milestones Released:11/8/2006 Isbn:9782832207192
English and French language
68 pages
sale 15% off
Preview
sale 15% off
Preview

Standards Content (Sample)


INTERNATIONAL IEC
STANDARD 62337
First edition
2006-11
Commissioning of electrical, instrumentation and
control systems in the process industry – Specific
phases and milestones
Reference number
Publication numbering
As from 1 January 1997 all IEC publications are issued with a designation in the
60000 series. For example, IEC 34-1 is now referred to as IEC 60034-1.
Consolidated editions
The IEC is now publishing consolidated versions of its publications. For example,
edition numbers 1.0, 1.1 and 1.2 refer, respectively, to the base publication, the
base publication incorporating amendment 1 and the base publication incorporating
amendments 1 and 2.
Further information on IEC publications
The technical content of IEC publications is kept under constant review by the IEC,
thus ensuring that the content reflects current technology. Information relating to
this publication, including its validity, is available in the IEC Catalogue of
publications (see below) in addition to new editions, amendments and corrigenda.
Information on the subjects under consideration and work in progress undertaken
by the technical committee which has prepared this publication, as well as the list
of publications issued, is also available from the following:
• IEC Web Site (www.iec.ch)
• Catalogue of IEC publications
The on-line catalogue on the IEC web site (www.iec.ch/searchpub) enables you to
search by a variety of criteria including text searches, technical committees
and date of publication. On-line information is also available on recently issued
publications, withdrawn and replaced publications, as well as corrigenda.
• IEC Just Published
This summary of recently issued publications (www.iec.ch/online_news/ justpub)
is also available by email. Please contact the Customer Service Centre (see
below) for further information.
• Customer Service Centre
If you have any questions regarding this publication or need further assistance,
please contact the Customer Service Centre:

Email: custserv@iec.ch
Tel: +41 22 919 02 11
Fax: +41 22 919 03 00
INTERNATIONAL IEC
STANDARD 62337
First edition
2006-11
Commissioning of electrical, instrumentation and
control systems in the process industry – Specific
phases and milestones
© IEC 2006 ⎯ Copyright - all rights reserved
No part of this publication may be reproduced or utilized in any form or by any means, electronic or
mechanical, including photocopying and microfilm, without permission in writing from the publisher.
International Electrotechnical Commission, 3, rue de Varembé, PO Box 131, CH-1211 Geneva 20, Switzerland
Telephone: +41 22 919 02 11 Telefax: +41 22 919 03 00 E-mail: inmail@iec.ch Web: www.iec.ch
PRICE CODE
Commission Electrotechnique Internationale U
International Electrotechnical Commission
МеждународнаяЭлектротехническаяКомиссия
For price, see current catalogue

– 2 – 62337 © IEC:2006(E)
CONTENTS
FOREWORD.3
INTRODUCTION.5

1 Scope.6
2 Terms and definitions .6
3 General preparations before acceptance of plant.8
4 Completion of erection.8
4.1 Mechanical checks and tests .8
4.2 Procedure .9
5 Precommissioning (mechanical completion) .9
5.1 General .9
5.2 Procedure .9
6 Commissioning.10
6.1 General .10
6.2 Procedure .10
7 Performance test and acceptance of plant .11
7.1 General .11
7.2 Conditions for commencement of performance test .12
7.3 Execution of performance test .12
7.4 Evaluation and report of performance test .13

Annex A (informative) List of documents to be used for the precommissioning and
commissioning phase.14
Annex B (informative) Description of precommissioning activities .15
Annex C (informative) Mechanical completion certificate.26
Annex D (informative) Description of commissioning activities .27
Annex E (informative ) Acceptance of plant certificate .29
Annex F (informative) Project-specific items .30

62337 © IEC:2006(E) – 3 –
INTERNATIONAL ELECTROTECHNICAL COMMISSION
____________
COMMISSIONING OF ELECTRICAL, INSTRUMENTATION AND CONTROL
SYSTEMS IN THE PROCESS INDUSTRY – SPECIFIC PHASES AND
MILESTONES
FOREWORD
1) The International Electrotechnical Commission (IEC) is a worldwide organization for standardization comprising
all national electrotechnical committees (IEC National Committees). The object of IEC is to promote
international co-operation on all questions concerning standardization in the electrical and electronic fields. To
this end and in addition to other activities, IEC publishes International Standards, Technical Specifications,
Technical Reports, Publicly Available Specifications (PAS) and Guides (hereafter referred to as “IEC
Publication(s)”). Their preparation is entrusted to technical committees; any IEC National Committee interested
in the subject dealt with may participate in this preparatory work. International, governmental and non-
governmental organizations liaising with the IEC also participate in this preparation. IEC collaborates closely
with the International Organization for Standardization (ISO) in accordance with conditions determined by
agreement between the two organizations.
2) The formal decisions or agreements of IEC on technical matters express, as nearly as possible, an international
consensus of opinion on the relevant subjects since each technical committee has representation from all
interested IEC National Committees.
3) IEC Publications have the form of recommendations for international use and are accepted by IEC National
Committees in that sense. While all reasonable efforts are made to ensure that the technical content of IEC
Publications is accurate, IEC cannot be held responsible for the way in which they are used or for any
misinterpretation by any end user.
4) In order to promote international uniformity, IEC National Committees undertake to apply IEC Publications
transparently to the maximum extent possible in their national and regional publications. Any divergence
between any IEC Publication and the corresponding national or regional publication shall be clearly indicated in
the latter.
5) IEC provides no marking procedure to indicate its approval and cannot be rendered responsible for any
equipment declared to be in conformity with an IEC Publication.
6) All users should ensure that they have the latest edition of this publication.
7) No liability shall attach to IEC or its directors, employees, servants or agents including individual experts and
members of its technical committees and IEC National Committees for any personal injury, property damage or
other damage of any nature whatsoever, whether direct or indirect, or for costs (including legal fees) and
expenses arising out of the publication, use of, or reliance upon, this IEC Publication or any other IEC
Publications.
8) Attention is drawn to the Normative references cited in this publication. Use of the referenced publications is
indispensable for the correct application of this publication.
9) Attention is drawn to the possibility that some of the elements of this IEC Publication may be the subject of
patent rights. IEC shall not be held responsible for identifying any or all such patent rights.
International Standard IEC 62337 has been prepared by IEC technical committee 65:
Industrial-process measurement and control.
This standard cancels and replaces IEC/PAS 62337 published in 2002. This first edition
constitutes a technical revision.
The text of this standard is based on the following documents:
FDIS Report on voting
65/384/FDIS 65/390/RVD
Full information on the voting for the approval of this standard can be found in the report on
voting indicated in the above table.
This publication has been drafted in accordance with the ISO/IEC Directives, Part 2.

– 4 – 62337 © IEC:2006(E)
The committee has decided that the contents of this publication will remain unchanged until
the maintenance result date indicated on the IEC web site under "http://webstore.iec.ch" in
the data related to the specific publication. At this date, the publication will be
• reconfirmed,
• withdrawn,
• replaced by a revised edition, or
• amended.
A bilingual version of this publication may be issued at a later date.

62337 © IEC:2006(E) – 5 –
INTRODUCTION
There is an increasing trend in the process industry to award the construction of whole plants
to contractors on a lump-sum turnkey or similar commercial basis. Experience has shown that
both the process industry (hereinafter called “the owner”) and the contractor have long and
expensive discussions to lay down unambiguously the scope of activities to be taken by the
contractor and the owner and their responsibilities to achieve the handover of the plant.
This standard should lead to an improvement and acceleration of the negotiation phase and to
a mutual understanding about the scope of activities of each party.
For application in the pharmaceutical or other highly specialized industries, additional
guidelines (for example, Good Automated Manufacturing Practice (GAMP)), definitions and
stipulations should apply in accordance with existing standards, for example, for GMP
Compliance 21 CFR (FDA) and the Standard Operating Procedure of the European Medicines
Agency (SOP/INSP/2003).
– 6 – 62337 © IEC:2006(E)
COMMISSIONING OF ELECTRICAL, INSTRUMENTATION
AND CONTROL SYSTEMS IN THE PROCESS INDUSTRY –
SPECIFIC PHASES AND MILESTONES

1 Scope
This International Standard defines specific phases and milestones (see Figure 1) in the
commissioning of electrical, instrumentation and control systems in the process industry. By
way of example, it describes activities following the “completion-of-erection” milestone of the
project and prior to the “acceptance-of-the-plant” phase by the owner. Such activities need to
be adapted for each type of process/plant concerned.
NOTE This standard assumes that the “acceptance-of-the-plant” milestone will occur after the performance test. If
there is a reduced scope, this document should be adapted accordingly.
Acceptance
of plant
Construction Precommissioning Commissioning Production
PHASES
Cold Hot
Completion of Mechanical          Start-up Start of
MILESTONES
erection completion production Performance
test
IEC  1985/06
NOTE Construction and precommissioning activities could be overlapping.
Figure 1 – Definition of phases and milestones
2 Terms and definitions
For the purposes of this document, the following terms and definitions apply.
2.1
precommissioning
phase during which the activities of non-operating adjustments, cold alignment checks,
cleaning, and testing of machinery take place
NOTE Refer to Annex B for the detailed activities.
2.2
mechanical completion
milestone which is achieved when the plant, or any part thereof, has been erected and tested
in accordance with drawings, specifications, instructions, and applicable codes and
regulations to the extent necessary to permit cold commissioning
NOTE This includes completion of all necessary electrical and instrumentation work. This is a milestone marking
the end of the precommissioning activities.
2.3
cold commissioning
phase during which the activities associated with the testing and operation of equipment or
facilities using test media such as water or inert substances, prior to introducing any chemical
in the system, take place
62337 © IEC:2006(E) – 7 –
2.4
start-up
milestone marking the end of cold commissioning
NOTE At this stage, the operating range of every instrument loop should already be adjusted to reflect the actual
working condition.
2.5
hot commissioning
phase during which the activities associated with the testing and operation of equipment or
facilities using the actual process chemical, prior to making an actual production run, take
place
2.6
start of production
milestone marking the end of hot commissioning
NOTE At this stage, the plant is ready for full and continuous operation.
2.7
performance test
milestone at which time the production plant runs to its design capacity
NOTE This test, carried out by the owner’s personnel with the help and supervision of the contractor, serves to
demonstrate the contractor’s p
...


IEC 62337 ®
Edition 1.0 2006-11
INTERNATIONAL
STANDARD
NORME
INTERNATIONALE
Commissioning of electrical, instrumentation and control systems in the
process industry – Specific phases and milestones

Mise en service des systèmes électriques, de mesure et de commande dans
l'industrie de transformation – Phases et jalons spécifiques

All rights reserved. Unless otherwise specified, no part of this publication may be reproduced or utilized in any form
or by any means, electronic or mechanical, including photocopying and microfilm, without permission in writing from
either IEC or IEC's member National Committee in the country of the requester.
If you have any questions about IEC copyright or have an enquiry about obtaining additional rights to this publication,
please contact the address below or your local IEC member National Committee for further information.

Droits de reproduction réservés. Sauf indication contraire, aucune partie de cette publication ne peut être reproduite ni
utilisée sous quelque forme que ce soit et par aucun procédé, électronique ou mécanique, y compris la photocopie et les
microfilms, sans l'accord écrit de la CEI ou du Comité national de la CEI du pays du demandeur.
Si vous avez des questions sur le copyright de la CEI ou si vous désirez obtenir des droits supplémentaires sur cette
publication, utilisez les coordonnées ci-après ou contactez le Comité national de la CEI de votre pays de résidence.

IEC Central Office Tel.: +41 22 919 02 11
3, rue de Varembé Fax: +41 22 919 03 00
CH-1211 Geneva 20 info@iec.ch
Switzerland www.iec.ch
About the IEC
The International Electrotechnical Commission (IEC) is the leading global organization that prepares and publishes
International Standards for all electrical, electronic and related technologies.

About IEC publications
The technical content of IEC publications is kept under constant review by the IEC. Please make sure that you have the
latest edition, a corrigenda or an amendment might have been published.

Useful links:
IEC publications search - www.iec.ch/searchpub Electropedia - www.electropedia.org
The advanced search enables you to find IEC publications The world's leading online dictionary of electronic and
by a variety of criteria (reference number, text, technical electrical terms containing more than 30 000 terms and
committee,…). definitions in English and French, with equivalent terms in
It also gives information on projects, replaced and additional languages. Also known as the International
withdrawn publications. Electrotechnical Vocabulary (IEV) on-line.

IEC Just Published - webstore.iec.ch/justpublished Customer Service Centre - webstore.iec.ch/csc
Stay up to date on all new IEC publications. Just Published If you wish to give us your feedback on this publication
details all new publications released. Available on-line and or need further assistance, please contact the
also once a month by email. Customer Service Centre: csc@iec.ch.

A propos de la CEI
La Commission Electrotechnique Internationale (CEI) est la première organisation mondiale qui élabore et publie des
Normes internationales pour tout ce qui a trait à l'électricité, à l'électronique et aux technologies apparentées.

A propos des publications CEI
Le contenu technique des publications de la CEI est constamment revu. Veuillez vous assurer que vous possédez
l’édition la plus récente, un corrigendum ou amendement peut avoir été publié.

Liens utiles:
Recherche de publications CEI - www.iec.ch/searchpub Electropedia - www.electropedia.org
La recherche avancée vous permet de trouver des Le premier dictionnaire en ligne au monde de termes
publications CEI en utilisant différents critères (numéro de électroniques et électriques. Il contient plus de 30 000
référence, texte, comité d’études,…). termes et définitions en anglais et en français, ainsi que
Elle donne aussi des informations sur les projets et les les termes équivalents dans les langues additionnelles.
publications remplacées ou retirées. Egalement appelé Vocabulaire Electrotechnique
International (VEI) en ligne.
Just Published CEI - webstore.iec.ch/justpublished
Service Clients - webstore.iec.ch/csc
Restez informé sur les nouvelles publications de la CEI.
Just Published détaille les nouvelles publications parues. Si vous désirez nous donner des commentaires sur
Disponible en ligne et aussi une fois par mois par email. cette publication ou si vous avez des questions
contactez-nous: csc@iec.ch.
IEC 62337 ®
Edition 1.0 2006-11
INTERNATIONAL
STANDARD
NORME
INTERNATIONALE
Commissioning of electrical, instrumentation and control systems in the

process industry – Specific phases and milestones

Mise en service des systèmes électriques, de mesure et de commande dans

l'industrie de transformation – Phases et jalons spécifiques

INTERNATIONAL
ELECTROTECHNICAL
COMMISSION
COMMISSION
ELECTROTECHNIQUE
PRICE CODE
INTERNATIONALE
CODE PRIX U
ICS 25.040.40; 91.010; 91.040; 91.140 ISBN 978-2-83220-719-2

– 2 – 62337  IEC:2006
CONTENTS
FOREWORD . 3
INTRODUCTION . 5

1 Scope . 6
2 Terms and definitions . 6
3 General preparations before acceptance of plant . 8
4 Completion of erection . 8
4.1 Mechanical checks and tests . 8
4.2 Procedure . 9
5 Precommissioning (mechanical completion) . 9
5.1 General . 9
5.2 Procedure . 9
6 Commissioning . 10
6.1 General . 10
6.2 Procedure . 10
7 Performance test and acceptance of plant . 11
7.1 General . 11
7.2 Conditions for commencement of performance test . 12
7.3 Execution of performance test . 12
7.4 Evaluation and report of performance test . 13

Annex A (informative) List of documents to be used for the precommissioning and
commissioning phase. 14
Annex B (informative) Description of precommissioning activities . 15
Annex C (informative) Mechanical completion certificate . 26
Annex D (informative) Description of commissioning activities . 27
Annex E (informative ) Acceptance of plant certificate . 29
Annex F (informative) Project-specific items . 30

62337  IEC:2006 – 3 –
INTERNATIONAL ELECTROTECHNICAL COMMISSION
____________
COMMISSIONING OF ELECTRICAL, INSTRUMENTATION
AND CONTROL SYSTEMS IN THE PROCESS INDUSTRY –
SPECIFIC PHASES AND MILESTONES

FOREWORD
1) The International Electrotechnical Commission (IEC) is a worldwide organization for standardization comprising
all national electrotechnical committees (IEC National Committees). The object of IEC is to promote
international co-operation on all questions concerning standardization in the electrical and electronic fields. To
this end and in addition to other activities, IEC publishes International Standards, Technical Specifications,
Technical Reports, Publicly Available Specifications (PAS) and Guides (hereafter referred to as “IEC
Publication(s)”). Their preparation is entrusted to technical committees; any IEC National Committee interested
in the subject dealt with may participate in this preparatory work. International, governmental and non-
governmental organizations liaising with the IEC also participate in this preparation. IEC collaborates closely
with the International Organization for Standardization (ISO) in accordance with conditions determined by
agreement between the two organizations.
2) The formal decisions or agreements of IEC on technical matters express, as nearly as possible, an international
consensus of opinion on the relevant subjects since each technical committee has representation from all
interested IEC National Committees.
3) IEC Publications have the form of recommendations for international use and are accepted by IEC National
Committees in that sense. While all reasonable efforts are made to ensure that the technical content of IEC
Publications is accurate, IEC cannot be held responsible for the way in which they are used or for any
misinterpretation by any end user.
4) In order to promote international uniformity, IEC National Committees undertake to apply IEC Publications
transparently to the maximum extent possible in their national and regional publications. Any divergence
between any IEC Publication and the corresponding national or regional publication shall be clearly indicated in
the latter.
5) IEC provides no marking procedure to indicate its approval and cannot be rendered responsible for any
equipment declared to be in conformity with an IEC Publication.
6) All users should ensure that they have the latest edition of this publication.
7) No liability shall attach to IEC or its directors, employees, servants or agents including individual experts and
members of its technical committees and IEC National Committees for any personal injury, property damage or
other damage of any nature whatsoever, whether direct or indirect, or for costs (including legal fees) and
expenses arising out of the publication, use of, or reliance upon, this IEC Publication or any other IEC
Publications.
8) Attention is drawn to the Normative references cited in this publication. Use of the referenced publications is
indispensable for the correct application of this publication.
9) Attention is drawn to the possibility that some of the elements of this IEC Publication may be the subject of
patent rights. IEC shall not be held responsible for identifying any or all such patent rights.
International Standard IEC 62337 has been prepared by IEC technical committee 65:
Industrial-process measurement and control.
This standard cancels and replaces IEC/PAS 62337 published in 2002. This first edition
constitutes a technical revision.
This bilingual version (2013-05) corresponds to the monolingual English version, published in
2006-11.
The text of this standard is based on the following documents:
FDIS Report on voting
65/384/FDIS 65/390/RVD
Full information on the voting for the approval of this standard can be found in the report on
voting indicated in the above table.

– 4 – 62337  IEC:2006
The French version of this standard has not been voted upon.
This publication has been drafted in accordance with the ISO/IEC Directives, Part 2.
The committee has decided that the contents of this publication will remain unchanged until
the maintenance result date indicated on the IEC web site under "http://webstore.iec.ch" in
the data related to the specific publication. At this date, the publication will be
• reconfirmed,
• withdrawn,
• replaced by a revised edition, or
• amended.
62337  IEC:2006 – 5 –
INTRODUCTION
There is an increasing trend in the process industry to award the construction of whole plants
to contractors on a lump-sum turnkey or similar commercial basis. Experience has shown that
both the process industry (hereinafter called “the owner”) and the contractor have long and
expensive discussions to lay down unambiguously the scope of activities to be taken by the
contractor and the owner and their responsibilities to achieve the handover of the plant.
This standard should lead to an improvement and acceleration of the negotiation phase and to
a mutual understanding about the scope of activities of each party.
For application in the pharmaceutical or other highly specialized industries, additional
guidelines (for example, Good Automated Manufacturing Practice (GAMP)), definitions and
stipulations should apply in accordance with existing standards, for example, for GMP
Compliance 21 CFR (FDA) and the Standard Operating Procedure of the European Medicines
Agency (SOP/INSP/2003).
– 6 – 62337  IEC:2006
COMMISSIONING OF ELECTRICAL, INSTRUMENTATION
AND CONTROL SYSTEMS IN THE PROCESS INDUSTRY –
SPECIFIC PHASES AND MILESTONES

1 Scope
This International Standard defines specific phases and milestones (see Figure 1) i
...

Questions, Comments and Discussion

Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.