EN 45510-8-1:1998
(Main)Guide for procurement of power station equipment - Part 8-1: Control and instrumentation
Guide for procurement of power station equipment - Part 8-1: Control and instrumentation
This standard gives guidance on writing the technical specification for the procurement of Control and Instrumentation (C&I) for use in electricity generating stations (power stations). This Guide for procurement is not applicable to equipment for use in the nuclear reactor plant area of nuclear power stations. Other possible applications of such equipment have not been considered in the preparation of this Guide.
Leitfaden für die Beschaffung von Ausrüstungen für Kraftwerke - Teil 8-1: Leittechnische Einrichtungen
Die vorliegende Norm ist eine Anleitung zur Erstellung der technischen Spezifikation für die Beschaffung von Leittechnik für den Einsatz in Anlagen zur Erzeugung von elektrischer Ernergie (Kraftwerke). Dieser Leitfaden ist nicht anwendbar auf Ausrüstung zur Verwendung im Nuklearbereich von Kernkraftwerken. Bei der Erstellung des Leitfadens wurden keine weiteren Möglichkeiten zur Anwendung der beschriebenen Ausrüstung in Betracht gezogen.
Guide pour l'acquisition d'équipements destinés aux centrales de production d'électricité - Partie 8-1: Contrôle-commande et instrumentation
La présente norme donne des recommandations pour la rédaction de la spécification technique nécessaire à l'acquisition de contrôle-commande et d'instrumentation (C&I) pour les centrales de production d'électricité. Ce guide d'achat n'est pas applicable à ce type d'équipement lorsque celui-ci est destiné à l'ilôt nucléaire des centrale nucléaires. D'autres applications possibles de ce type d'équipement n'ont pas été prises en considération dans la préparation de ce guide.
Vodilo za nabavo opreme elektrarn –8-1. del: Krmiljenje in instrumentacija
General Information
- Status
- Published
- Publication Date
- 17-Mar-1998
- Withdrawal Date
- 29-Sep-1998
- Technical Committee
- CEN/CLC/TC 2 - Power Engineering
- Drafting Committee
- CEN/CLC/JTF PE - Joint Task Force Power Engineering
- Current Stage
- 9060 - Closure of 2 Year Review Enquiry - Review Enquiry
- Start Date
- 02-Sep-2017
- Completion Date
- 02-Sep-2017
Overview
EN 45510-8-1:1998 - published by CEN - is a guidance standard for preparing technical specifications when procuring Control and Instrumentation (C&I) equipment for electricity generating stations. The Guide helps specification writers define requirements for instrumentation, control systems and related procurement documentation used in power stations in general. It explicitly excludes equipment for use in the nuclear reactor plant area of nuclear power stations and does not address other potential applications outside electricity generation.
Key topics
This procurement guide outlines the typical elements to include when specifying C&I for power stations. Key topics covered or recommended by the Guide include:
- Scope and functional requirements for control and instrumentation systems in power stations
- Performance and reliability expectations relevant to plant operation and process control
- Environmental and site conditions (e.g., ambient, humidity, vibration) for equipment selection
- Interfaces and interoperability between control systems, field instruments and plant networks
- Testing and acceptance criteria including factory and site acceptance testing
- Documentation and deliverables (drawings, manuals, software records, calibration certificates)
- Quality assurance and inspection requirements for suppliers and contractors
- Maintenance, spare parts and lifecycle considerations to support long‑term operation
(The Guide provides structure and wording guidance for these topics to produce clear, consistent technical specifications for tenders and procurement.)
Applications
EN 45510-8-1 is practical for organizations involved in specifying or buying C&I for non‑nuclear power plants:
- Procurement engineers and tender writers preparing specifications and contract documents
- Project managers and EPC contractors defining supplier scope and deliverables
- Power plant operators and maintenance teams setting acceptance, testing and lifecycle requirements
- Consultants and system integrators developing functional and technical requirements for control systems
Typical uses include preparing tender documents, evaluating supplier proposals, defining acceptance tests, and ensuring equipment meets operational and environmental needs.
Related standards
- This Guide sits within the EN 45510 series for power station equipment procurement.
- Users should consider relevant national and international standards for instrumentation and control (for example, applicable IEC and CEN standards) and plant‑specific regulatory requirements when preparing final technical specifications.
Keywords: EN 45510-8-1, control and instrumentation, power station procurement, technical specification, power plant instrumentation, C&I specification, power station control systems.
Frequently Asked Questions
EN 45510-8-1:1998 is a standard published by the European Committee for Standardization (CEN). Its full title is "Guide for procurement of power station equipment - Part 8-1: Control and instrumentation". This standard covers: This standard gives guidance on writing the technical specification for the procurement of Control and Instrumentation (C&I) for use in electricity generating stations (power stations). This Guide for procurement is not applicable to equipment for use in the nuclear reactor plant area of nuclear power stations. Other possible applications of such equipment have not been considered in the preparation of this Guide.
This standard gives guidance on writing the technical specification for the procurement of Control and Instrumentation (C&I) for use in electricity generating stations (power stations). This Guide for procurement is not applicable to equipment for use in the nuclear reactor plant area of nuclear power stations. Other possible applications of such equipment have not been considered in the preparation of this Guide.
EN 45510-8-1:1998 is classified under the following ICS (International Classification for Standards) categories: 25.040.40 - Industrial process measurement and control; 27.100 - Power stations in general. The ICS classification helps identify the subject area and facilitates finding related standards.
EN 45510-8-1:1998 is associated with the following European legislation: EU Directives/Regulations: 93/38/EEC; Standardization Mandates: M/BC/CEN/92/10. When a standard is cited in the Official Journal of the European Union, products manufactured in conformity with it benefit from a presumption of conformity with the essential requirements of the corresponding EU directive or regulation.
You can purchase EN 45510-8-1:1998 directly from iTeh Standards. The document is available in PDF format and is delivered instantly after payment. Add the standard to your cart and complete the secure checkout process. iTeh Standards is an authorized distributor of CEN standards.
Standards Content (Sample)
2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.Vodilo za nabavo opreme elektrarn –8-1. del: Krmiljenje in instrumentacijaLeitfaden für die Beschaffung von Ausrüstungen für Kraftwerke - Teil 8-1: Leittechnische EinrichtungenGuide pour l'acquisition d'équipements destinés aux centrales de production d'électricité - Partie 8-1: Contrôle-commande et instrumentationGuide for procurement of power station equipment - Part 8-1: Control and instrumentation27.100Elektrarne na splošnoPower stations in general25.040.40Merjenje in krmiljenje industrijskih postopkovIndustrial process measurement and controlICS:Ta slovenski standard je istoveten z:EN 45510-8-1:1998SIST EN 45510-8-1:1999en01-april-1999SIST EN 45510-8-1:1999SLOVENSKI
STANDARD
S
...










Questions, Comments and Discussion
Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.
Loading comments...