Low-voltage electrical installations - Part 7-712: Requirements for special installations or locations - Photovoltaic (PV) systems

This section applies to the electrical installation of PV generator intended to supply all or part of an installation and feeding of electricity into the public grid or local distribution. In this section, the electrical equipment of a PV generator, like any other item of electrical equipment, is dealt with only so far as its selection and application in the installation is concerned. The electrical installation of a PV generator starts from a PV module or a set of PV modules connected in series with their cables, provided by the PV module manufacturer, up to the user installation or the utility supply point. Requirements of this document apply to – PV generators for supply to an installation which is not connected to a system for distribution of electricity to the public, – PV generators for supply to an installation in parallel with a system for distribution of electricity to the public, – PV generators for supply to an installation as an alternative to a system for distribution of electricity to the public, – appropriate combination of the above. Requirements for PV generators with batteries or other energy storage methods are under consideration.

Errichten von Niederspannungsanlagen - Teil 7-712: Anforderungen für Betriebsstätten, Räume und Anlagen besonderer Art - Photovoltaik-(PV)-Stromversorgungssysteme

Installations électriques basses tensions - Partie 7-712: Exigences pour les installations et emplacements spéciaux – Systèmes photovoltaïques (PV)

Nizkonapetostne električne inštalacije - 7-712. del: Zahteve za posebne inštalacije ali lokacije - Fotonapetostni (PV) sistemi

Ta razdelek se uporablja za električno inštalacijo fotonapetostnega generatorja za napajanje celotne napeljave (ali njenega dela)
in prenos elektrike v javno omrežje ali lokalno distribucijo.
V tem razdelku je električna oprema fotonapetostnega generatorja (kot kateri koli drugi del električne opreme)
zajeta le toliko, kolikor je to povezano z njeno izbiro in uporabo v inštalaciji.
Električna inštalacija fotonapetostnega generatorja se začne pri fotonapetostnem modulu ali naboru zaporednih fotonapetostnih modulov s kabli, ki ga/jih zagotovi proizvajalec fotonapetostnih modulov, vse do uporabniške inštalacije ali točke oskrbe z napajanjem.
Zahteve tega dokumenta se uporabljajo za:
– fotonapetostne generatorje za napajanje inštalacije, ki ni povezana s sistemom za distribucijo električne energije v javnih omrežjih;
– fotonapetostne generatorje za napajanje inštalacije, vzporedno povezane s sistemom za distribucijo električne energije v javnih omrežjih;
– fotonapetostne generatorje za napajanje inštalacije kot alternative sistemu za distribucijo električne energije v javnih omrežjih;
– ustrezno kombinacijo zgoraj omenjenih možnosti.
Upoštevajo se zahteve za fotonapetostne generatorje z baterijami ali drugimi viri shranjevanja energije.

General Information

Status
Published
Publication Date
07-Apr-2016
Withdrawal Date
07-Apr-2019
Current Stage
6060 - Document made available - Publishing
Start Date
08-Apr-2016
Completion Date
08-Apr-2016

Relations

Buy Standard

Standardization document
HD 60364-7-712:2016 - BARVE
English language
27 pages
sale 10% off
Preview
sale 10% off
Preview
e-Library read for
1 day

Standards Content (Sample)


SLOVENSKI STANDARD
01-junij-2016
1DGRPHãþD
SIST HD 60364-7-712:2005
1L]NRQDSHWRVWQHHOHNWULþQHLQãWDODFLMHGHO=DKWHYH]DSRVHEQHLQãWDODFLMH
DOLORNDFLMH)RWRQDSHWRVWQL 39 VLVWHPL
Low-voltage electrical installations - Part 7-712: Requirements for special installations or
locations - Photovoltaic (PV) systems
Errichten von Niederspannungsanlagen - Teil 7-712: Anforderungen für Betriebsstätten,
Räume und Anlagen besonderer Art - Photovoltaik-(PV)-Stromversorgungssysteme
Installations électriques basses tensions - Partie 7-712: Exigences pour les installations
et emplacements spéciaux – Systèmes photovoltaïques (PV)
Ta slovenski standard je istoveten z: HD 60364-7-712:2016
ICS:
27.160 6RQþQDHQHUJLMD Solar energy engineering
91.140.50 Sistemi za oskrbo z elektriko Electricity supply systems
2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.

HARMONIZATION DOCUMENT HD 60364-7-712

DOCUMENT D'HARMONISATION
HARMONISIERUNGSDOKUMENT
April 2016
ICS 27.160; 91.140.50 Supersedes HD 60364-7-712:2005
English Version
Low-voltage electrical installations -
Part 7-712: Requirements for special installations or locations -
Photovoltaic (PV) systems
Installations électriques basses tensions -  Errichten von Niederspannungsanlagen -
Partie 7-712: Exigences pour les installations et Teil 7-712: Anforderungen für Betriebsstätten, Räume
emplacements spéciaux - und Anlagen besonderer Art -
Systèmes photovoltaïques (PV) Photovoltaik-(PV)-Stromversorgungssysteme
This Harmonization Document was approved by CENELEC on 2015-07-27. CENELEC members are bound to comply with the
CEN/CENELEC Internal Regulations which stipulate the conditions for implementation of this Harmonization Document at national level.
Up-to-date lists and bibliographical references concerning such national implementations may be obtained on application to the CEN-
CENELEC Management Centre or to any CENELEC member.
This Harmonization Document exists in three official versions (English, French, German).
CENELEC members are the national electrotechnical committees of Austria, Belgium, Bulgaria, Croatia, Cyprus, the Czech Republic,
Denmark, Estonia, Finland, Former Yugoslav Republic of Macedonia, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia,
Lithuania, Luxembourg, Malta, the Netherlands, Norway, Poland, Portugal, Romania, Slovakia, Slovenia, Spain, Sweden, Switzerland,
Turkey and the United Kingdom.

European Committee for Electrotechnical Standardization
Comité Européen de Normalisation Electrotechnique
Europäisches Komitee für Elektrotechnische Normung
CEN-CENELEC Management Centre: Avenue Marnix 17, B-1000 Brussels
© 2016 CENELEC All rights of exploitation in any form and by any means reserved worldwide for CENELEC Members.
Ref. No. HD 60364-7-712:2016 E

Contents Page
European foreword .4
Introduction .5
712 Photovoltaic systems (PV generator) .6
712.1 Scope .6
712.2 Normative references .6
712.3 Terms and definitions .8
712.4 Protection for safety . 10
712.41 Protection against electric shock . 10
712.410 Introduction . 10
712.412 Protective measure: double or reinforced insulation . 10
712.414 Protective measure: extra-low-voltage provided by SELV and PELV . 10
712.42 Protection against thermal effects . 10
712.421 Protection against fire caused by electrical equipment . 11
712.43 Protection against overcurrent . 11
712.431 Requirements according to the nature of the circuits . 11
712.432 Nature of protective devices . 12
712.433 Protection against overload current . 12
712.434 Protection against short-circuit currents. 13
712.44 Protection against voltage disturbances and electromagnetic disturbances . 13
712.443 Protection against overvoltages of atmospheric origin or due to switching . 13
712.5 Selection and erection of electrical equipment . 14
712.51 Common rules . 14
712.511 Compliance with standards . 14
712.512 Operational conditions and external influences . 14
712.513 Accessibility . 15
712.514 Identification . 15
712.52 Wiring systems . 16
712.521 Types of wiring systems . 16
712.523 Current-carrying capacities . 16
712.525 Voltage drop in consumers installations . 16
712.526 Electrical connections . 16
712.53 Protection, isolation, switching, control and monitoring . 16
712.531 Devices for fault protection by automatic disconnection of supply . 16
712.532 Devices for protection against the risk of fire . 17
712.533 Devices for protection against overcurrent . 17
712.534 Devices for protection against overvoltages . 17
712.537 Isolation and switching . 19
712.54 Earthing arrangements and protective conductors . 20
712.542 Earthing arrangements . 20
712.6 Verification . 21
Annex A (informative) Example for a single or parallel connected multi-string PV array . 22
Annex B (normative) Calculation of U and I . 23
OC MAX SC MAX
B.1 Calculation of U . 23
OC MAX
B.2 Calculation of I . 24
SC MAX
Annex C (informative) Examples for installation of SPDs for different cases . 25
Annex D (normative) Special national conditions . 26
Bibliography . 27

European foreword
This document (HD 60364-7-712:2016) has been prepared by CLC/TC 64 "Electrical installations and
protection against electric shock".
The following dates are fixed:
• latest date by which the document has to be implemented at (dop) 2016-10-08
national level by publication of an identical national
standard or by endorsement
(dow) 2019-04-08
• latest date by which the national standards conflicting with
the document have to be withdrawn

This document supersedes HD 60364-7-712:2005 + corrigendum April 2006.
HD 60364-7-712:2005:
– the scope has been amended to provide explanation for which PV supply systems this
Harmonization Document is suitable;
– terms and definitions are updated to the used wording for the technical definitions of PV-Systems;
– safety related requirements are brought in line with the latest editions of Harmonization
Documents from the HD 60364-4 series, especially on the protection for safety
HD 384.4/HD 60364-4. The respective structure has been adopted;
– calculation principles for the selection of protective devices are provided and brought in line with
the product standards for PV modules;
– where HD 60364-4-443 is not appropriate, a method for a risk assessment is introduced;
– to ensure safety of the various operators (maintenance personnel, inspectors, public distribution
network operators, emergency aid services, etc.), a warning symbol to indicate the presence of a
photovoltaic installation on a building was introduced;
– particular usage of overvoltage devices and their selection is explained;
– Annex B provides calculation methods for U and I .
OC MAX SC MAX
Attention is drawn to the possibility that some of the elements of this document may be the subject of
patent rights. CENELEC [and/or CEN] shall not be held responsible for identifying any or all such
patent rights.
Introduction
For the purpose of this part, the requirements of HD 60364/HD 384 apply.
The Parts 7XX of HD 60364 contain particular requirements for special installations or locations which
are based on the requirements of the general parts of HD 60364 (Part 1, Part 4, Part 5 and Part 6).
These Parts 7XX have to be considered in conjunction with the requirements of the general parts.
The particular requirements of this part of HD 60364 supplement, modify or replace certain of the
requirements of the general parts of HD 60364 being valid at the time of publication of this part.
The absence of reference to the exclusion of a part or a clause of a general part means that the
corresponding clauses of the general part are applicable (undated reference).
Requirements of other Parts 7XX being relevant for installations covered by this part also apply. This
part may therefore also supplement, modify or replace certain of these requirements valid at the time
of publication of this part.
The clause numbering of this part follows the pattern and corresponding references of HD 60364. The
numbers following the particular number of this part are those of the corresponding parts, or clauses of
HD 60364 being valid at the time of publication of this part as indicated in the normative references of
this document (dated reference).
If additional requirements or explanations are needed which have no direct relation to general parts or
other Parts 7XX the numbering of such clauses are stated as 712.101, 712.102, 712.103 etc.
NOTE In the case where new or amended general parts with modified numbering were published after this
part was issued, the clause numbers referring to a general part in this Part 712 may no longer align with the latest
edition of the general part. Dated references should be observed.
712 Photovoltaic systems (PV generator)
712.1 Scope
This section applies to the electrical installation of PV generator intended to supply all or part of an
installation and feeding of electricity into the public grid or local distribution.
In this section, the electrical equipment of a PV generator, like any other item of electrical equipment,
is dealt with only so far as its selection and application in the installation is concerned.
The electrical installation of a PV generator starts from a PV module or a set of PV modules
connected in series with their cables, provided by the PV module manufacturer, up to the user
installation or the utility supply point.
Requirements of this document apply to
– PV generators for supply to an installation which is not connected to a system for distribution of
electricity to the public,
– PV generators for supply to an installation in parallel with a system for distribution of electricity to
the public,
– PV generators for supply to an installation as an alternative to a system for distribution of
electricity to the public,
– appropriate combination of the above.
Requirements for PV generators with bat
...