oSIST prEN 12583:2021
(Main)Gas Infrastructure - Compressor stations - Functional requirements
Gas Infrastructure - Compressor stations - Functional requirements
This European Standard describes the specific functional requirements for the design, construction, operation, maintenance and disposal activities for safe and secure gas compressor stations.
This European Standard applies to new gas compressor stations with a Maximum Operating Pressure (MOP) over 16 bar and with a total shaft power over 1 MW. For existing compressor stations, this European Standard applies to new compressor units. Where changes/modifications to existing installations or gas composition take place, due account may be taken of the requirements of this European Standard.
This European Standard does not apply to gas compressor stations operating prior to the publication of this European Standard.
The purpose of this European Standard is intended to:
— ensure the health and safety of the public and all site personnel,
— to cover environmental issues and
— to avoid incidental damage to nearby property and
— to open the gas infrastructure to accommodate renewable gases.
This European Standard does not apply to:
— off-shore gas compressor stations;
— gas compressor stations for compressed natural gas filling-stations;
— customer installations downstream of the point of custody transfer;
— design and construction of driver packages (see Annex C);
— mobile compressor equipment.
For supplies to utility services such as small central heating boilers reference should be made to EN 1775.
Gasinfrastruktur - Verdichterstationen - Funktionale Anforderungen
Dieses Dokument legt die spezifischen funktionalen Anforderungen für sichere und zuverlässige Gasverdichterstationen fest, die bei Planung, Errichtung, Betrieb, Instandhaltung und Entsorgung zu beachten sind.
Dieses Dokument gilt für neue Gasverdichterstationen mit einem maximal zulässigen Betriebsdruck (MOP) über 16 bar und einer Gesamtkupplungsleistung über 1 MW. Für bestehende Verdichterstationen gilt diese Europäische Norm für neue Verdichtereinheiten. Falls Änderungen/Modifikationen an bestehenden Anlagen erfolgen, können die Anforderungen dieser Norm angemessen berücksichtigt werden.
Dieses Dokument braucht nicht auf Gasverdichterstationen angewendet zu werden, die vor der Veröffentlichung dieses Dokuments in Betrieb genommen wurden.
Der Zweck dieses Dokumentes ist es
- die Gesundheit und Sicherheit der Öffentlichkeit und der Mitarbeiter sicherzustellen,
- die Aspekte des Umweltschutzes zu behandeln,
- die Beschädigung fremden Eigentums zu verhindern und
- die Gasinfrastruktur für die Nutzung erneuerbare Gase, mit Hinsicht auf bis zu 100 % Wasserstoff, zu öffnen.
Dieses Dokument enthält allgemeine Grundsätze der Gasinfrastruktur. Anwender dieses Dokumentes sollten sich bewusst sein, dass detailliertere nationale Normen bzw. Technische Regeln in den CEN Mitgliedsländern existieren können.
Dieses Dokument sollte in Verbindung mit diesen, die oben erwähnten allgemeinen Grundsätze darlegenden nationalen Normen bzw. Technischen Regeln angewendet werden.
Beim Auftreten von Widersprüchen aufgrund restriktiverer Anforderungen in nationalen Gesetzen/Vorschriften als in diesem Dokument gefordert, haben nationale Gesetze/Vorschriften Vorrang, wie im CEN/TR 13737 beschrieben. Der CEN/TR 13737 (alle Teile) enthält
- eine Klarstellung aller in den Mitgliedsstaaten anwendbaren Gesetze und Bestimmungen;
- soweit zutreffend, restriktivere nationale Anforderungen;
- eine nationale Kontaktstelle für aktuelle Informationen.
Dieses Dokument gilt nicht für:
- Off-shore-Gasverdichterstationen;
- Gasverdichter in Erdgastankstellen;
- Kundenanlagen hinter der Liefergrenze;
- Auslegung und Bau von Antriebseinheiten (siehe Anhang C);
- Mobile Verdichteranlagen.
Für die Anbindung von Versorgungeinrichtungen, z. B. von kleinen Heizkesseln, sollte EN 1775 angewandt werden.
Bild 1 zeigt eine schematische Darstellung von Verdichterstationen in einem Gasversorgungssystem. Weitere Informationen sind in Anhang A, Anhang B, Anhang C, Anhang D, Anhang E und Anhang F zu finden.
Infrastructures gazières - Stations de compression - Prescriptions fonctionnelles
Le présent document établit les prescriptions fonctionnelles spécifiques pour la conception, la construction, l'exploitation, la maintenance et au démantèlement en sécurité des stations de compression du gaz.
Le présent document s'applique aux nouvelles stations de compression dont la pression maximale de service (MOP) est supérieure à 16 bar et dont la puissance totale à l'arbre est supérieure à 1 MW. Dans le cas des stations de compression existantes, le présent document s'applique aux nouvelles unités de compression. Lorsque des changements/modifications d'installations existantes ou de composition du gaz ont lieu, les exigences du présent document peuvent être prises en compte.
Le présent document ne s'applique pas aux stations de compression de gaz en fonctionnement avant la publication du présent document.
Le but du présent document consiste à :
- assurer la santé et la sécurité du public et de tout le personnel du site,
- couvrir les questions environnementales,
- éviter d'endommager incidemment les biens à proximité, et
- ouvrir l'infrastructure gazière pour l'adapter aux gaz renouvelables, y compris une conception possible pour l'hydrogène à 100 %.
Le présent document spécifie les principes de base communs pour les infrastructures gazières. Il convient que les utilisateurs du présent document gardent à l'esprit l'existence éventuelle, dans les pays membres du CEN, de codes de pratique et/ou de Normes nationales plus détaillés.
Le présent document est destiné à être appliqué conjointement avec ces normes nationales et/ou codes de pratique, qui détaillent les principes de base précités.
En cas de conflits liés à des exigences législatives/réglementaires plus restrictives que les prescriptions du présent document, la législation/réglementation nationale doit prévaloir, comme illustré dans le CEN/TR 13737 (toutes parties). Le CEN/TR 13737 (toutes les parties).donne :
- des clarifications sur les lois et règlements applicables dans les états membres ;
- si applicable, des impositions nationales plus contraignantes ;
- un point de contact national pour les informations les plus récentes.
Le présent document ne s'applique pas :
- aux stations de compression de gaz de plates-formes off-shore ;
- aux stations de compression de gaz pour stations de remplissage de gaz comprimé pour les véhicules ;
- aux installations des clients en aval du point de transfert de responsabilité ;
- à la conception et la construction des packages de l'entraînement (voir Annexe C) ;
- aux équipements de compression mobiles.
Pour les fournitures aux services publics tels que les petites chaudières de chauffage central, voir la norme EN 1775.
La Figure 1 présente un schéma des stations de compression dans une infrastructure gazière. Pour plus d'informations, se référer aux Annexes A, B, C, D, E et F.
Infrastruktura za plin - Kompresorske postaje - Funkcionalne zahteve
General Information
RELATIONS
Standards Content (sample)
SLOVENSKI STANDARD
oSIST prEN 12583:2021
01-februar-2021
Infrastruktura za plin - Kompresorske postaje - Funkcionalne zahteve
Gas Infrastructure - Compressor stations - Functional requirements
Gasinfrastruktur - Verdichterstationen - Funktionale Anforderungen
Infrastructures gazières - Stations de compression - Prescriptions fonctionnelles
Ta slovenski standard je istoveten z: prEN 12583ICS:
23.140 Kompresorji in pnevmatični Compressors and pneumatic
stroji machines
75.200 Oprema za skladiščenje Petroleum products and
nafte, naftnih proizvodov in natural gas handling
zemeljskega plina equipment
oSIST prEN 12583:2021 en,fr,de
2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.
---------------------- Page: 1 ----------------------oSIST prEN 12583:2021
---------------------- Page: 2 ----------------------
oSIST prEN 12583:2021
DRAFT
EUROPEAN STANDARD
prEN 12583
NORME EUROPÉENNE
EUROPÄISCHE NORM
February 2021
ICS 23.140; 75.200 Will supersede EN 12583:2014
English Version
Gas Infrastructure - Compressor stations - Functional
requirements
Infrastructures gazières - Stations de compression - Gasinfrastruktur - Verdichterstationen - Funktionale
Prescriptions fonctionnelles AnforderungenThis draft European Standard is submitted to CEN members for enquiry. It has been drawn up by the Technical Committee
CEN/TC 234.If this draft becomes a European Standard, CEN members are bound to comply with the CEN/CENELEC Internal Regulations
which stipulate the conditions for giving this European Standard the status of a national standard without any alteration.
This draft European Standard was established by CEN in three official versions (English, French, German). A version in any other
language made by translation under the responsibility of a CEN member into its own language and notified to the CEN-CENELEC
Management Centre has the same status as the official versions.CEN members are the national standards bodies of Austria, Belgium, Bulgaria, Croatia, Cyprus, Czech Republic, Denmark, Estonia,
Finland, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta, Netherlands, Norway,
Poland, Portugal, Republic of North Macedonia, Romania, Serbia, Slovakia, Slovenia, Spain, Sweden, Switzerland, Turkey and
United Kingdom.Recipients of this draft are invited to submit, with their comments, notification of any relevant patent rights of which they are
aware and to provide supporting documentation.Warning : This document is not a European Standard. It is distributed for review and comments. It is subject to change without
notice and shall not be referred to as a European Standard.EUROPEAN COMMITTEE FOR STANDARDIZATION
COMITÉ EUROPÉEN DE NORMALISATION
EUROPÄISCHES KOMITEE FÜR NORMUNG
CEN-CENELEC Management Centre: Rue de la Science 23, B-1040 Brussels
© 2021 CEN All rights of exploitation in any form and by any means reserved Ref. No. prEN 12583:2021 E
worldwide for CEN national Members.---------------------- Page: 3 ----------------------
oSIST prEN 12583:2021
prEN 12583:2020 (E)
Contents Page
European foreword ...................................................................................................................................................... 5
1 Scope .................................................................................................................................................................... 7
2 Normative references .................................................................................................................................... 8
3 Terms and definitions ................................................................................................................................. 10
4 Safety ................................................................................................................................................................. 16
5 Asset management and quality assurance .......................................................................................... 16
6 Environmental constraints ........................................................................................................................ 16
6.1 General.............................................................................................................................................................. 16
6.2 NOx and CO determination ........................................................................................................................ 17
6.2.1 General.............................................................................................................................................................. 17
6.2.2 Periodic measurements .............................................................................................................................. 17
6.2.3 Continuous Emission Monitoring System (CEMS) ............................................................................. 17
6.2.4 Predictive Emission Monitoring System (PEMS) ............................................................................... 17
6.3 Methane emission management .............................................................................................................. 18
6.3.1 General.............................................................................................................................................................. 18
6.3.2 Design phase ................................................................................................................................................... 18
6.3.3 Construction, commissioning and decommissioning ...................................................................... 19
6.3.4 Operation and maintenance ..................................................................................................................... 19
7 Design, construction .................................................................................................................................... 19
7.1 General requirements for design ............................................................................................................ 19
7.1.1 General.............................................................................................................................................................. 19
7.1.2 Safety and the environment ...................................................................................................................... 20
7.2 Location and station lay-out ..................................................................................................................... 20
7.2.1 Location ............................................................................................................................................................ 20
7.2.2 Station lay-out ................................................................................................................................................ 21
7.3 Pipework .......................................................................................................................................................... 23
7.3.1 Design considerations ................................................................................................................................. 23
7.3.2 Valves ................................................................................................................................................................ 23
7.3.3 Gas cleaning .................................................................................................................................................... 23
7.3.4 Gas coolers....................................................................................................................................................... 23
7.3.5 Pressure reduction stations ...................................................................................................................... 23
7.3.6 Recycle line ..................................................................................................................................................... 23
7.3.7 Vent systems ................................................................................................................................................... 24
7.3.8 Station isolation system ............................................................................................................................. 24
7.3.9 Corrosion protection ................................................................................................................................... 24
7.3.10 Services pipework ........................................................................................................................................ 24
7.3.11 Standard colour code ................................................................................................................................... 24
7.4 Compressor unit ............................................................................................................................................ 25
7.4.1 General.............................................................................................................................................................. 25
7.4.2 Driver ................................................................................................................................................................ 25
7.4.3 Compressor ..................................................................................................................................................... 26
7.4.4 Unit Control System (UCS) ......................................................................................................................... 27
7.4.5 Unit auxiliary equipment ........................................................................................................................... 31
7.4.6 Foundations .................................................................................................................................................... 35
7.4.7 Compressor unit housing ........................................................................................................................... 35
---------------------- Page: 4 ----------------------oSIST prEN 12583:2021
prEN 12583:2021 (E)
7.5 Station control and automation .............................................................................................................. 35
7.5.1 Station Control System (SCS) .................................................................................................................... 35
7.5.2 Station emergency shutdown systems .................................................................................................. 36
7.5.3 Gas detection system ................................................................................................................................... 36
7.5.4 Fire protection system ................................................................................................................................ 36
7.5.5 Station valve control and supervision .................................................................................................. 36
7.5.6 Over-pressure protection system ........................................................................................................... 37
7.5.7 Over-temperature protection system ................................................................................................... 37
7.6 Electrical installation and power supply ............................................................................................. 37
7.6.1 General ............................................................................................................................................................. 37
7.6.2 Electrical power supply .............................................................................................................................. 38
7.6.3 Electrical installation .................................................................................................................................. 38
7.6.4 Illumination requirements ....................................................................................................................... 38
7.7 General requirements for construction ............................................................................................... 38
7.7.1 General ............................................................................................................................................................. 38
7.7.2 Execution of work ......................................................................................................................................... 38
7.7.3 Station pipework construction ................................................................................................................ 38
8 Testing, commissioning and acceptance .............................................................................................. 39
8.1 General requirements ................................................................................................................................. 39
8.2 Pre-commissioning ...................................................................................................................................... 39
8.3 Commissioning .............................................................................................................................................. 39
8.4 As built records of the station .................................................................................................................. 40
8.5 Handover ......................................................................................................................................................... 40
8.6 Responsibility for safety ............................................................................................................................ 40
9 Operation ......................................................................................................................................................... 40
9.1 Introduction and basic requirements ................................................................................................... 40
9.2 Operating organization .............................................................................................................................. 41
9.3 Instruction procedures ............................................................................................................................... 41
9.3.1 General ............................................................................................................................................................. 41
9.3.2 Instructions for normal situations ......................................................................................................... 41
9.3.3 Instructions for failure or emergency situations .............................................................................. 41
9.3.4 Procedures for specific planned situations ......................................................................................... 42
9.4 Management of operating procedures .................................................................................................. 42
9.5 Training of personnel ................................................................................................................................. 43
9.6 Safety precautions ........................................................................................................................................ 43
9.6.1 Prevention of gas explosion and fire ..................................................................................................... 43
9.6.2 Storage of combustible materials ........................................................................................................... 43
9.6.3 Venting.............................................................................................................................................................. 43
9.6.4 IT-Security ....................................................................................................................................................... 43
10 Maintenance ................................................................................................................................................... 44
10.1 Introduction and basic requirements ................................................................................................... 44
10.2 Maintenance organization ......................................................................................................................... 44
10.3 Maintenance procedures ........................................................................................................................... 44
10.3.1 General ............................................................................................................................................................. 44
10.3.2 Gas compressor units .................................................................................................................................. 45
10.3.3 Pipework .......................................................................................................................................................... 45
10.4 Management of the maintenance procedures .................................................................................... 45
10.5 Training of personnel ................................................................................................................................. 45
10.6 Maintenance tools and equipment ......................................................................................................... 46
10.7 Safety ................................................................................................................................................................. 46
10.7.1 General ............................................................................................................................................................. 46
10.7.2 Safety precautions ........................................................................................................................................ 46
---------------------- Page: 5 ----------------------oSIST prEN 12583:2021
prEN 12583:2021 (E)
10.7.3 Safety devices ................................................................................................................................................. 47
11 Decommissioning and disposal ............................................................................................................... 47
11.1 Decommissioning ......................................................................................................................................... 47
11.2 Disposal ............................................................................................................................................................ 47
Annex A (informative) Boundary of a gas compressor station.................................................................. 48
Annex B (informative) Parts of a gas compressor unit................................................................................. 50
Annex C (informative) Boundary Gas compressor unit — Driver package .......................................... 51
Annex D (informative) Boundary Gas compressor unit — Gas compressor ........................................ 52
Annex E (informative) Boundary Gas compressor unit — Unit control system .................................. 53
Annex F (informative) Boundary Gas compressor unit — Auxiliary equipment ................................ 54
Annex G (informative) Significant technical changes between this document and the
previous edition ............................................................................................................................................ 55
Annex H (normative) Applicable measurement systems for NOx and CO determination ............... 56
Annex I (informative) Examples of PEMS and quality insurance applications .................................... 58
I.1 Predictive Emission Monitoring System (PEMS), a relational model: quality criteria
implementation: ............................................................................................................................................ 58
I.1.1 General.............................................................................................................................................................. 58
I.1.2 QAL 1, design part ......................................................................................................................................... 58
I.1.3 QAL 2 calibration and functional test (installation) ........................................................................ 59
I.1.4 QAL 3, drift and precision control in operation ................................................................................. 59
I.1.5 AST Annual Survey Test .............................................................................................................................. 59
I.2 An example of a polynomial model for PEMS for gas fired conventional turbines /
engines: ............................................................................................................................................................. 60
Annex J (informative) Categories of methane emissions ............................................................................ 61
Bibliography ................................................................................................................................................................. 62
---------------------- Page: 6 ----------------------oSIST prEN 12583:2021
prEN 12583:2021 (E)
European foreword
This document (prEN 12583:2021) has been prepared by Technical Committee CEN/TC 234 “Gas
Infrastructure”, the secretariat of which is held by DIN.This document is currently submitted to the CEN Enquiry.
This document will supersede EN 12583:2014.
In comparison with the previous edition, the following technical modifications have been made:
— Addition of requirements for hydrogen readiness— Addition of Methane Emissions Management
— Addition of NOx and CO determination
— Addition of references to new European Standards, for example the merging of EN 16348 and
EN 15399 (WI 00234093)— Updated normative references
— Updated with practical experience from the application of the previous edition
— Clarification of technical wording
A detailed overview of all changes is given in Annex G.
This document has been prepared under a mandate given to CEN by the European Commission and the
European Free Trade Association.There is a complete suite of functional standards prepared by CEN/TC 234 “Gas infrastructure” to cover
all parts of the gas infrastructure from the input of gas into the on-shore transmission network up to the
inlet connection of gas appliances, including transmission, distribution, storage, compression, pressure
regulation and metering, installation, injection of non-conventional gases, gas quality issues and others.
In preparing this document a basic understanding of gas infrastructure by the user has been assumed.
The gas infrastructure is complex and the importance on safety of its construction and use has led to the
development of very detailed codes of practice and operating manuals in the member countries. These
detailed statements embrace recognized standards of gas engineering and the specific requirements
imposed by the legal structures of the member countries.Directive 2009/73/EC concerning common rules for the internal market in natural gas and the related
Regulation (EC) No 715/2009 on conditions for access to the natural gas transmission networks also
aim at technical safety (security) including technical reliability of the European gas system. These
aspects are also in the scope of CEN/TC 234 standardization. In this respect CEN/TC 234 evaluated the
indicated EU legislation and amended this document accordingly, where required and appropriate.
In this edition of EN 12583 environmental aspects relevant to the design, construction and testing,
operation and maintenance, decommissioning and disposal of compressor stations in the scope of this
document are covered in accordance with CEN Guide 4 and CEN/TR 16388.---------------------- Page: 7 ----------------------
oSIST prEN 12583:2021
prEN 12583:2021 (E)
Directive 2009/28/EC on the promotion of the use of energy from renewable sources and amending
and subsequently repealing Directives 2001/77/EC and 2003/30/EC, in Article 3 and 5 are with regard
to the calculation of the share of energy from renewable sources and the contribution of hydrogen
originating from renewable sources in the total fuel mix. In this respect CEN/TC 234 evaluated the
indicated EU legislation and amended this document.---------------------- Page: 8 ----------------------
oSIST prEN 12583:2021
prEN 12583:2021 (E)
1 Scope
This document describes the specific functional requirements for the design, construction, operation,
maintenance and disposal activities for safe and secure gas compressor stations.This document applies to new gas compressor stations with a Maximum Operating Pressure (MOP)
over 16 bar and with a total shaft power over 1 MW. For existing compressor stations, this document
applies to new compressor units. Where changes/modifications to existing installations or gas
composition take place, due account may be taken of the requirements of this document.
This document does not apply to gas compressor stations operating prior to the publication of this
document.The purpose of this document is intended to:
— ensure the health and safety of the public and all site personnel,
— to cover environmental issues,
— to avoid incidental damage to nearby property, and
— to open the gas infrastructure to accommodate renewable gases, including a possible design for
100 % hydrogen.This document specifies common basic principles for the gas infrastructure. Users of this document are
expected to be aware that more detailed national standards and/or codes of practice can exist in the
CEN member countries.This document is intended to be applied in association with these national standards and/or codes of
practice setting out the above-mentioned basic principles.In the event of conflicts in terms of more restrictive requirements in national legislation/regulation
with the requirements of this document, the national legislation/regulation takes precedence as
illustrated in CEN/TR 13737 (all parts). CEN/TR 13737 (all parts) gives:— clarification of all legislations/regulations applicable in a member state;
— if appropriate, more restrictive national requirements;
— a national contact point for the latest information.
This document does not apply to:
— off-shore gas compressor stations;
— gas compressor stations for compressed gas filling-stations;
— customer installations downstream of the point of custody transfer;
— design and construction of driver packages (see Annex C);
— mobile compressor equipment.
For supplies to utility services such as small central heating boilers reference is made to EN 1775.
Figure 1 shows a schematic representation of compressor stations in a gas infrastructure. For further
information refer to Annexes A, B, C, D, E and F.---------------------- Page: 9 ----------------------
oSIST prEN 12583:2021
prEN 12583:2021 (E)
Key
1 compressor station 4 pig traps
2 distribution system 5 transmission line
3 metering and/or pressure limiting or regulation station 6 storage facility
* part of pipeline but operated by safety control systems
NOTE Parts indicated in frames by thick lines are within the scope of this document.
Figure 1 — Schematic representation of compressor stations in the gas infrastructure
2 Normative referencesThe following documents are referred to in the text in such a way that some or all of their content
constitutes requirements of this document. For dated references, only the edition cited applies. For
undated references, the latest edition of the referenced document (including any amendments) applies.
EN 1012-3, Compressors and vacuum pumps - Safety requirements - Part 3: Process compressors
EN 1594, Gas infrastructure - Pipelines for maximum operating pressure over 16 bar - Functional
requirementsEN 12186, Gas infrastructure - Gas pressure regulating stations for transmission and distribution -
Functional requirementsEN 12266-1, Industrial valves - Testing of metallic valves - Part 1: Pressure tests, test procedures and
acceptance criteria - Mandatory requirements---------------------- Page: 10 ----------------------
oSIST prEN 12583:2021
prEN 12583:2021 (E)
EN 12266-2, Industrial valves - Testing of metallic valves - Part 2: Tests, test procedures and acceptance
criteria - Supplementary requirementsEN 12732, Gas infrastructure — Welding steel pipework — Functional requirements
EN 14505, Cathodic protection of complex structures
EN 60079-10-1:2015, Explosive atmospheres — Part 10-1: Classification of areas — Explosiv
...
Questions, Comments and Discussion
Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.