Rigid cellular plastics - Spray-applied polyurethane foam for thermal insulation - Part 2: Application

This part of ISO 8873 outlines requirements for the application of rigid cellular plastic spray polyurethane foam
for thermal insulation. The primary application of the material is for use as thermal insulation. Spray
polyurethane foam can also be used as the air barrier material which forms part of an air barrier assembly in
buildings. Under specific application conditions, the material can be used in vapour barrier applications in a
building assembly (details of the conditions can be obtained from the manufacturer). The application
requirements are for the installation of spray polyurethane foam whether applied on a building site or in a
prefabrication (manufacturing) facility.
This part of ISO 8873 can be used for non-building applications when agreed to by the supplier and the
purchaser.
The requirements include obligations for the manufacturer, the contractor and the installer. The requirements
include the selection of chemical components, application requirements, quality control and documentation of
the application, limitations for the application and requirements for safety and for disposal of associated waste
material and packaging.
Installation of spray polyurethane foam for thermal insulation, according to this part of ISO 8873 requires the
use of materials and/or equipment that could be hazardous (see Warning).

Plastiques alvéolaires rigides - Mousse de polyuréthanne projetée pour l'isolation thermique - Partie 2: Application

Penjeni polimerni materiali - Brizgana poliuretanska pena za toplotno izolacijo - 2. del: Uporaba

General Information

Status
Published
Publication Date
19-Feb-2015
Current Stage
6060 - National Implementation/Publication (Adopted Project)
Start Date
27-Jan-2015
Due Date
03-Apr-2015
Completion Date
20-Feb-2015

RELATIONS

Buy Standard

Standard
ISO 8873-2:2007 - Rigid cellular plastics -- Spray-applied polyurethane foam for thermal insulation
English language
37 pages
sale 15% off
Preview
sale 15% off
Preview
Standard
SIST ISO 8873-2:2015
English language
42 pages
sale 10% off
Preview
sale 10% off
Preview

e-Library read for
1 day

Standards Content (sample)

INTERNATIONAL ISO
STANDARD 8873-2
First edition
2007-05-01
Rigid cellular plastics — Spray-applied
polyurethane foam for thermal
insulation —
Part 2:
Application
Plastiques alvéolaires rigides — Mousse de polyuréthanne projetée
pour l'isolation thermique —
Partie 2: Application
Reference number
ISO 8873-2:2007(E)
ISO 2007
---------------------- Page: 1 ----------------------
ISO 8873-2:2007(E)
PDF disclaimer

This PDF file may contain embedded typefaces. In accordance with Adobe's licensing policy, this file may be printed or viewed but

shall not be edited unless the typefaces which are embedded are licensed to and installed on the computer performing the editing. In

downloading this file, parties accept therein the responsibility of not infringing Adobe's licensing policy. The ISO Central Secretariat

accepts no liability in this area.
Adobe is a trademark of Adobe Systems Incorporated.

Details of the software products used to create this PDF file can be found in the General Info relative to the file; the PDF-creation

parameters were optimized for printing. Every care has been taken to ensure that the file is suitable for use by ISO member bodies. In

the unlikely event that a problem relating to it is found, please inform the Central Secretariat at the address given below.

COPYRIGHT PROTECTED DOCUMENT
© ISO 2007

All rights reserved. Unless otherwise specified, no part of this publication may be reproduced or utilized in any form or by any means,

electronic or mechanical, including photocopying and microfilm, without permission in writing from either ISO at the address below or

ISO's member body in the country of the requester.
ISO copyright office
Case postale 56 • CH-1211 Geneva 20
Tel. + 41 22 749 01 11
Fax + 41 22 749 09 47
E-mail copyright@iso.org
Web www.iso.org
Published in Switzerland
ii © ISO 2007 – All rights reserved
---------------------- Page: 2 ----------------------
ISO 8873-2:2007(E)
Contents Page

Foreword............................................................................................................................................................ iv

Introduction ........................................................................................................................................................ v

1 Scope...................................................................................................................................................... 1

2 Normative references ........................................................................................................................... 1

3 Terms and definitions........................................................................................................................... 2

4 Requirements ........................................................................................................................................ 3

4.1 Manufacturer ......................................................................................................................................... 3

4.2 Spray polyurethane foam contractor .................................................................................................. 3

4.3 Spray polyurethane foam installer ...................................................................................................... 4

4.4 Apprentice installer............................................................................................................................... 6

4.5 Material................................................................................................................................................... 6

4.6 Equipment.............................................................................................................................................. 6

4.7 Installation ............................................................................................................................................. 6

5 Applications........................................................................................................................................... 8

5.1 General................................................................................................................................................... 8

5.2 Air barrier system application ............................................................................................................. 8

5.3 Vapour barrier application ................................................................................................................... 8

5.4 Exterior foundation insulation application......................................................................................... 8

5.5 Interior foundation insulation application.......................................................................................... 8

5.6 Cathedral ceilings, flat ceilings and decks over heated spaces...................................................... 8

5.7 Attic application, exterior (cavity) and interior wall application ...................................................... 8

6 Sampling ................................................................................................................................................ 8

7 Test methods......................................................................................................................................... 9

7.1 Determination of density...................................................................................................................... 9

7.2 Cohesion and adhesion test .............................................................................................................. 10

7.3 Verification of substrate (application surface) preparation............................................................ 10

7.4 Reporting requirements ..................................................................................................................... 10

8 Manufacturer's marking...................................................................................................................... 11

9 Manufacturer’s documentation ......................................................................................................... 12

10 Limitations ........................................................................................................................................... 12

Annex A (normative) Substrate preparation.................................................................................................. 13

Annex B (normative) Selection of chemical components (system)............................................................ 16

Annex C (informative) Climatic factors .......................................................................................................... 17

Annex D (normative) Job-site set up.............................................................................................................. 18

Annex E (informative) Trouble shooting and repair...................................................................................... 20

Annex F (normative) Handling and safety precautions................................................................................ 22

Annex G (normative) Disposal and detoxification of drums........................................................................ 25

Annex H (informative) Daily work record ....................................................................................................... 27

Annex I (informative) Example of job site label............................................................................................. 29

Annex J (informative) Outline of licensed installer training programme.................................................... 30

Annex K (normative) Minimum equipment for site test kit .......................................................................... 36

Bibliography ..................................................................................................................................................... 37

© ISO 2007 – All rights reserved iii
---------------------- Page: 3 ----------------------
ISO 8873-2:2007(E)
Foreword

ISO (the International Organization for Standardization) is a worldwide federation of national standards bodies

(ISO member bodies). The work of preparing International Standards is normally carried out through ISO

technical committees. Each member body interested in a subject for which a technical committee has been

established has the right to be represented on that committee. International organizations, governmental and

non-governmental, in liaison with ISO, also take part in the work. ISO collaborates closely with the

International Electrotechnical Commission (IEC) on all matters of electrotechnical standardization.

International Standards are drafted in accordance with the rules given in the ISO/IEC Directives, Part 2.

The main task of technical committees is to prepare International Standards. Draft International Standards

adopted by the technical committees are circulated to the member bodies for voting. Publication as an

International Standard requires approval by at least 75 % of the member bodies casting a vote.

Attention is drawn to the possibility that some of the elements of this document may be the subject of patent

rights. ISO shall not be held responsible for identifying any or all such patent rights.

ISO 8873-2 was prepared by Technical Committee ISO/TC 61, Plastics, Subcommittee SC 10, Cellular

plastics.

This first edition of ISO 8873-2, together with ISO 8873-1 and ISO 8873-3, cancels and replaces

ISO 8873:1987, which has been technically revised.

ISO 8873 consists of the following parts, under the general title Rigid cellular plastics — Spray-applied

polyurethane foam for thermal insulation:
⎯ Part 1: Material specifications
⎯ Part 2: Application
⎯ Part 3: Test methods
iv © ISO 2007 – All rights reserved
---------------------- Page: 4 ----------------------
ISO 8873-2:2007(E)
Introduction

Spray polyurethane foam for thermal insulation is made by combining two liquid components on the project

site to manufacture a product. As the manufactured product is what provides the physical and thermal

properties desired by the user, it only becomes spray polyurethane foam when it is installed. As such, an

International Standard for the application and installation is required.

This part of ISO 8873 outlines the obligations for the installer of the liquid components that produce the actual

material.

ISO 8873-1 outlines obligations for the manufacturers of spray polyurethane foam liquid components.

ISO 8873-3 provides test methods which have not previously been specified in International Standards.

© ISO 2007 – All rights reserved v
---------------------- Page: 5 ----------------------
INTERNATIONAL STANDARD ISO 8873-2:2007(E)
Rigid cellular plastics — Spray-applied polyurethane foam for
thermal insulation —
Part 2:
Application

WARNING — Persons using this document should be familiar with normal laboratory practice, if

applicable. This document does not purport to address all of the safety concerns, if any, associated

with its use. It is the responsibility of the user to establish appropriate safety and health practices and

to ensure compliance with any regulatory requirements.
1 Scope

This part of ISO 8873 outlines requirements for the application of rigid cellular plastic spray polyurethane foam

for thermal insulation. The primary application of the material is for use as thermal insulation. Spray

polyurethane foam can also be used as the air barrier material which forms part of an air barrier assembly in

buildings. Under specific application conditions, the material can be used in vapour barrier applications in a

building assembly (details of the conditions can be obtained from the manufacturer). The application

requirements are for the installation of spray polyurethane foam whether applied on a building site or in a

prefabrication (manufacturing) facility.

This part of ISO 8873 can be used for non-building applications when agreed to by the supplier and the

purchaser.

The requirements include obligations for the manufacturer, the contractor and the installer. The requirements

include the selection of chemical components, application requirements, quality control and documentation of

the application, limitations for the application and requirements for safety and for disposal of associated waste

material and packaging.

Installation of spray polyurethane foam for thermal insulation, according to this part of ISO 8873 requires the

use of materials and/or equipment that could be hazardous (see Warning).
2 Normative references

The following referenced documents are indispensable for the application of this document. For dated

references, only the edition cited applies. For undated references, the latest edition of the referenced

document (including any amendments) applies.

ISO 8873-1, Rigid cellular plastics — Spray-applied polyurethane foam for thermal insulation — Part 1:

Material specifications

ISO/IEC 17024, Conformity assessment — General requirements for bodies operating certification of persons

© ISO 2007 – All rights reserved 1
---------------------- Page: 6 ----------------------
ISO 8873-2:2007(E)
3 Terms and definitions

The following referenced documents are indispensable for the application of this document. For dated

references, only the edition cited applies. For undated references, the latest edition of the referenced

document (including any amendments) applies.
3.1
authority having jurisdiction

officer or officers having authority, under appropriate regulatory instruments, to exercise enforcement

3.2
apprentice installer

individual who applies spray polyurethane foam on the job site, under the direct supervision of a spray

polyurethane installer
3.3
certification organization

impartial body possessing the necessary competence and reliability to operate a certification system in

accordance with ISO/IEC 17024, in which the interests of all parties concerned with the functioning of the

system are represented
3.4
equipment manufacturer

manufacturer of equipment designed for spray-application of rigid polyurethane cellular plastic thermal

insulation
3.5
in-situ thermal insulation

thermal insulation product produced or taking its final form at the site of application and which achieves its

properties after installation
3.6
site quality assurance programme

quality assurance programme (QAP) based upon quality standards, which ties the chemical system

components manufacturer (supplier), the contractor and the installer together for the installation of spray

polyurethane foam

NOTE 1 The QAP should outline the responsibilities and obligations of each of the three parties. The QAP should

outline the training and certification requirements for each of the three parties and should include a site inspection of the

installation of spray polyurethane foam.
NOTE 2 ISO 9001 and ISO 12576-2 are examples of quality standards.
3.7
spray polyurethane foam

rigid cellular plastic material with substantially closed cell structure based on polyurethanes, which is foamed

in situ by the catalysed reaction of polyisocyanates and polyhydroxyl compounds, expanded with blowing

agents
3.8
spray polyurethane foam contractor

individual, organization or corporation who is responsible for all requirements and obligations for the

installation of the product
3.9
spray polyurethane foam installer

individual or worker who applies the chemical components by mixing and spraying them to form the rigid

cellular plastic spray polyurethane foam product

NOTE The installer is responsible for the actual installation and site requirements identified by the manufacturer

and/or this part of ISO 8873 for application of the product. The installer should be trained and qualified as having

2 © ISO 2007 – All rights reserved
---------------------- Page: 7 ----------------------
ISO 8873-2:2007(E)

demonstrated the required knowledge for proper application of the product by a certification organization (CO). The

installer should follow the requirements for installation and the obligations for installers identified by the manufacturer and

this part of ISO 8873.
3.10
spray polyurethane foam system manufacturer

manufacturer/supplier of the liquid chemical components, polyisocyanates and polyhydroxyl blends containing

also flame retardants, blowing agent and catalysts (system), which are designed to be mixed and sprayed to

form rigid polyurethane foam insulation material in situ
4 Requirements
4.1 Manufacturer
The manufacturer (supplier)
a) shall produce material that meets the requirements of ISO 8873-1,

b) shall mark and label the shipping containers to declare that the material meets the requiements of

ISO 8773-1,

c) shall declare the certification organization that is responsible for delivering the site quality assurance

programme for their product, and

d) shall ensure that the material is installed by a spray polyurethane foam contractor using a spray

polyurethane foam installer in accordance with this part of ISO 8873 and the instructions given by the

chemical manufacturer.
4.2 Spray polyurethane foam contractor
The spray polyurethane foam contractor

a) shall produce material that meets the requirements of ISO 8873-1 and shall comply with all requirements

of this part of ISO 8873;
b) shall select the material that is appropriate for the installation;

c) shall procure material which complies with ISO 8873-1 from a spray polyurethane foam system

manufacturer;

d) shall verify, through the use of drum labels or other documentation, that the material received complies

with ISO 8873-1;

e) shall have at least one trained and certification organization approved spray polyurethane foam installer

on each job site during the application of the spray polyurethane foam thermal insulation;

f) shall be responsible for all aspects of the installation of the material; all regulations shall be complied with

during the installation of the material; the completed application shall comply with all appropriate

regulations such as building codes;

g) shall ensure that the spray polyurethane foam installer has successfully completed a training course

approved by the manufacturer and the certification organization; the spray polyurethane foam installer

shall successfully complete the training and have obtained certification as a spray polyurethane foam

installer;

h) shall provide the spray polyurethane foam installer with proper equipment to install spray polyurethane

foam; equipment may include, but is not limited to, transfer pumps, a proportioner unit, hoses, hose

heaters, spray guns, compressors and generators;
© ISO 2007 – All rights reserved 3
---------------------- Page: 8 ----------------------
ISO 8873-2:2007(E)

i) shall provide, or ensure that the spray polyurethane foam installer has, proper personnel protection,

which shall include a positive fresh-air-supplied full-face respirator; other protection includes head

protection, eye protection, ear protection, body protection, hand protection and foot protection;

j) shall provide, on each job site, a test kit meeting the requirements outlined in Annex K for use by the

spray polyurethane foam installer to conduct the testing required for thermal insulation in accordance with

this part of ISO 8873;

k) shall ensure that the spray polyurethane foam installer conducts the daily testing;

l) shall ensure that the installer completes daily work records in accordance with the site quality assurance

programme; this daily work record shall contain
⎯ information on the job site, date and material used,
⎯ name of the installer and certification number,
⎯ application conditions and environmental conditions,
⎯ results of the testing completed on site,
⎯ whether the material complies with ISO 8873-1,
⎯ whether the project required isolation and ventilation, and
⎯ whether the material used has been evaluated by a third party;

m) shall supply the installer with all the forms required; the daily work record shall be completed at the

beginning of each day, each time a material batch is changed, and when the job site is changed within a

given day;

n) shall keep the daily work records for a period of seven years; these records shall be made available upon

request, within a reasonable time, to the manufacturer or the certification organization; the minimum

information required for a daily work record is shown in Annex H;

o) shall provide a job site declaration form containing the minimum information outlined in Annex I to the

customer within 30 days of completion of the project;

p) shall ensure that the spray polyurethane foam installer follows the site quality assurance programme

developed by the certification organization; a copy of the site quality assurance programme shall be made

available upon request;
q) shall maintain the installation equipment in proper working order;

r) where a separate contractor is responsible for the thermal barrier installation and when the authority

having jurisdiction requires a thermal barrier for that application, the spray polyurethane foam contractor

shall notify the building owner or the owner’s representative in writing of the requirement for a thermal

barrier and the flammability hazard, which could exist until such time that the foam is covered.

4.3 Spray polyurethane foam installer
The installer

a) shall produce material that meets the requirements of ISO 8873-1 in accordance with this part of

ISO 8873, the instructions provided by the spray polyurethane foam system manufacturer and the spray

polyurethane foam contractor;
4 © ISO 2007 – All rights reserved
---------------------- Page: 9 ----------------------
ISO 8873-2:2007(E)

b) shall confirm, using drum labels or other documentation, that the liquid chemicals to be used on site have

been declared by the manufacturer to comply with ISO 8873-1 before commencing installation;

c) shall be responsible for the on-site installation of the material, safe handling and storage of the material,

proper isolation of the spray area, warning signs when spraying is in progress, site housekeeping, and

their own personal and the crew's health and safety; the spray polyurethane foam installer shall wear

proper personnel protection, which includes head protection, eye protection, a positive fresh-air-supplied

full-face respirator, ear protection, body protection, hand protection and foot protection in compliance with

regulations;

d) shall successfully complete a training course approved by the manufacturer and the designated

certification organization; the installer shall obtain certification from the designated certification

organization as a spray polyurethane foam installer; a recommended training outline is shown in Annex J;

e) shall follow all operating instructions for the equipment provided by the equipment manufacturer; this

equipment may include, but is not limited to, transfer pumps, a proportioner unit, hoses, hose heaters,

guns, compressors and generators; the installer shall follow instructions from the equipment manufacturer

for the operation, maintenance and cleaning of the equipment used for installation; the spray

polyurethane foam installer shall follow all safety procedures required by the equipment manufacturer;

f) shall verify, through a material label, that the material on site has been declared by the manufacturer to

comply with ISO 8873-1;
g) shall verify that the substrate has been properly prepared;

h) shall verify that the environmental conditions are within the range approved by the spray polyurethane

foam system manufacturer;
i) shall set the equipment to the proper operating parameters;

j) shall install the material in accordance with this part of ISO 8873 and the manufacturer’s instructions;

k) shall comply with all requirements of the site quality assurance programme provided by the certification

organization;

l) shall apply the spray polyurethane foam so that the surface is reasonably smooth and of consistent

thickness;

m) shall exercise an ongoing visual and physical quality control check throughout the spray application to

ensure proper adhesion to the substrate and proper quality of the spray polyurethane foam;

n) shall check with a depth gauge (see Figure 1) the thickness of the the applied foam on a continual basis

and shall provide the minimum thickness specified by the owner;

o) shall conduct density, adhesion, cohesion and substrate verification at the beginning of each day, each

time a material batch is changed, and when the job site is changed within a given day;

p) shall complete daily work records in accordance with the site quality assurance programme; this daily

work record shall contain
⎯ information on the job site (see Annex D), date and material used,
⎯ name of the installer and certification number,
⎯ application conditions and environmental conditions,
⎯ results of the testing completed on site,
⎯ whether the material complies with ISO 8873-1,
© ISO 2007 – All rights reserved 5
---------------------- Page: 10 ----------------------
ISO 8873-2:2007(E)
⎯ whether project required isolation and ventilation, and
⎯ whether the material used has been evaluated by a third party;

q) shall at the end of each working day, remove all waste from the construction site and dispose of it in a

safe and proper manner, in accordance with local, provincial and federal requirements;

r) shall, in cases where an apprentice installer is applying the material, ensure that the apprentice is under

the direct supervision of the spray polyurethane foam installer who has the responsibility for the

application.

The daily work record shall be completed at the beginning of each day, each time a material batch is changed,

and when the job site is changed within a given day; the minimum information required for a daily work record

is shown in Annex H.
4.4 Apprentice installer
The apprentice installer

a) shall only install spray polyurethane foam thermal insulation under the direct and constant supervision of

a spray polyurethane foam installer,

b) shall be required to meet all the same requirements as a spray polyurethane foam installer when

installing spray polyurethane foam, and

c) shall wear proper personnel protection, which includes head protection, eye protection, a positive fresh-

air-supplied full-face respirator, ear protection, body protection, hand protection and foot protection in

compliance with regulations.
4.5 Material

The spray polyurethane foam system, when stored in accordance with the chemical manufacturer’s

instructions, properly mixed and spray applied as required in 4.3, and within the shelf life of the chemicals as

declared by the manufacturer, shall produce a finished product that meets the requirements of the ISO 8873-1.

Application requirements, which will affect the performance of the finished product, shall be considered when

choosing the chemical components (see Annex B).

When installed as given in 4.3, the spray polyurethane foam shall not present a health hazard to the potential

occupants, nor shall the cured insulation have any residual odour.
4.6 Equipment

The chemical components shall be mixed and sprayed with a commercially available spray gun and a fixed-

ratio, positive-displacement proportioning unit, specially designed for the application of spray polyurethane

foam. The manufacturer shall recommend appropriate equipment to be used.

Operation, maintenance, safety and cleaning procedures detailed in the equipment manufacturer’s manual

shall be strictly followed.
4.7 Installation

Special applications which require properties in addition to those specified in this part of ISO 8873 shall be

agreed upon by the interested parties prior to commencement of the installation.

Prior to application, a test shall be run to ensure that proper equipment settings have been selected.

Consideration shall be given to reactivity, spray pattern, adhesion to substrate and the appearance of the

spray polyurethane foam to ensure that each of these properties meets the requirements specified by the

6 © ISO 2007 – All rights reserved
---------------------- Page: 11 ----------------------
ISO 8873-2:2007(E)

spray polyurethane foam system manufacturer. The spray polyurethane foam installer shall confirm that the

density of the installed material meets the minimum density declared by the spray polyurethane foam system

manufacturer.

The spray polyurethane foam system shall be applied in passes to a clean, dry and sound substrate, prepared

in accordance with Annex A. The thickness of the insulation shall be ascertained by using a thickness gauge

as shown in Figure 1. Successive passes shall overlap to ensure a smooth surface, free of ridges.

Each pass should not be less than 15 mm thick because of the possibility of reduced foaming, which

adversely affects the adhesion to the substrate. Each pass should not be more than 50 mm thick to avoid

elongated cell formation and to minimize the possibility of stress cracking. When several passes are required,

allow for cooling of the foam to prevent scorching.

In any interior building installations, where required by the authority having jurisdiction, a thermal barrier shall

cover the interior side of spray polyurethane foam for fire protection.

In permanently exposed exterior installations, coatings or coverings are necessary for protection from

ultraviolet degradation. Co
...

SLOVENSKI STANDARD
SIST ISO 8873-2:2015
01-marec-2015
1DGRPHãþD
SIST ISO 8873:1996

Penjeni polimerni materiali - Brizgana poliuretanska pena za toplotno izolacijo - 2.

del: Uporaba

Rigid cellular plastics - Spray-applied polyurethane foam for thermal insulation - Part 2:

Application

Plastiques alvéolaires rigides - Mousse de polyuréthanne projetée pour l'isolation

thermique - Partie 2: Application
Ta slovenski standard je istoveten z: ISO 8873-2:2007
ICS:
83.100 Penjeni polimeri Cellular materials
91.120.10 Toplotna izolacija stavb Thermal insulation
SIST ISO 8873-2:2015 en

2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.

---------------------- Page: 1 ----------------------
SIST ISO 8873-2:2015
---------------------- Page: 2 ----------------------
SIST ISO 8873-2:2015
INTERNATIONAL ISO
STANDARD 8873-2
First edition
2007-05-01
Rigid cellular plastics — Spray-applied
polyurethane foam for thermal
insulation —
Part 2:
Application
Plastiques alvéolaires rigides — Mousse de polyuréthanne projetée
pour l'isolation thermique —
Partie 2: Application
Reference number
ISO 8873-2:2007(E)
ISO 2007
---------------------- Page: 3 ----------------------
SIST ISO 8873-2:2015
ISO 8873-2:2007(E)
PDF disclaimer

This PDF file may contain embedded typefaces. In accordance with Adobe's licensing policy, this file may be printed or viewed but

shall not be edited unless the typefaces which are embedded are licensed to and installed on the computer performing the editing. In

downloading this file, parties accept therein the responsibility of not infringing Adobe's licensing policy. The ISO Central Secretariat

accepts no liability in this area.
Adobe is a trademark of Adobe Systems Incorporated.

Details of the software products used to create this PDF file can be found in the General Info relative to the file; the PDF-creation

parameters were optimized for printing. Every care has been taken to ensure that the file is suitable for use by ISO member bodies. In

the unlikely event that a problem relating to it is found, please inform the Central Secretariat at the address given below.

COPYRIGHT PROTECTED DOCUMENT
© ISO 2007

All rights reserved. Unless otherwise specified, no part of this publication may be reproduced or utilized in any form or by any means,

electronic or mechanical, including photocopying and microfilm, without permission in writing from either ISO at the address below or

ISO's member body in the country of the requester.
ISO copyright office
Case postale 56 • CH-1211 Geneva 20
Tel. + 41 22 749 01 11
Fax + 41 22 749 09 47
E-mail copyright@iso.org
Web www.iso.org
Published in Switzerland
ii © ISO 2007 – All rights reserved
---------------------- Page: 4 ----------------------
SIST ISO 8873-2:2015
ISO 8873-2:2007(E)
Contents Page

Foreword............................................................................................................................................................ iv

Introduction ........................................................................................................................................................ v

1 Scope...................................................................................................................................................... 1

2 Normative references ........................................................................................................................... 1

3 Terms and definitions........................................................................................................................... 2

4 Requirements ........................................................................................................................................ 3

4.1 Manufacturer ......................................................................................................................................... 3

4.2 Spray polyurethane foam contractor .................................................................................................. 3

4.3 Spray polyurethane foam installer ...................................................................................................... 4

4.4 Apprentice installer............................................................................................................................... 6

4.5 Material................................................................................................................................................... 6

4.6 Equipment.............................................................................................................................................. 6

4.7 Installation ............................................................................................................................................. 6

5 Applications........................................................................................................................................... 8

5.1 General................................................................................................................................................... 8

5.2 Air barrier system application ............................................................................................................. 8

5.3 Vapour barrier application ................................................................................................................... 8

5.4 Exterior foundation insulation application......................................................................................... 8

5.5 Interior foundation insulation application.......................................................................................... 8

5.6 Cathedral ceilings, flat ceilings and decks over heated spaces...................................................... 8

5.7 Attic application, exterior (cavity) and interior wall application ...................................................... 8

6 Sampling ................................................................................................................................................ 8

7 Test methods......................................................................................................................................... 9

7.1 Determination of density...................................................................................................................... 9

7.2 Cohesion and adhesion test .............................................................................................................. 10

7.3 Verification of substrate (application surface) preparation............................................................ 10

7.4 Reporting requirements ..................................................................................................................... 10

8 Manufacturer's marking...................................................................................................................... 11

9 Manufacturer’s documentation ......................................................................................................... 12

10 Limitations ........................................................................................................................................... 12

Annex A (normative) Substrate preparation.................................................................................................. 13

Annex B (normative) Selection of chemical components (system)............................................................ 16

Annex C (informative) Climatic factors .......................................................................................................... 17

Annex D (normative) Job-site set up.............................................................................................................. 18

Annex E (informative) Trouble shooting and repair...................................................................................... 20

Annex F (normative) Handling and safety precautions................................................................................ 22

Annex G (normative) Disposal and detoxification of drums........................................................................ 25

Annex H (informative) Daily work record ....................................................................................................... 27

Annex I (informative) Example of job site label............................................................................................. 29

Annex J (informative) Outline of licensed installer training programme.................................................... 30

Annex K (normative) Minimum equipment for site test kit .......................................................................... 36

Bibliography ..................................................................................................................................................... 37

© ISO 2007 – All rights reserved iii
---------------------- Page: 5 ----------------------
SIST ISO 8873-2:2015
ISO 8873-2:2007(E)
Foreword

ISO (the International Organization for Standardization) is a worldwide federation of national standards bodies

(ISO member bodies). The work of preparing International Standards is normally carried out through ISO

technical committees. Each member body interested in a subject for which a technical committee has been

established has the right to be represented on that committee. International organizations, governmental and

non-governmental, in liaison with ISO, also take part in the work. ISO collaborates closely with the

International Electrotechnical Commission (IEC) on all matters of electrotechnical standardization.

International Standards are drafted in accordance with the rules given in the ISO/IEC Directives, Part 2.

The main task of technical committees is to prepare International Standards. Draft International Standards

adopted by the technical committees are circulated to the member bodies for voting. Publication as an

International Standard requires approval by at least 75 % of the member bodies casting a vote.

Attention is drawn to the possibility that some of the elements of this document may be the subject of patent

rights. ISO shall not be held responsible for identifying any or all such patent rights.

ISO 8873-2 was prepared by Technical Committee ISO/TC 61, Plastics, Subcommittee SC 10, Cellular

plastics.

This first edition of ISO 8873-2, together with ISO 8873-1 and ISO 8873-3, cancels and replaces

ISO 8873:1987, which has been technically revised.

ISO 8873 consists of the following parts, under the general title Rigid cellular plastics — Spray-applied

polyurethane foam for thermal insulation:
⎯ Part 1: Material specifications
⎯ Part 2: Application
⎯ Part 3: Test methods
iv © ISO 2007 – All rights reserved
---------------------- Page: 6 ----------------------
SIST ISO 8873-2:2015
ISO 8873-2:2007(E)
Introduction

Spray polyurethane foam for thermal insulation is made by combining two liquid components on the project

site to manufacture a product. As the manufactured product is what provides the physical and thermal

properties desired by the user, it only becomes spray polyurethane foam when it is installed. As such, an

International Standard for the application and installation is required.

This part of ISO 8873 outlines the obligations for the installer of the liquid components that produce the actual

material.

ISO 8873-1 outlines obligations for the manufacturers of spray polyurethane foam liquid components.

ISO 8873-3 provides test methods which have not previously been specified in International Standards.

© ISO 2007 – All rights reserved v
---------------------- Page: 7 ----------------------
SIST ISO 8873-2:2015
---------------------- Page: 8 ----------------------
SIST ISO 8873-2:2015
INTERNATIONAL STANDARD ISO 8873-2:2007(E)
Rigid cellular plastics — Spray-applied polyurethane foam for
thermal insulation —
Part 2:
Application

WARNING — Persons using this document should be familiar with normal laboratory practice, if

applicable. This document does not purport to address all of the safety concerns, if any, associated

with its use. It is the responsibility of the user to establish appropriate safety and health practices and

to ensure compliance with any regulatory requirements.
1 Scope

This part of ISO 8873 outlines requirements for the application of rigid cellular plastic spray polyurethane foam

for thermal insulation. The primary application of the material is for use as thermal insulation. Spray

polyurethane foam can also be used as the air barrier material which forms part of an air barrier assembly in

buildings. Under specific application conditions, the material can be used in vapour barrier applications in a

building assembly (details of the conditions can be obtained from the manufacturer). The application

requirements are for the installation of spray polyurethane foam whether applied on a building site or in a

prefabrication (manufacturing) facility.

This part of ISO 8873 can be used for non-building applications when agreed to by the supplier and the

purchaser.

The requirements include obligations for the manufacturer, the contractor and the installer. The requirements

include the selection of chemical components, application requirements, quality control and documentation of

the application, limitations for the application and requirements for safety and for disposal of associated waste

material and packaging.

Installation of spray polyurethane foam for thermal insulation, according to this part of ISO 8873 requires the

use of materials and/or equipment that could be hazardous (see Warning).
2 Normative references

The following referenced documents are indispensable for the application of this document. For dated

references, only the edition cited applies. For undated references, the latest edition of the referenced

document (including any amendments) applies.

ISO 8873-1, Rigid cellular plastics — Spray-applied polyurethane foam for thermal insulation — Part 1:

Material specifications

ISO/IEC 17024, Conformity assessment — General requirements for bodies operating certification of persons

© ISO 2007 – All rights reserved 1
---------------------- Page: 9 ----------------------
SIST ISO 8873-2:2015
ISO 8873-2:2007(E)
3 Terms and definitions

The following referenced documents are indispensable for the application of this document. For dated

references, only the edition cited applies. For undated references, the latest edition of the referenced

document (including any amendments) applies.
3.1
authority having jurisdiction

officer or officers having authority, under appropriate regulatory instruments, to exercise enforcement

3.2
apprentice installer

individual who applies spray polyurethane foam on the job site, under the direct supervision of a spray

polyurethane installer
3.3
certification organization

impartial body possessing the necessary competence and reliability to operate a certification system in

accordance with ISO/IEC 17024, in which the interests of all parties concerned with the functioning of the

system are represented
3.4
equipment manufacturer

manufacturer of equipment designed for spray-application of rigid polyurethane cellular plastic thermal

insulation
3.5
in-situ thermal insulation

thermal insulation product produced or taking its final form at the site of application and which achieves its

properties after installation
3.6
site quality assurance programme

quality assurance programme (QAP) based upon quality standards, which ties the chemical system

components manufacturer (supplier), the contractor and the installer together for the installation of spray

polyurethane foam

NOTE 1 The QAP should outline the responsibilities and obligations of each of the three parties. The QAP should

outline the training and certification requirements for each of the three parties and should include a site inspection of the

installation of spray polyurethane foam.
NOTE 2 ISO 9001 and ISO 12576-2 are examples of quality standards.
3.7
spray polyurethane foam

rigid cellular plastic material with substantially closed cell structure based on polyurethanes, which is foamed

in situ by the catalysed reaction of polyisocyanates and polyhydroxyl compounds, expanded with blowing

agents
3.8
spray polyurethane foam contractor

individual, organization or corporation who is responsible for all requirements and obligations for the

installation of the product
3.9
spray polyurethane foam installer

individual or worker who applies the chemical components by mixing and spraying them to form the rigid

cellular plastic spray polyurethane foam product

NOTE The installer is responsible for the actual installation and site requirements identified by the manufacturer

and/or this part of ISO 8873 for application of the product. The installer should be trained and qualified as having

2 © ISO 2007 – All rights reserved
---------------------- Page: 10 ----------------------
SIST ISO 8873-2:2015
ISO 8873-2:2007(E)

demonstrated the required knowledge for proper application of the product by a certification organization (CO). The

installer should follow the requirements for installation and the obligations for installers identified by the manufacturer and

this part of ISO 8873.
3.10
spray polyurethane foam system manufacturer

manufacturer/supplier of the liquid chemical components, polyisocyanates and polyhydroxyl blends containing

also flame retardants, blowing agent and catalysts (system), which are designed to be mixed and sprayed to

form rigid polyurethane foam insulation material in situ
4 Requirements
4.1 Manufacturer
The manufacturer (supplier)
a) shall produce material that meets the requirements of ISO 8873-1,

b) shall mark and label the shipping containers to declare that the material meets the requiements of

ISO 8773-1,

c) shall declare the certification organization that is responsible for delivering the site quality assurance

programme for their product, and

d) shall ensure that the material is installed by a spray polyurethane foam contractor using a spray

polyurethane foam installer in accordance with this part of ISO 8873 and the instructions given by the

chemical manufacturer.
4.2 Spray polyurethane foam contractor
The spray polyurethane foam contractor

a) shall produce material that meets the requirements of ISO 8873-1 and shall comply with all requirements

of this part of ISO 8873;
b) shall select the material that is appropriate for the installation;

c) shall procure material which complies with ISO 8873-1 from a spray polyurethane foam system

manufacturer;

d) shall verify, through the use of drum labels or other documentation, that the material received complies

with ISO 8873-1;

e) shall have at least one trained and certification organization approved spray polyurethane foam installer

on each job site during the application of the spray polyurethane foam thermal insulation;

f) shall be responsible for all aspects of the installation of the material; all regulations shall be complied with

during the installation of the material; the completed application shall comply with all appropriate

regulations such as building codes;

g) shall ensure that the spray polyurethane foam installer has successfully completed a training course

approved by the manufacturer and the certification organization; the spray polyurethane foam installer

shall successfully complete the training and have obtained certification as a spray polyurethane foam

installer;

h) shall provide the spray polyurethane foam installer with proper equipment to install spray polyurethane

foam; equipment may include, but is not limited to, transfer pumps, a proportioner unit, hoses, hose

heaters, spray guns, compressors and generators;
© ISO 2007 – All rights reserved 3
---------------------- Page: 11 ----------------------
SIST ISO 8873-2:2015
ISO 8873-2:2007(E)

i) shall provide, or ensure that the spray polyurethane foam installer has, proper personnel protection,

which shall include a positive fresh-air-supplied full-face respirator; other protection includes head

protection, eye protection, ear protection, body protection, hand protection and foot protection;

j) shall provide, on each job site, a test kit meeting the requirements outlined in Annex K for use by the

spray polyurethane foam installer to conduct the testing required for thermal insulation in accordance with

this part of ISO 8873;

k) shall ensure that the spray polyurethane foam installer conducts the daily testing;

l) shall ensure that the installer completes daily work records in accordance with the site quality assurance

programme; this daily work record shall contain
⎯ information on the job site, date and material used,
⎯ name of the installer and certification number,
⎯ application conditions and environmental conditions,
⎯ results of the testing completed on site,
⎯ whether the material complies with ISO 8873-1,
⎯ whether the project required isolation and ventilation, and
⎯ whether the material used has been evaluated by a third party;

m) shall supply the installer with all the forms required; the daily work record shall be completed at the

beginning of each day, each time a material batch is changed, and when the job site is changed within a

given day;

n) shall keep the daily work records for a period of seven years; these records shall be made available upon

request, within a reasonable time, to the manufacturer or the certification organization; the minimum

information required for a daily work record is shown in Annex H;

o) shall provide a job site declaration form containing the minimum information outlined in Annex I to the

customer within 30 days of completion of the project;

p) shall ensure that the spray polyurethane foam installer follows the site quality assurance programme

developed by the certification organization; a copy of the site quality assurance programme shall be made

available upon request;
q) shall maintain the installation equipment in proper working order;

r) where a separate contractor is responsible for the thermal barrier installation and when the authority

having jurisdiction requires a thermal barrier for that application, the spray polyurethane foam contractor

shall notify the building owner or the owner’s representative in writing of the requirement for a thermal

barrier and the flammability hazard, which could exist until such time that the foam is covered.

4.3 Spray polyurethane foam installer
The installer

a) shall produce material that meets the requirements of ISO 8873-1 in accordance with this part of

ISO 8873, the instructions provided by the spray polyurethane foam system manufacturer and the spray

polyurethane foam contractor;
4 © ISO 2007 – All rights reserved
---------------------- Page: 12 ----------------------
SIST ISO 8873-2:2015
ISO 8873-2:2007(E)

b) shall confirm, using drum labels or other documentation, that the liquid chemicals to be used on site have

been declared by the manufacturer to comply with ISO 8873-1 before commencing installation;

c) shall be responsible for the on-site installation of the material, safe handling and storage of the material,

proper isolation of the spray area, warning signs when spraying is in progress, site housekeeping, and

their own personal and the crew's health and safety; the spray polyurethane foam installer shall wear

proper personnel protection, which includes head protection, eye protection, a positive fresh-air-supplied

full-face respirator, ear protection, body protection, hand protection and foot protection in compliance with

regulations;

d) shall successfully complete a training course approved by the manufacturer and the designated

certification organization; the installer shall obtain certification from the designated certification

organization as a spray polyurethane foam installer; a recommended training outline is shown in Annex J;

e) shall follow all operating instructions for the equipment provided by the equipment manufacturer; this

equipment may include, but is not limited to, transfer pumps, a proportioner unit, hoses, hose heaters,

guns, compressors and generators; the installer shall follow instructions from the equipment manufacturer

for the operation, maintenance and cleaning of the equipment used for installation; the spray

polyurethane foam installer shall follow all safety procedures required by the equipment manufacturer;

f) shall verify, through a material label, that the material on site has been declared by the manufacturer to

comply with ISO 8873-1;
g) shall verify that the substrate has been properly prepared;

h) shall verify that the environmental conditions are within the range approved by the spray polyurethane

foam system manufacturer;
i) shall set the equipment to the proper operating parameters;

j) shall install the material in accordance with this part of ISO 8873 and the manufacturer’s instructions;

k) shall comply with all requirements of the site quality assurance programme provided by the certification

organization;

l) shall apply the spray polyurethane foam so that the surface is reasonably smooth and of consistent

thickness;

m) shall exercise an ongoing visual and physical quality control check throughout the spray application to

ensure proper adhesion to the substrate and proper quality of the spray polyurethane foam;

n) shall check with a depth gauge (see Figure 1) the thickness of the the applied foam on a continual basis

and shall provide the minimum thickness specified by the owner;

o) shall conduct density, adhesion, cohesion and substrate verification at the beginning of each day, each

time a material batch is changed, and when the job site is changed within a given day;

p) shall complete daily work records in accordance with the site quality assurance programme; this daily

work record shall contain
⎯ information on the job site (see Annex D), date and material used,
⎯ name of the installer and certification number,
⎯ application conditions and environmental conditions,
⎯ results of the testing completed on site,
⎯ whether the material complies with ISO 8873-1,
© ISO 2007 – All rights reserved 5
---------------------- Page: 13 ----------------------
SIST ISO 8873-2:2015
ISO 8873-2:2007(E)
⎯ whether project required isolation and ventilation, and
⎯ whether the material used has been evaluated by a third party;

q) shall at the end of each working day, remove all waste from the construction site and dispose of it in a

safe and proper manner, in accordance with local, provincial and federal requirements;

r) shall, in cases where an apprentice installer is applying the material, ensure that the apprentice is under

the direct supervision of the spray polyurethane foam installer who has the responsibility for the

application.

The daily work record shall be completed at the beginning of each day, each time a material batch is changed,

and when the job site is changed within a given day; the minimum information required for a daily work record

is shown in Annex H.
4.4 Apprentice installer
The apprentice installer

a) shall only install spray polyurethane foam thermal insulation under the direct and constant supervision of

a spray polyurethane foam installer,

b) shall be required to meet all the same requirements as a spray polyurethane foam installer when

installing spray polyurethane foam, and

c) shall wear proper personnel protection, which includes head protection, eye protection, a positive fresh-

air-supplied full-face respirator, ear protection, body protection, hand protection and foot protection in

compliance with regulations.
4.5 Material

The spray polyurethane foam system, when stored in accordance with the chemical manufacturer’s

instructions, properly mixed and spray applied as required in 4.3, and within the shelf life of the chemicals as

declared by the manufacturer, shall produce a finished product that meets the requirements of the ISO 8873-1.

Application requirements, which will affect the performance of the finished product, shall be considered when

choosing the chemical components (see Annex B).

When installed as given in 4.3, the spray polyurethane foam shall not present a health hazard to the potential

occupants, nor shall the cured insulation have any residual odour.
4.6 Equipment

The chemical components shall be mixed and sprayed with a commercially available spray gun and a fixed-

ratio, positive-displacement proportioning unit, specially designed for the application of spray polyurethane

foam. The manufacturer shall recommend appropriate equipment to be used.

Operation, maintenance, safety and cleaning procedures detailed in the equipment manufacturer’s manual

shall be strictly followed.
4.7 Installation

Special applications which require properties in addition to those specified in this part of ISO 8873 shall be

agreed upon by the interested parties prior to commencement of the installation.

Prior to application, a test shall be run to ensure that proper equipment settings have been selected.

Consideration shall be given to reactivity, spray pattern, adhesion to substrate and the appearance of the

spray polyurethane foam to ensure that each of these properties meets the requirements specified by the

6 © ISO 2007 – All rights reserved
---------------------- Page: 14 ----------------------
SIST ISO 8873-2:2015
ISO 8873-2:2007(E)
spray polyurethane foam system manufacturer.
...