Lightning protection system components (LPSC) - Part 1: Requirements for connection components (IEC 62561-1:2023)

This part of IEC 62561 specifies the requirements and tests for metallic connection
components that form part of a lightning protection system (LPS). Typically, these can be
connectors, clamps, bonding and bridging components, expansion pieces and test joints.
For the purposes of this document the following connection types are considered as
connection components: exothermic, brazing, welding, clamping, crimping, seaming, screwing
or bolting.
Testing of components for an explosive atmosphere is not covered by this document.

Blitzschutzsystembauteile (LPSC) - Teil 1: Anforderungen an Verbindungsbauteile (IEC 62561-1:2023)

Composants des systèmes de protection contre la foudre (CSPF) - Parte 1: Exigences pour les composants de connexion (IEC 62561-1:2023)

IEC 62561-1:2023 est disponible sous forme de IEC 62561-1:2023 RLV qui contient la Norme internationale et sa version Redline, illustrant les modifications du contenu technique depuis l'édition précédente.

L'IEC 62561-1:2023 spécifie les exigences et les essais applicables aux composants métalliques de connexion qui font partie d'un système de protection contre la foudre (SPF). Il peut s'agir, en général, des connecteurs, des colliers de serrage, des composants de collage et de pontage, des pièces de dilatation et des joints de contrôle. Cette troisième édition annule et remplace la deuxième édition parue en 2017. Cette édition constitue une révision technique. Cette édition inclut les modifications techniques majeures suivantes par rapport à l'édition précédente:
a) les définitions des types de connexions mentionnés dans le domaine d'application du document ont été ajoutées;
b) la classification des emplacements a été développée de façon détaillée;
c) le document a été mis à jour conformément à la nouvelle édition de l'ISO 22479:2019 concernant le traitement en atmosphère humide sulfureuse;
d) la nouvelle Annexe E normative concernant les procédures d'essai simplifiées a été introduite.

Elementi za zaščito pred strelo (LPSC) - 1. del: Zahteve za spojne komponente (IEC 62561-1:2023)

Ta del standarda IEC 62561 določa zahteve in preskuse za kovinske spojne komponente, ki so del sistema za zaščito pred strelo (LPS). Običajno so to lahko konektorji, spojke, vezne in premostitvene komponente, ekspanzijski kosi in preskusni spoji.
Za namene tega dokumenta se kot spojne komponente obravnavajo naslednje vrste spojev: eksotermni, spajkani, varjeni, spajani, stiskani, spojeni, vijačeni ali netani.
Preskušanje komponent za eksplozivno atmosfero v tem dokumentu ni zajeto.

General Information

Status
Published
Publication Date
31-May-2023
Technical Committee
Current Stage
6060 - National Implementation/Publication (Adopted Project)
Start Date
17-May-2023
Due Date
22-Jul-2023
Completion Date
01-Jun-2023

Relations

Buy Standard

Standard
EN IEC 62561-1:2023
English language
32 pages
sale 10% off
Preview
sale 10% off
Preview
e-Library read for
1 day

Standards Content (Sample)

SLOVENSKI STANDARD
SIST EN IEC 62561-1:2023
01-julij-2023
Elementi za zaščito pred strelo (LPSC) - 1. del: Zahteve za spojne komponente
(IEC 62561-1:2023)
Lightning protection system components (LPSC) - Part 1: Requirements for connection
components (IEC 62561-1:2023)
Blitzschutzsystembauteile (LPSC) - Teil 1: Anforderungen an Verbindungsbauteile (IEC
62561-1:2023)
Composants des systèmes de protection contre la foudre (CSPF) - Parte 1: Exigences
pour les composants de connexion (IEC 62561-1:2023)
Ta slovenski standard je istoveten z: EN IEC 62561-1:2023
ICS:
29.120.20 Spojni elementi Connecting devices
91.120.40 Zaščita pred strelo Lightning protection
SIST EN IEC 62561-1:2023 en
2003-01.Slovenski inštitut za standardizacijo. Razmnoževanje celote ali delov tega standarda ni dovoljeno.

---------------------- Page: 1 ----------------------
SIST EN IEC 62561-1:2023

---------------------- Page: 2 ----------------------
SIST EN IEC 62561-1:2023


EUROPEAN STANDARD EN IEC 62561-1

NORME EUROPÉENNE

EUROPÄISCHE NORM May 2023
ICS 29.020; 91.120.40 Supersedes EN 62561-1:2017
English Version
Lightning protection system components (LPSC) - Part 1:
Requirements for connection components
(IEC 62561-1:2023)
Composants des systèmes de protection contre la foudre Blitzschutzsystembauteile (LPSC) - Teil 1: Anforderungen
(CSPF) - Partie 1: Exigences pour les composants de an Verbindungsbauteile
connexion (IEC 62561-1:2023)
(IEC 62561-1:2023)
This European Standard was approved by CENELEC on 2023-05-04. CENELEC members are bound to comply with the CEN/CENELEC
Internal Regulations which stipulate the conditions for giving this European Standard the status of a national standard without any alteration.
Up-to-date lists and bibliographical references concerning such national standards may be obtained on application to the CEN-CENELEC
Management Centre or to any CENELEC member.
This European Standard exists in three official versions (English, French, German). A version in any other language made by translation
under the responsibility of a CENELEC member into its own language and notified to the CEN-CENELEC Management Centre has the
same status as the official versions.
CENELEC members are the national electrotechnical committees of Austria, Belgium, Bulgaria, Croatia, Cyprus, the Czech Republic,
Denmark, Estonia, Finland, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta, the
Netherlands, Norway, Poland, Portugal, Republic of North Macedonia, Romania, Serbia, Slovakia, Slovenia, Spain, Sweden, Switzerland,
Türkiye and the United Kingdom.


European Committee for Electrotechnical Standardization
Comité Européen de Normalisation Electrotechnique
Europäisches Komitee für Elektrotechnische Normung
CEN-CENELEC Management Centre: Rue de la Science 23, B-1040 Brussels
© 2023 CENELEC All rights of exploitation in any form and by any means reserved worldwide for CENELEC Members.
 Ref. No. EN IEC 62561-1:2023 E

---------------------- Page: 3 ----------------------
SIST EN IEC 62561-1:2023
EN IEC 62561-1:2023 (E)
European foreword
The text of document 81/721/FDIS, future edition 3 of IEC 62561-1, prepared by IEC/TC 81 "Lightning
protection" was submitted to the IEC-CENELEC parallel vote and approved by CENELEC as
EN IEC 62561-1:2023.
The following dates are fixed:
• latest date by which the document has to be implemented at national (dop) 2024-02-04
level by publication of an identical national standard or by endorsement
• latest date by which the national standards conflicting with the (dow) 2026-05-04
document have to be withdrawn

This document supersedes EN 62561-1:2017 and all of its amendments and corrigenda (if any).
Attention is drawn to the possibility that some of the elements of this document may be the subject of
patent rights. CENELEC shall not be held responsible for identifying any or all such patent rights.
Any feedback and questions on this document should be directed to the users’ national committee. A
complete listing of these bodies can be found on the CENELEC website.
Endorsement notice
The text of the International Standard IEC 62561-1:2023 was approved by CENELEC as a European
Standard without any modification.
In the official version, for Bibliography, the following note has to be added for the standard indicated:
IEC 62305 (series) NOTE Approved as EN 62305 (series)
2

---------------------- Page: 4 ----------------------
SIST EN IEC 62561-1:2023
EN IEC 62561-1:2023 (E)
Annex ZA
(normative)

Normative references to international publications
with their corresponding European publications
The following documents are referred to in the text in such a way that some or all of their content
constitutes requirements of this document. For dated references, only the edition cited applies. For
undated references, the latest edition of the referenced document (including any amendments)
applies.
NOTE 1 Where an International Publication has been modified by common modifications, indicated by (mod), the
relevant EN/HD applies.
NOTE 2 Up-to-date information on the latest versions of the European Standards listed in this annex is available
here: www.cencenelec.eu.
Publication Year Title EN/HD Year
IEC 60068-2-52 2017 Environmental testing - Part 2-52: Tests - EN IEC 60068-2-52 2018
Test Kb: Salt mist, cyclic (sodium chloride
solution)
IEC 62561-2 - Lightning protection system components EN IEC 62561-2 -
(LPSC) - Part 2: Requirements for
conductors and earth electrodes
ISO 6957 1988 Copper alloys; ammonia test for stress - -
corrosion resistance
ISO 22479 2019 Corrosion of metals and alloys - Sulfur EN ISO 22479 2022
dioxide test in a humid atmosphere (fixed
gas method)

3

---------------------- Page: 5 ----------------------
SIST EN IEC 62561-1:2023

---------------------- Page: 6 ----------------------
SIST EN IEC 62561-1:2023



IEC 62561-1

®


Edition 3.0 2023-03




INTERNATIONAL



STANDARD




NORME



INTERNATIONALE











Lightning protection system components (LPSC) –

Part 1: Requirements for connection components




Composants des systèmes de protection contre la foudre (CSPF) –

Partie 1: Exigences pour les composants de connexion
















INTERNATIONAL

ELECTROTECHNICAL

COMMISSION


COMMISSION

ELECTROTECHNIQUE


INTERNATIONALE




ICS 29.020; 91.120.40 ISBN 978-2-8322-6650-2



Warning! Make sure that you obtained this publication from an authorized distributor.

Attention! Veuillez vous assurer que vous avez obtenu cette publication via un distributeur agréé.

® Registered trademark of the International Electrotechnical Commission
Marque déposée de la Commission Electrotechnique Internationale

---------------------- Page: 7 ----------------------
SIST EN IEC 62561-1:2023
– 2 – IEC 62561-1:2023 © IEC 2023
CONTENTS
FOREWORD . 4
INTRODUCTION . 6
1 Scope . 7
2 Normative references . 7
3 Terms and definitions . 7
4 Classification . 11
4.1 According to the ability to withstand lightning current . 11
4.2 According to the installation location . 11
4.3 According to the mechanical behaviour of connection components . 11
4.4 According to whether or not a connection is permanent . 11
5 Requirements . 11
5.1 General . 11
5.2 Documentation and installation instructions . 11
5.3 Marking . 12
5.3.1 Content of marking . 12
5.3.2 Durability and legibility . 12
5.4 Lightning current carrying capability . 12
5.5 Static mechanical withstand capability . 12
5.6 Permanent connection . 12
5.7 Non-permanent connection . 13
5.8 Dismantling of test joints . 13
5.9 Expansion piece . 13
6 Tests . 13
6.1 General test conditions . 13
6.2 Documentation and installation instructions . 14
6.2.1 General test conditions . 14
6.2.2 Acceptance criteria . 14
6.3 Marking test . 14
6.3.1 General test conditions . 14
6.3.2 Acceptance criteria . 14
6.4 Preparation of the specimen . 14
6.5 Conditioning and ageing . 19
6.6 Electrical test . 19
6.6.1 General test conditions . 19
6.6.2 Acceptance criteria . 20
6.7 Static mechanical withstand-capability test . 21
7 Electromagnetic compatibility (EMC) . 21
8 Structure and content of the test report . 22
8.1 General . 22
8.2 Report identification . 22
8.3 Specimen description . 22
8.4 Conductor . 22
8.5 Standards and references . 23
8.6 Test procedure . 23
8.7 Testing equipment description . 23
8.8 Measuring instruments description . 23

---------------------- Page: 8 ----------------------
SIST EN IEC 62561-1:2023
IEC 62561-1:2023 © IEC 2023 – 3 –
8.9 Results and parameters recorded . 23
8.10 Statement of pass or fail . 23
Annex A (normative) Summary of the requirements and corresponding tests . 24
Annex B (informative) Typical connection arrangements for various LPSC . 25
Annex C (normative) Flow chart of tests for connection components . 26
Annex D (normative) Conditioning and ageing for connection components . 27
D.1 General . 27
D.2 Salt mist treatment . 27
D.3 Humid sulphurous atmosphere treatment . 27
D.4 Ammonia atmosphere treatment. 27
Annex E (normative) Reduced test procedures . 28
Bibliography . 29

Figure 1 – Basic arrangement of specimen with cross-connection component . 15
Figure 2 – Basic arrangement of specimen with parallel connection component . 16
Figure 3 – Basic arrangement of specimen with expansion piece or bridging
component . 17
Figure 4 – Basic arrangement of specimen with equipotential bonding bar . 18
Figure 5 – Basic arrangement of specimen with clamped connection of reinforcing

rods . 18
Figure 6 – Basic arrangement of specimen with welded, brazed or exothermic
connections of reinforcing rods . 19
Figure 7 – Basic arrangement for contact measurement of expansion piece or bridging
component . 20
Figure 8 – Examples of sequence of loosening of bolts and screws . 21
Figure B.1 – Typical arrangements for various LPSC . 25
Figure C.1 – Flowchart of tests for connection components . 26

Table 1 – Lightning impulse current ( I ) parameters . 20
imp
Table A.1 – Requirements and corresponding tests . 24
Table E.1 – Reduced test procedures for connection components complying with

IEC 62561-1:2017 or IEC 62561-1:2012 . 28

---------------------- Page: 9 ----------------------
SIST EN IEC 62561-1:2023
– 4 – IEC 62561-1:2023 © IEC 2023
INTERNATIONAL ELECTROTECHNICAL COMMISSION
____________

LIGHTNING PROTECTION SYSTEM COMPONENTS (LPSC) –

Part 1: Requirements for connection components

FOREWORD
1) The International Electrotechnical Commission (IEC) is a worldwide organization for standardization comprising
all national electrotechnical committees (IEC National Committees). The object of IEC is to promote
international co-operation on all questions concerning standardization in the electrical and electronic fields. To
this end and in addition to other activities, IEC publishes International Standards, Technical Specifications,
Technical Reports, Publicly Available Specifications (PAS) and Guides (hereafter referred to as “IEC
Publication(s)”). Their preparation is entrusted to technical committees; any IEC National Committee interested
in the subject dealt with may participate in this preparatory work. International, governmental and non-
governmental organizations liaising with the IEC also participate in this preparation. IEC collaborates closely
with the International Organization for Standardization (ISO) in accordance with conditions determined by
agreement between the two organizations.
2) The formal decisions or agreements of IEC on technical matters express, as nearly as possible, an international
consensus of opinion on the relevant subjects since each technical committee has representation from all
interested IEC National Committees.
3) IEC Publications have the form of recommendations for international use and are accepted by IEC National
Committees in that sense. While all reasonable efforts are made to ensure that the technical content of IEC
Publications is accurate, IEC cannot be held responsible for the way in which they are used or for any
misinterpretation by any end user.
4) In order to promote international uniformity, IEC National Committees undertake to apply IEC Publications
transparently to the maximum extent possible in their national and regional publications. Any divergence
between any IEC Publication and the corresponding national or regional publication shall be clearly indicated in
the latter.
5) IEC itself does not provide any attestation of conformity. Independent certification bodies provide conformity
assessment services and, in some areas, access to IEC marks of conformity. IEC is not responsible for any
services carried out by independent certification bodies.
6) All users should ensure that they have the latest edition of this publication.
7) No liability shall attach to IEC or its directors, employees, servants or agents including individual experts and
members of its technical committees and IEC National Committees for any personal injury, property damage or
other damage of any nature whatsoever, whether direct or indirect, or for costs (including legal fees) and
expenses arising out of the publication, use of, or reliance upon, this IEC Publication or any other IEC
Publications.
8) Attention is drawn to the Normative references cited in this publication. Use of the referenced publications is
indispensable for the correct application of this publication.
9) Attention is drawn to the possibility that some of the elements of this IEC Publication may be the subject of
patent rights. IEC shall not be held responsible for identifying any or all such patent rights.
IEC 62561-1has been prepared by IEC technical committee 81: Lightning protection. It is an
International Standard.
This third edition cancels and replaces the second edition published in 2017. This edition
constitutes a technical revision.
This edition includes the following significant technical changes with respect to the previous
edition:
a) definitions of connection types mentioned in the scope have been added;
b) location classification has been expanded in detail;
c) the document has been updated in line with the new edition of ISO 22479:2019 on humid
sulphurous atmosphere treatment;
d) a new normative Annex E for reduced test procedures has been introduced.

---------------------- Page: 10 ----------------------
SIST EN IEC 62561-1:2023
IEC 62561-1:2023 © IEC 2023 – 5 –
The text of this International Standard is based on the following documents:
Draft Report on voting
81/721/FDIS 81/724/RVD

Full information on the voting for its approval can be found in the report on voting indicated in
the above table.
The language used for the development of this International Standard is English.
This document was drafted in accordance with ISO/IEC Directives, Part 2, and developed in
accordance with ISO/IEC Directives, Part 1 and ISO/IEC Directives, IEC Supplement,
available at www.iec.ch/members_experts/refdocs. The main document types developed by
IEC are described in greater detail at www.iec.ch/publications.
A list of all parts in the IEC 62561 series, published under the general title Lightning
protection system components (LPSC), can be found on the IEC website.
The committee has decided that the contents of this document will remain unchanged until the
stability date indicated on the IEC website under webstore.iec.ch in the data related to the
specific document. At this date, the document will be
• reconfirmed,
• withdrawn,
• replaced by a revised edition, or
• amended.

---------------------- Page: 11 ----------------------
SIST EN IEC 62561-1:2023
– 6 – IEC 62561-1:2023 © IEC 2023
INTRODUCTION
This part of IEC 62561 deals with the requirements and tests for lightning protection system
components (LPSC) used for the installation of a lightning protection system (LPS) designed
and implemented according to the IEC 62305 series.

---------------------- Page: 12 ----------------------
SIST EN IEC 62561-1:2023
IEC 62561-1:2023 © IEC 2023 – 7 –
LIGHTNING PROTECTION SYSTEM COMPONENTS (LPSC) –

Part 1: Requirements for connection components



1 Scope
This part of IEC 62561 specifies the requirements and tests for metallic connection
components that form part of a lightning protection system (LPS). Typically, these can be
connectors, clamps, bonding and bridging components, expansion pieces and test joints.
For the purposes of this document the following connection types are considered as
connection components: exothermic, brazing, welding, clamping, crimping, seaming, screwing
or bolting.
Testing of components for an explosive atmosphere is not covered by this document.
2 Normative references
The following documents are referred to in the text in such a way that some or all of their
content constitutes requirements of this document. For dated references, only the edition
cited applies. For undated references, the latest edition of the referenced document (including
any amendments) applies.
IEC 60068-2-52:2017, Environmental testing – Part 2-52: Tests – Test Kb: Salt mist, cyclic
(sodium chloride solution)
IEC 62561-2, Lightning protection system components (LPSC) – Part 2: Requirements for
conductors and earth electrodes
ISO 6957:1988, Copper alloys – Ammonia test for stress corrosion resistance
ISO 22479:2019, Corrosion of metals and alloys – Sulfur dioxide test in a humid atmosphere
(fixed gas method)
3 Terms and definitions
For the purposes of this document, the following terms and definitions apply.
ISO and IEC maintain terminology databases for use in standardization at the following
addresses:
• IEC Electropedia: available at http://www.electropedia.org/
• ISO Online browsing platform: available at http://www.iso.org/obp
3.1
connection component
part of an external LPS which is used for the connection of conductors to each other or to
metal installations
EXAMPLE Examples of connection components are given in Clause 1.

---------------------- Page: 13 ----------------------
SIST EN IEC 62561-1:2023
– 8 – IEC 62561-1:2023 © IEC 2023
3.2
metal installation
extended metal items in the structure to be protected which can form a path for lightning
current
EXAMPLE Pipes, staircases, elevator guide rails, ventilation, heating and air conditioning ducts, and
interconnected reinforcing steel.

3.3
conductor
element intended to carry electric current
Note 1 to entry: A metal installation is not intended to carry electrical current.
[SOURCE: IEC 60050-151:2001, 151-12-05, modified – The notes have been replaced with a
new Note 1 to entry.]
3.4
bridging component
connection component for the connection of metal installations
3.5
expansion piece
connection component designed to compensate for changes in length in conductors or metal
installations or both caused by temperature changes
3.6
connector
connection component to interconnect two or more conductors
3.7
clamp
connection component for the connection of conductors to metal installations
3.8
pipe clamp
clamp for the connection of conductors to metal pipes
3.9
test joint
connection component designed to facilitate electrical testing and measurement of LPS
components
3.10
connection range
minimum to maximum range for which a specific connection component is designed to be
used
3.11
bonding
technique for joining one object to another
[SOURCE: IEC 60050-523:2018, 523-06-01, modified – The example has been deleted.]

---------------------- Page: 14 ----------------------
SIST EN IEC 62561-1:2023
IEC 62561-1:2023 © IEC 2023 – 9 –
3.12
bonding bar
connection component such as a metal bar on which metal installations, external conductive
parts, electric power and telecommunication lines and other cables can be connected to an
LPS
3.13
type test
test made before supplying a type of material covered by IEC 62561-1 on a general
commercial basis, in order to demonstrate satisfactory performance characteristics to meet
the intended application
3.14
permanent connection
connection that cannot or is not intended to be dismantled
3.15
non-permanent connection
connection that can or is intended to be dismantled
3.16
exothermic connection
welding process that employs molten metal to permanently join the conductors
Note 1 to entry: The electrical connection suitability and electrical durability of the exothermic connection is
tested using a lightning current test.
3.17
brazed connection
metal-joining process in which two or more metal items are joined together by melting and
flowing a filler metal into the joint
Note 1 to entry: The electrical connection suitability and electrical durability of the brazed connection is tested
using a lightning current test.
3.18
welded connection
fabrication process that joins materials, usually metals
Note 1 to entry: The electrical connection suitability and electrical durability of the welded connection is tested
using a lightning current test.
3.19
force-locked connection
connection between two metal parts which does not allow any relative movement due to
thermal expansion and to environmental load, for example snow, ice, wind
EXAMPLE Connection by means of crimping, clamping, bolting or screwing.
Note 1 to entry: The electrical connection suitability and electrical durability of the force-locked connection is
tested using a lightning current test.
3.20
form-locked connection
connection between two metal parts which allows a small relative movement of metal parts due to thermal
expansion and to environmental load, for example snow, ice, wind
EXAMPLE Connection by means of seaming, overlapping and zipping, locked overlapping or hooking.
Note 1 to entry: The electrical connection suitability and electrical durability of the form-locked connection is
tested using a lightning current test.

---------------------- Page: 15 ----------------------
SIST EN IEC 62561-1:2023
– 10 – IEC 62561-1:2023 © IEC 2023
3.21
clamped connection
force-locked connection, which can usually be disassembled, between two components
Note 1 to entry: The electrical connection suitability and electrical durability of the clamped connection is tested
using a lightning current test.
3.22
crimped connection
connection method of permanently attaching a termination to a conductor by pressure
deformation or by reshaping the barrel around the conductor to establish good electrical and
mechanical connection
Note 1 to entry: Crimping as a means of achieving a connection between two conductors may not always require
an additional component to achieve the final connection.
Note 2 to entry: The electrical connection suitability and electrical durability of the crimped connection is tested
using a lightning current test.
[SOURCE: IEC 60050-581:2008, 581-23-10, modified – The term "crimping" has been
replaced with "crimped connection", in the definition "method" has been replaced with
"connection method" and the notes to entry have been added.]
3.23
seamed connection
form-locked connection created by bending of the edges of two adjacent metal sheets
bringing them into intimate contact in a way that they cannot be separated by natural action
Note 1 to entry: The electrical connection suitability and electrical durability of the seamed connection is tested
using a lightning current test.
3.24
screwed connection
force-locked connection, which can be disassembled, between two components which have
threads of their own and can be bolted directly
Note 1 to entry: The electrical connection suitability and electrical durability of the screwed connection is tested
using a lightning current test.
3.25
bolted connection
force-locked connection, which can be disassembled, between two components which can be
bolted indirectly by means of third components (bolts and nuts)
Note 1 to entry: The electrical connection suitability and electrical durability of the bolted connection
...

Questions, Comments and Discussion

Ask us and Technical Secretary will try to provide an answer. You can facilitate discussion about the standard in here.