ISO/PRF 25074 - Ships and marine technology — Mobile emergency unloading pump system — Technical requirements

Release Date:03-Nov-2026
English language (11 pages)
sale 15% off
sale 15% off
Draft

REDLINE ISO/PRF 25074 - Ships and marine technology — Mobile emergency unloading pump system — Technical requirements

Release Date:03-Nov-2026
English language (11 pages)
sale 15% off
sale 15% off

ISO/PRF 25074 is an ISO technical standard for mobile emergency unloading pump systems used on ships and floating production storage and offloading (FPSO) facilities. It specifies the system’s composition, interfaces, design requirements, acceptance tests, identification, packaging, transportation and storage for manufacturers, users, classification societies and product certification agencies.

What does ISO/PRF 25074 specify?

ISO/PRF 25074 specifies technical requirements for a mobile emergency unloading pump system used to unload liquid cargo when the main cargo pump fails. The document is aimed at oil tankers, chemical tankers and FPSO facilities, where emergency discharge arrangements support cargo safety and pollution prevention.

The document is organized into clauses on scope, normative references, terms and definitions, composition and interface, design requirements, acceptance tests, and identification, packaging, transportation and storage. A bibliography is included for background terminology.

What are the key requirements of ISO/PRF 25074?

ISO/PRF 25074 focuses on system safety, compatibility with cargo and ship installations, pump performance, and factory acceptance testing. In practice, it tells suppliers what the mobile emergency unloading pump system must be able to do, what it must withstand, and how it should be checked before delivery.

  • System composition and interfaces - Clause 4 describes a system made up of a mobile unloading pump unit and a lifting device, with power input and cargo output interfaces. This matters because buyers need to confirm that the equipment can connect to the ship or FPSO facilities and move cargo safely.
  • Electrical and hazardous-area safety - Clause 5.1 requires electrical equipment to meet ship and FPSO safety and explosion-proof requirements, with explosion-proof certification and secure grounding in hazardous areas. This means the system is intended for flammable cargo environments, so electrical design and installation are central.
  • Cargo and hose compatibility - Clause 5.1 requires cargo-contacting parts to be compatible with the cargo, and hose selection to be tested to ISO 6802 and ISO 6803. That tells users to verify material compatibility and hose performance before putting the system into service.
  • Core operating functions - Clause 5.2 requires lifting and holding, unloading after main pump failure, and safety protection functions. The unloading speed is controlled by the operation control module, so the control arrangement is part of normal operation, not just a convenience feature.
  • Performance acceptance - Clause 5.3 requires pump acceptance tolerances for flow rate, head, efficiency and NPSH to meet grade 2 in ISO 9906. For the lifting device, Clause 5.3 requires the minimum lifting height and smooth lifting and lowering within the time agreed by user and manufacturer.
  • Material and mechanical design - Clauses 5.4 and 5.5 require cargo-suitable materials, suitable sealing materials, a centrifugal pump as the recommended type, rotor balancing to ISO 21940-11, and pressure casing design to ISO 13709. This is the section that guides structural design, material selection and mechanical integrity.
  • Factory acceptance tests - Clause 6 covers pressure tests, running tests, performance tests, no-load and load tests, overload checks, and mechanical locking checks. This is the practical gate before delivery: the equipment has to demonstrate leak tightness, stable running, rated performance and safe lifting behavior.
  • Identification, packaging, transport and storage - Clause 7 requires clear operation signs, nameplates, protected packaging, transport precautions, and storage conditions. For operators and suppliers, this helps preserve equipment condition between delivery, installation and first use.

What terms does ISO/PRF 25074 define?

  • Mobile emergency unloading pump system - A movable pumping system that can be quickly installed to unload liquid cargo in an emergency.
  • Mobile unloading pump unit - The pump, cargo hose, power connection device and pump driver as one combined unit.
  • Lifting device - The set of parts used to lift the mobile unloading pump unit out of the cargo tank.
  • Cargo hose - The flexible hose that connects the pump outlet to the ship or FPSO cargo unloading pipeline.
  • Power connection device - The device that connects the pump to its power supply.
  • Pump driver - The machine that supplies mechanical energy to drive the pump, such as an electric motor or hydraulic motor.
  • Operation control module - The module on the power connection device that controls pump operation and can control speed.
  • FPSO - Floating production storage and offloading facility, a main application environment for this document.

Who uses ISO/PRF 25074?

ISO/PRF 25074 is used by manufacturers developing mobile emergency unloading pump systems, by shipowners and operators buying or specifying them, and by classification societies and product certification agencies checking conformity. It is also relevant to designers and maintenance teams working on oil tankers, chemical tankers and FPSO facilities, especially where emergency cargo discharge arrangements are required.

Which standards are used with ISO/PRF 25074?

  • ISO 5199 - Supports the centrifugal pump design and critical speed requirements.
  • ISO 6802 - Sets the hose impulse test method used for cargo hose selection.
  • ISO 6803 - Provides the hydraulic-pressure impulse test without flexing for hoses.
  • ISO 9906 - Supplies the pump hydraulic performance acceptance test grades and is referenced for performance tolerances and test procedures.
  • ISO 13709 - Supports the design of the centrifugal pump pressure casing.
  • ISO 21940-11 - Provides rotor balancing procedures and tolerances for rotating parts.
  • ISO 17769-1:2012 - Supplies the source definition used for the term pump.

What does the ISO/PRF 25074 document contain?

ISO/PRF 25074 contains two figures that show the overall system arrangement and the mobile unloading pump unit arrangement. It also includes formulas for allowable stress in lifting device components, with the calculation method given in Clause 5.5.2.6.

Clause 6 contains the acceptance test procedures for hydrostatic and pneumatic pressure tests, running tests, performance testing, and lifting device tests. Those procedures are used for factory acceptance, product verification and certification checks.

Clause 7 gives the identification and handling content, including nameplate data, packaging rules, transport precautions and storage conditions. This part is practical for delivery, warehouse handling and preservation before installation or use.

Buy Documents

Draft

ISO/PRF 25074 - Ships and marine technology — Mobile emergency unloading pump system — Technical requirements

Release Date:03-Nov-2026
English language (11 pages)
sale 15% off
sale 15% off
Draft

REDLINE ISO/PRF 25074 - Ships and marine technology — Mobile emergency unloading pump system — Technical requirements

Release Date:03-Nov-2026
English language (11 pages)
sale 15% off
sale 15% off

Get Certified

Connect with accredited certification bodies for this standard

DNV

DNV is an independent assurance and risk management provider.

NA Norway Verified

Lloyd's Register

Lloyd's Register is a global professional services organisation specialising in engineering and technology.

UKAS United Kingdom Verified

Element Materials Technology

Materials testing and product certification.

UKAS United Kingdom Verified

Sponsored listings

Frequently Asked Questions

ISO/PRF 25074 is a draft published by the International Organization for Standardization (ISO). Its full title is "Ships and marine technology — Mobile emergency unloading pump system — Technical requirements". This standard covers: Ships and marine technology — Mobile emergency unloading pump system — Technical requirements

Ships and marine technology — Mobile emergency unloading pump system — Technical requirements

ISO/PRF 25074 is classified under the following ICS (International Classification for Standards) categories: 47.020.50 - Deck equipment and installations; 47.040 - Seagoing vessels; 75.200 - Petroleum products and natural gas handling equipment. The ICS classification helps identify the subject area and facilitates finding related standards.

ISO/PRF 25074 is available in PDF format for immediate download after purchase. The document can be added to your cart and obtained through the secure checkout process. Digital delivery ensures instant access to the complete standard document.

Standards Content (Sample)

Contents

  • Introduction
  • 1 Scope
  • 2 Normative references
  • 3 Terms and definitions
  • 3.1 mobile emergency unloading pump system
  • 3.2 mobile unloading pump unit
  • 3.3 lifting device
  • 3.4 pump
  • 3.5 cargo hose
  • 3.6 power connection device
  • 3.7 pump driver
  • 3.8 operation control module
  • 4 Composition and interface
  • 4.1 Composition
  • 4.2 Interface
  • 5 Design requirements
  • 5.1 General
  • 5.2 Basic functions
  • 5.3 Performance requirements
  • 5.4 Material requirements
  • 5.5 Technical requirements
  • 6 Acceptance tests
  • 6.1 General requirements
  • 6.2 Mobile unloading pump unit test
  • 6.3 Lifting device test
  • 7 Identification, packaging, transportation, storage
  • 7.1 Identification
  • 7.2 Packaging
  • 7.3 Transportation
  • 7.4 Storage
  • Bibliography

Introduction

The mobile emergency unloading pump system is an emergency pumping arrangement of equipment that transports the liquid cargo in the tank of a ship to another tank in or outside of the ship. It is mainly used in chemical tankers, oil tankers and floating production storage and offloading (FPSO) facilities, and is the key element of emergency unloading equipment. At the time of publication of this document, the cargo pumps used in chemical tankers, FPSO facilities and other vessels are arranged in the way of one tank with one pump. When the cargo pump in the cargo tank fails, the cargo cannot be unloaded in time, which has a significant impact on shipping, cargo safety, pollution prevention and other aspects of ship operations. In order to safely complete unloading, emergency measures should be provided to discharge the cargo in case of malfunction. This emergency unloading operation is a requirement explicitly stated in some regulations. For example, in considering the procurement of cargo pumps that apply to ships and FPSO facilities, it is clearly specified that one or two mobile unloading pumps per ship are required to be provided, so that cargo can be unloaded in case of failure of the main cargo pumps.

This document provides requirements for manufacturers to develop mobile emergency unloading pumps and also provides a product acceptance basis for users, classification societies and other product certification agencies.

PROOF/ÉPREUVE

International Standard ISO 25074:2026(en) Ships and marine technology — Mobile emergency unloading pump system — Technical requirements

1 Scope

This document specifies the technical requirements for the composition, interface, design and acceptance tests of the mobile emergency unloading pump system. This document also includes requirements for nameplate, packaging, transportation and storage.

This document is applicable to the mobile emergency unloading pump systems on ships such as oil tankers and chemical tankers, as well as floating production storage and offloading (FPSO) facilities.

2 Normative references

The following documents are referred to in the text in such a way that some or all of their content constitutes requirements of this document. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies. ISO 5199, Technical specifications for centrifugal pumps — Class II ISO 6802, Rubber or plastics hoses and hose assemblies — Hydraulic impulse test with flexing ISO 6803, Rubber or plastics hoses and hose assemblies — Hydraulic-pressure impulse test without flexing ISO 9906, Rotodynamic pumps — Hydraulic performance acceptance tests — Grades 1, 2 and 3 ISO 13709, Centrifugal pumps for petroleum, petrochemical and natural gas industries ISO 21940-11, Mechanical vibration — Rotor balancing — Part 11: Procedures and tolerances for rotors with rigid behaviour

3 Terms and definitions

For the purposes of this document, the terms and definitions given in ISO 9906, ISO 13709 and the following apply.

ISO and IEC maintain terminology databases for use in standardization at the following addresses:

  • ISO Online browsing platform: available at https:// www .iso .org/ obp
  • IEC Electropedia: available at https:// www .electropedia .org/

3.1 mobile emergency unloading pump system

non-fixed (movable) pumping system that can be quickly installed for unloading the liquid cargo of ships in the event of an emergency, such as failure of the pump system Note 1 to entry: The pumping system is generally composed of a mobile unloading pump unit (3.2) and a lifting device (3.3).

3.2 mobile unloading pump unit

combination of a pump (3.4), cargo hose (3.5), power connection device (3.6), and pump driver (3.7) PROOF/ÉPREUVE

ISO 25074:2026(en)

3.3 lifting device

combination of parts to lift out the mobile unloading pump unit from the cargo tank Note 1 to entry: The lifting device is composed of an assembly of supports (fixed or movable), winding device, lifting wire rope and pulley.

3.4 pump

mechanical device for moving liquids, including the inlet and outlet connections as well as, in general, its shaft ends [SOURCE: ISO 17769-1:2012, 2.1.1.1]

3.5 cargo hose

flexible hollow tube assembly used to connect the pump outlet to the cargo unloading pipeline of ships and floating production storage and offloading (FPSO) facilities

3.6 power connection device

device used to connect for supply power to pump (3.4)

3.7 pump driver

machine supplying mechanical energy to power the pump (3.4) Note 1 to entry: This can include, but is not limited to, electric motors and hydraulic motors. [SOURCE: ISO 17769-1:2012, 2.1.17.23, modified — deleted “turbines, pneumatic motors, and internal combustion engines” in the Note to entry.]

3.8 operation control module

module on the power connection device (3.6) that can control the operation of the pump (3.4) Note 1 to entry: The operation control module can be electronic or hydraulic. Note 2 to entry: The operation control module can control the pump speed.

4 Composition and interface

4.1 Composition

4.1.1 The mobile emergency unloading pump system is recommended to be of the type shown in Figure 1. The mobile unloading pump unit is recommended to be of the type shown in Figure 2. 4.1.2 The lifting device may be either a mobile type, see Figure 1 a), or a fixed type, see Figure 1 b). PROOF/ÉPREUVE

ISO 25074:2026(en) a) Mobile lifting device b) Fixed lifting device Key 1 mobile unloading pump unit 2 mobile lifting device 3 fixed lifting device 4 winding device 5 deck 6 cargo 7 cargo tank 8 entrance hatch Figure 1 — Mobile emergency unloading pump system PROOF/ÉPREUVE

ISO 25074:2026(en) Key 1 pump 2 cargo hose 3 power connection device 4 pump driver Figure 2 — Mobile unloading pump unit

4.2 Interface

The mobile emergency unloading pump system shall have at least the following interfaces related to ships and FPSO facilities:

a) power input interface; b) cargo output interface.

5 Design requirements

5.1 General

5.1.1 The electrical equipment of the mobile emergency unloading pump system shall conform to the safety and explosion-proof requirements of the ships and FPSO facilities. This electrical equipment shall also have an explosion-proof certificate.

5.1.2 The material of mechanical components shall be resistant to generating electrical sparks. 5.1.3 The components of the mobile emergency unloading pump system that come into contact with cargo shall be compatible with the characteristics of cargo on ships and FPSO facilities. 5.1.4 The power source for the mobile emergency unloading pump system shall be compatible with the power setup on ships and FPSO facilities.

...

Contents

  • Introduction
  • 1 Scope
  • 2 Normative references
  • 3 Terms and definitions
  • 4 Composition and interface
  • 4.1 Composition
  • 4.2 Interface
  • 5 Design requirements
  • 5.1 General
  • 5.2 Basic functions
  • 5.3 Performance requirementrequirements
  • 5.4 Material requirements
  • 5.5 Technical requirements
  • 6 Acceptance tests
  • 6.1 General requirements
  • 6.2 Mobile unloading pump unit test
  • 6.3 Lifting device test
  • 7 Identification, packaging, transportation, storage
  • 7.1 Identification
  • 7.2 Packaging
  • 7.3 Transportation
  • 7.4 Storage
  • Bibliography

Introduction

The mobile emergency unloading pump system is an emergency pumping arrangement of equipment that transports the liquid cargo in the tank of a ship to another tank in or outside of the ship. It is mainly used in chemical tankers, oil tankers and floating production storage and offloading (FPSO) facilities, and is the key element of emergency unloading equipment. At the time of publication of this document, the cargo pumps used in chemical tankers, FPSOsFPSO facilities and other vessels are arranged in the way of one tank with one pump. When the cargo pump in the cargo tank fails, the cargo cannot be unloaded in time, which has a significant impact on shipping, cargo safety, pollution prevention and other aspects of ship operations. In order to safely complete unloading, emergency measures should be provided to discharge the cargo in case of malfunction. This emergency unloading operation is a requirement explicitly stated in some regulations. Therefore For example, in considering the requirements for purchasingprocurement of cargo pumps that apply to ships and FPSOsFPSO facilities, it is clearly specified that one or two mobile unloading pumps per ship are required to be provided, so that cargo can be unloaded in case of failure of cargo pumps. This document provides requirements for manufacturers to develop mobile emergency unloading pumps, and also provides a product acceptance basis for users, classification societies, and other product certification agenciesthe main cargo pumps.

This document provides requirements for manufacturers to develop mobile emergency unloading pumps and also provides a product acceptance basis for users, classification societies and other product certification agencies.

DRAFT International Standard ISO/DIS 25074:2026(en)

Ships and marine technology- — Mobile emergency unloading pump system- — Technical requirements

1 Scope

This document specifies the technical requirements for the composition, interface, design and acceptance tests of the mobile emergency unloading pump system. This document also includes requirements for nameplate, packaging, transportation and storage.

This document is applicable to the mobile emergency unloading pump systems on ships such as oil tankers and chemical tankers, as well as floating production storage and offloading (FPSO) facilities.

2 Normative references

The following documents are referred to in the text in such a way that some or all of their content constitutes requirements of this document. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies. ISO 5199, Technical specifications for centrifugal pumps — Class II ISO 6802, Rubber or plastics hoses and hose assemblies — Hydraulic impulse test with flexing ISO 6803, Rubber or plastics hoses and hose assemblies — Hydraulic-pressure impulse test without flexing ISO 9906, Rotodynamic pumps — Hydraulic performance acceptance tests — Grades 1, 2 and 3 ISO 13709, Centrifugal pumps for petroleum, petrochemical and natural gas industries ISO 21940--11, Mechanical vibration — Rotor balancing — Part 11: Procedures and tolerances for rotors with rigid behaviour

3 Terms and definitions

For the purposes of this document, the terms and definitions given in ISO 9906, ISO 13709 and the following apply.

ISO and IEC maintain terminology databases for use in standardization at the following addresses:

  • — ISO Online browsing platform: available at https://www.iso.org/obp
  • — IEC Electropedia: available at https://www.electropedia.org/ 3.1 3.1 mobile emergency unloading pump system non-fixed (movable) pumping system that can be quickly installed for unloading the liquid cargo of ships in the event of an emergency, such as failure of the pump system Note 1 to entry: The pumping system is generally composed of a mobile unloading pump unit (3.2(3.2)) and a lifting device (3.3(3.3).).

ISO DIS/PRF 25074: 2025(E2026(en)

3.2 3.2 mobile unloading pump unit combination of a pump (3.4(3.4),), cargo hose (3.5(3.5),), power connection device (3.6(3.6),), and pump driver (3.7(3.7)) 3.3 3.3 lifting device combination of parts to lift out the mobile unloading pump unit from the cargo tank Note 1 to entry: The lifting device is composed of an assembly of supports (fixed or movable), winding device, lifting wire rope and pulley.

3.4 3.4 pump mechanical device for moving liquids, including the inlet and outlet connections as well as, in general, its shaft ends [SOURCE: ISO 17769-1:2012, 2.1.1.1] 3.5 3.5 cargo hose flexible hollow tube assembly used to connect the pump outlet to the cargo unloading pipeline of ships and floating production storage and offloading (FPSO) facilities.

3.6 3.6 power connection device device used to connect for supply power to pump (3.4(3.4)) 3.7 3.7 pump driver machine supplying mechanical energy to power the pump (3.4(3.4)) Note 1 to entry: This can include, but is not limited to, electric motors and hydraulic motors. [SOURCE: ISO 17769-1:2012, 2.1.17.23, modified — deleted "“turbines, pneumatic motors, and internal combustion engines"” in the Note to entry.] 3.8 3.8 operation control module module on the power connection device (3.6(3.6)) that can control the operation of the pump (3.4(3.4)) Note 1 to entry: The operation control module can be electronic or hydraulic. Note 2 to entry: The operation control module can control the pump speed.

4 Composition and interface

4.1 Composition

4.1.1 4.1.1 The mobile emergency unloading pump system is recommended to be of the type shown in Figure 1Figure 1.. The mobile unloading pump unit is recommended to be of the type shown in Figure 2Figure 2..

4.1.2 4.1.2 The lifting device may be either a mobile type, see Figure 1Figure 1 a), or a fixed type, see Figure 1Figure 1 b).

ISO/DISPRF 25074:2026(en) Inserted Cells

a) Mobile lifting device b) Fixed lifting device Key 1 mobile unloading pump unit 2 mobile lifting device 3 fixed lifting device 4 winding device 5 deck 6 cargo

ISO DIS/PRF 25074: 2025(E2026(en) 7 cargo tank 8 entrance hatch Figure 1 — Mobile emergency unloading pump system

Key 1 pump 2 cargo hose 3 power connection device 4 pump driver Figure 2 — Mobile unloading pump unit

4.2 Interface

The mobile emergency unloading pump system shall have at least the following interfaces related to ships and FPSO facilities:

ISO/DISPRF 25074:2026(en) a) a) Powerpower input interface.; b) b) Cargocargo output interface.

5 Design requirements

5.1 General

5.1.1 5.1.1 The electrical equipment of the mobile emergency unloading pump system shall conform to the safety and explosion-proof requirements of the ships and FPSOs and shallFPSO facilities. This electrical equipment shall also have an explosion-proof certificate.

5.1.2 5.1.2 The material of mechanical components shall be resistant to generating electrical sparks. 5.1.3 5.1.3 The components of the mobile emergency unloading pump system that come into contact with cargo shall be compatible with the characteristics of cargo on ships and FPSOsFPSO facilities. 5.1.4 5.1.4 The power source for the mobile emergency unloading pump system shall be compatible with the power setup on ships and FPSO facilities.

...